Overview and Scrutiny Commission, Monday 22 June 2026 at 7.00pm

Three Bridges Station Improvement Scheme

Noted Scrutiny 2 papers

AI summaryCrawley scrutiny commission notes Three Bridges Station Improvement Scheme report and will feed comments back to Cabinet, where a £7,970,968 budget rise and procurement delegations are recommended.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommission noted report, views to be sent via Comment sheet
Money£7,970,968Proposed revised scheme budget for Full Council approval
What happens nextConstruction contract award Autumn 2026Subject to Cabinet delegations and ECI process
Who it affectsThree Bridges station users, CrawleyPassengers, businesses, sustainable travel in Crawley

What was decided

The Commission noted the report on the Three Bridges Station Improvement Scheme.

The Commission requested that views expressed during debate be fed back to Cabinet through the Commission's Comment sheet.

Why

The scheme is identified as a priority in the Crawley Growth Programme and the Council's Corporate Plan 2025-2028, and is at a stage where procurement of a construction contractor has commenced. Report 4.2, 5.1

A revised cost estimate of £7,970,968 reflects inflationary pressures and the more detailed design work and railway assessment completed since 2018. Report 6.4, 6.5

A funding package has been put together from existing Crawley capital, Community Infrastructure Levy strategic infrastructure monies, and reallocated West Sussex County Council funding through the Crawley Growth Programme. Report 3.2, 3.3, 6.6, 6.7

What happens next

Cabinet is recommended to delegate authority to the Council Leader, in consultation with the relevant Cabinet Member, Head of Law and Governance and Head of Corporate Finance, to award the construction contract after the Early Contractor Involvement procurement. Report P6

Cabinet is recommended to ask Full Council to increase the Three Bridges Station budget to £7,970,968, funded from existing capital (£2,086,192), CIL Strategic Infrastructure Strand (£2,049,776) and Crawley Growth Programme reallocation (£3,835,000). Report P7, 6.8

Subject to satisfactory ECI outcomes and Cabinet approval, a construction contract is expected to be awarded in Autumn 2026, with mobilisation and a start on site in early 2027. Report 5.6

The money

  • £7,970,968 Proposed revised total scheme budget Report P7, 6.4, 6.8
  • £2,086,192 Already approved within the capital programme Report P7, 6.3
  • £2,049,776 Community Infrastructure Levy Strategic Infrastructure Strand Report P7, 6.6
  • £3,835,000 Reallocation of West Sussex County Council funding through the Crawley Growth Programme Report P7, 3.3, 6.7
  • £1,500,000 Original Cabinet allocation approved 29 June 2016 (FIN/385) Report 6.3
  • £393,759 Section 106 allocation agreed March 2018 (PES/280) Report 6.3
  • £89,000 Further S106 monies added March 2020 (PES/338) Report 6.3

Options considered

  • Chosen: Note the report and feedback views to Cabinet via the Commission's Comment sheet. The Commission's role is scrutiny, with the substantive decisions reserved for Cabinet and Full Council. Report 2.1, P2
  • Rejected: Recommend Cabinet delegate authority to award the construction contract following the ECI process. Decision sits with Cabinet; Commission only noted and commented. Report P6
  • Rejected: Recommend Full Council increase the scheme budget to £7,970,968. Decision sits with Cabinet and Full Council; Commission only noted and commented. Report P7

Implications

  • Financial: The revised £7,970,968 budget covers construction, landscaping, utilities, fees and a contingency aligned with HM Treasury guidelines, with optimism bias and risk allowances built in. Report 6.4, 6.5
  • Legal: The Council relies on the general power of competence (Section 1, Localism Act 2011) and Section 111 of the Local Government Act 1972 to deliver and procure the scheme, with procurement via a compliant framework route. Report 6.10, 6.13
  • Equalities: An Equality Impact Assessment has been completed and is appended; the Council must have due regard to the public sector equality duty under section 149 of the Equality Act 2010. Report 6.26, 6.27
  • Climate: Recommendations on funding and procurement do not have direct environmental impacts, but the scheme is expected to support modal shift to walking, cycling and public transport and improve air quality. Report 6.17, 6.18
  • Risk: Temporary disruption to customers during construction is to be managed through communication and phasing; design includes natural surveillance and lighting improvements. Report 6.20, 6.24
  • Staffing: Delivery will be managed within existing resources, including a dedicated project manager funded by the scheme, with support from relevant services and external consultants. Report 6.15

Who and where

  • Passengers and users of Three Bridges Station Report 4.4, 4.5, 6.22
  • Crawley businesses and inward investment prospects Report 4.5
  • Pedestrians, cyclists and public transport users in the station area Report 4.4, 4.5
  • Taxis and passenger pick-up and drop-off users Report 4.4, 4.5
  • Network Rail and Govia Thameslink Railway as scheme partners Report 4.1, 4.8

Timeline

  • 29 June 2016: Cabinet approved £1,500,000 allocation to the scheme (FIN/385) Report 6.3
  • March 2018: Cabinet agreed additional £393,759 of S106 resources (PES/280) Report 6.3
  • March 2020: Cabinet delegated authority to officers to undertake a procurement exercise and added £89,000 S106 (PES/338) Report 3.1, 6.3
  • 2014, 2017, 2019 and December 2022 to February 2023: Four rounds of public consultation on the scheme Report 4.3
  • 7 March 2023: CBC Planning Committee granted planning permission (CR/2022/0783/FUL) Report 4.6
  • March 2026: Leader of West Sussex County Council approved reallocation of £3,835,000 from Crawley Growth Programme (LDR04 (25/26)) and S106 agreement signed Report 3.3, 4.6, 6.7
  • 11 March 2026: Cabinet approved ringfencing of CIL Strategic Infrastructure Strand monies (PES/510) Report 3.2, 6.6
  • April 2026: Tender process commenced Report 5.6
  • May to August 2026: Intended progression through ECI stages Report 5.6
  • Autumn 2026: Anticipated award of construction contract Report 5.6
  • Early 2027: Anticipated mobilisation and start on site Report 5.6

Plain English for the jargon

  • ECI (Early Contractor Involvement): A two-stage procurement approach that brings the contractor in early to refine design, programme and cost before a full construction contract is committed.
  • CIL (Community Infrastructure Levy): A levy on new development that local authorities can use to fund infrastructure; the Strategic Infrastructure Strand is a portion ringfenced for larger projects.
  • NEC engineering contract: A standard form of construction contract developed by the Institution of Civil Engineers, widely used for engineering and infrastructure works.
  • Section 106 agreement: A legal agreement under section 106 of the Town and Country Planning Act 1990 used to secure planning obligations, typically contributions to infrastructure or affordable housing.
  • Station Change Management Procedure: Network Rail's process for authorising changes to station assets, including Form A (Asset Protection and Optimisation) approval.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back to the Cabinet through the Commission’s Comment sheet.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Overview and Scrutiny Commission

Recommendations

2.1To the Overview and Scrutiny Commission

That the Commission considers this report, and decide what comments, if any, it wishes to submit to the Cabinet.

2.2To the Cabinet

That the Cabinet is recommended to:

a) Note the progress made with the Three Bridges Station Improvement Scheme.

b) Delegate authority to the Leader of the Council in consultation with the relevant Cabinet Member, Head of Law & Governance and Head of Corporate Finance to approve the award of the construction contract following completion of an Early Contractor Involvement (ECI) procurement process, as set out in Section 5 of this report.

c) Delegate the negotiation, approval and completion of all relevant documentation including legal paperwork, following the awarding of the contract to the relevant Head of Service, Head of Law & Governance, Head of Corporate Finance, in consultation with the appropriate Cabinet Member. (Generic Delegations 2 & 3 will be used to enact this recommendation) d) Endorse and recommend to Full Council that Three Bridges Station budget be increased to £7,970,968. This will be funded by £2,086,192 already approved within the capital programme, £2,049,776 of Community Infrastructure Levy (CIL) Strategic Infrastructure Strand and £3,835,000 reallocation of West Sussex County Council funding through the Crawley Growth Programme.

Reasons for the recommendations

3.1To enable the progression of the Three Bridges Station Improvement scheme to construction and implementation, in accordance with the Council’s Procurement Code, secured through a compliant and risk-managed procurement process. In March 2020, Cabinet delegated authority to officers to undertake a procurement exercise for the scheme in accordance with the Council’s procurement code.

3.2To formally allocate CIL Strategic Infrastructure Strand monies to the Three Bridges Station Improvement Scheme to ensure sufficient funds enable delivery of the scheme. On 11 March 2026 Cabinet approved the ringfencing of CIL Strategic Infrastructure Strand monies for the scheme.

3.3To formally allocate from within the Crawley Growth Programme the capital budget required to enable fully funded delivery of the Three Bridges Station Improvement scheme. This follows an Executive Decision by the Leader of West Sussex County Council in March 2026 to allocate £3,835,000 of capital monies from within the Crawley Growth Programme to the scheme.

Background

4.1The Three Bridges Station Improvement Scheme is a flagship infrastructure project that has been developed over several years, led by Crawley Borough Council (CBC) in partnership with West Sussex County Council (WSCC), Govia Thameslink Railway (GTR) and Network Rail.

4.2Identified as a priority scheme within the Crawley Growth Programme and Crawley Borough Council’s Corporate Plan 2025-2028, the scheme will transform one of the region’s busiest transport hubs into a modern, sustainable and accessible gateway by upgrading the station forecourt, improving the transport interchange, creating a new “eastern” entrance, enhancing accessibility and promoting sustainable travel.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Three Bridges Station Improvement Scheme: EIA Appendix AAppendix 103 KB Download
PDF
Three Bridges Station Improvement SchemeReport 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 20 attended
JR
Councillor Justin RussellChair, present
TC
Councillor Tim ChartersVice-Chair, present
OA
Councillor Olu AdeniyiCommittee Member, present
MA
Councillor Marion AylingCommittee Member, present
SB
Councillor Shelly BushnellCommittee Member, present
GC
Councillor Grainne ConwayCommittee Member, present
MH
Councillor Mandie HainsCommittee Member, apologies
MH
Councillor Marilyn HiltonCommittee Member, present
KK
Councillor Kiran KhanCommittee Member, present
DR
Councillor Dominic RamsayCommittee Member, present
JT
Councillor James TidyCommittee Member, present
EW
Councillor Emma WhiteoakCommittee Member, present

All 20 on the meeting page

On this subject at Crawley

Search all
  1. Three Bridges Station Improvement SchemeThis decision
  2. Three Bridges Station Improvement SchemeApproved
  3. Planning Application CR/2022/0637/FUL - Lazer World, Spindle Way, Three BridgesAgreed
  4. Planning Application CR/2021/0791/FUL - Fairlawn House, Wassand Close, Three BridgesAgreed
  5. Planning Application CR/2025/0520/NCC - Crawley College, College Road, Three BridgesAgreed
  6. Planning Application CR/2024/0057/FUL - 76 Gales Drive, Three Bridges, CrawleyDecided

More from Crawley Overview and Scrutiny Commission

All decisions
MeetingDecisionOutcome
7 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate were fed back ... Noted Open
7 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open
7 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Commission noted the report and requested that the views expressed during the debate, were fed back... Noted Open