Crawley Borough Council
Cabinet, Wednesday 24 June 2026 at 7.00pm

Three Bridges Station Improvement Scheme

Approved Executive 2 papers

AI summaryCrawley Borough Council Cabinet agreed to delegate the award of the Three Bridges Station construction contract and recommended Full Council raise the scheme budget to £7,970,968, funded by existing capital, CIL monies and West Sussex County Council.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet delegates award of construction contract after ECI process
Money£7,970,968Total scheme budget recommended to Full Council
What happens nextContract award Autumn 2026Start on site anticipated early 2027
Who it affectsThree Bridges Station users, CrawleyRegion's transport hub and local businesses

What was decided

The Cabinet noted progress made with the Three Bridges Station Improvement Scheme. Report P5

The Cabinet delegated authority to the Leader, in consultation with relevant Cabinet Member, Head of Law and Governance and Head of Corporate Finance, to approve the construction contract award after the Early Contractor Involvement procurement process. Report P6

The Cabinet recommended that Full Council approve increasing the scheme budget to £7,970,968, funded by £2,086,192 of existing capital, £2,049,776 of CIL Strategic Infrastructure Strand monies and £3,835,000 reallocated from West Sussex County Council's Crawley Growth Programme. Report P7

Why

To enable progression of the scheme to construction and implementation, in line with the Council's Procurement Code, following the 2020 Cabinet delegation to officers to undertake a procurement exercise. Report 3.1, P54

To formally allocate CIL Strategic Infrastructure Strand monies to the scheme, building on the 11 March 2026 Cabinet decision to ringfence those funds. Report 3.2, P51

To formally allocate the capital budget required for fully funded delivery from the Crawley Growth Programme, following the Leader of West Sussex County Council's March 2026 Executive Decision to allocate £3,835,000. Report 3.3, P50

What happens next

Full Council to consider the recommendation to increase the scheme budget to £7,970,968 and approve the funding allocations. Report P7, 6.8

The two stage Early Contractor Involvement procurement process is to run between May and August 2026, with the tender having commenced in April 2026. Report 5.3, 5.6

Subject to satisfactory ECI outcomes and Cabinet approval, award of the construction contract is expected in Autumn 2026, with a start on site anticipated in early 2027. Report 5.6

The money

  • £7,970,968 Revised total scheme budget, covering construction, landscaping, utilities, professional fees and contingency Report 6.4, P7
  • £2,086,192 Already approved within the capital programme, comprising Local Growth Fund, CBC and WSCC capital and S106 allocations Report 6.3, P7
  • £2,049,776 Community Infrastructure Levy Strategic Infrastructure Strand allocation to the scheme Report 6.6, P7
  • £3,835,000 West Sussex County Council capital reallocation from the Crawley Growth Programme Report 6.7, P50, P7
  • £1,500,000 Original Cabinet allocation on 29 June 2016 for the scheme Report 6.3, P58
  • £393,759 Additional S106 allocation agreed by Cabinet in March 2018 Report 6.3, P56
  • £89,000 Further S106 monies added to the budget in March 2020 Report 6.3, P54

Options considered

  • Chosen: Two stage Early Contractor Involvement procurement via an established framework. Best practice for complex transport schemes, lowers risk and ensures compliance with the Procurement Code Report 5.2, 5.3, 5.4
  • Rejected: Open tender procurement process. Framework route described as a faster and lower risk alternative while remaining compliant and auditable Report 5.2

Implications

  • Legal: The Council relies on the general power of competence under Section 1 of the Localism Act 2011 and Section 111 of the Local Government Act 1972 to deliver and procure the scheme. Report 6.10
  • Legal: Procurement will be carried out in accordance with the Council's Procurement Code and public procurement legislation, using a compliant framework. Report 6.13
  • Equalities: An Equality Impact Assessment has been completed and is attached as appendix A, with the Council having due regard to its section 149 Equality Act 2010 duties. Report 6.26, 6.27
  • Climate: The scheme is expected to support modal shift to walking, cycling and public transport and contribute to reduced carbon emissions, although the funding and procurement decisions themselves have no direct environmental impact. Report 6.17, 6.18
  • Risk: Contingency and optimism bias allowances are factored in to address inflation, market volatility, Network Rail standards, accessibility regulations, sequencing and operational complexity. Report 6.5
  • Staffing: Delivery will be managed within existing resources, with a dedicated project manager funded by the scheme and officer support from economic development, finance, legal, procurement and the built environment. Report 6.15
  • Other: Temporary disruption to customers during construction will be managed through communication and phasing plans. Report 6.24

Who and where

  • Users of Three Bridges Station and local residents Report 4.4, 6.22
  • Crawley's 3,400+ businesses and inward investment prospects Report 4.5
  • West Sussex County Council as a partner and funder Report 4.1, 6.7, 6.11
  • Govia Thameslink Railway and Network Rail as station partners Report 4.1, 4.8
  • Taxi, bus, walking and cycling users of the interchange Report 4.4, 4.5

Timeline

  • 29 June 2016: Cabinet approved original £1,500,000 allocation to the scheme Report 6.3, P58
  • March 2018: Cabinet agreed additional £393,759 from S106 resources Report 6.3, P56
  • March 2020: Cabinet delegated authority to officers to undertake a procurement exercise and added £89,000 of S106 monies Report 3.1, 6.3, P54
  • 7 March 2023: CBC Planning Committee granted planning permission for the scheme Report 4.6, P53
  • March 2026: Leader of West Sussex County Council approved reallocation of £3,835,000 from the Crawley Growth Programme, and the S106 agreement was signed Report 3.3, 4.6, 6.7, P50
  • 11 March 2026: CBC Cabinet approved ringfencing of CIL Strategic Infrastructure Strand monies for the scheme Report 3.2, 6.6, P51
  • April 2026: Tender process commenced for the construction contractor Report 5.6
  • May to August 2026: Planned progression through the two stage Early Contractor Involvement stages Report 5.6
  • Autumn 2026: Anticipated award of the construction contract Report 5.6
  • Early 2027: Anticipated start on site Report 5.6

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development
  • ECI: Early Contractor Involvement, a two stage procurement approach bringing the contractor in early to refine design, programme and cost
  • S106: Section 106 agreement, a legal planning obligation between a developer and a local authority
  • NEC: New Engineering Contract, a standard form of construction contract
  • Crawley Growth Programme: Joint programme between Crawley Borough Council and West Sussex County Council funding major infrastructure in Crawley
  • EIA: Equality Impact Assessment, an analysis of the equality effects of a policy or decision
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED That the Cabinet: a) notes the progress made with the Three Bridges Station Improvement Scheme. b) delegates authority to the Leader of the Council in consultation with the relevant Cabinet Member, Head of Law & Governance and Head of Corporate Finance to approve the award of the construction contract following completion of an Early Contractor Involvement (ECI) procurement process, as set out in Section 5 of report PES/523 . c) delegates the negotiation, approval and completion of all relevant documentation including legal paperwork, following the awarding of the contract to the relevant Head of Service, Head of Law & Governance, Head of Corporate Finance, in consultation with the appropriate Cabinet Member. (Generic Delegations 2 & 3 will be used to enact this recommendation) That Full Council be recommended to approve that the Three Bridges Station budget be increased to £7,970,968. This will be funded by £2,086,192 already approved within the capital programme, £2,049,776 of Community Infrastructure Levy (CIL) Strategic Infrastructure Strand and £3,835,000 reallocation of West Sussex County Council funding through the Crawley Growth Programme. Reasons for the Recommendations To enable the progression of the Three Bridges Station Improvement scheme to construction and implementation, in accordance with the Council’s Procurement Code, secured through a compliant and risk-managed procurement process. In March 2020, Cabinet delegated authority to officers to undertake a procurement exercise for the scheme in accordance with the Council’s procurement code. To formally allocate CIL Strategic Infrastructure Strand monies to the Three Bridges Station Improvement Scheme to ensure sufficient funds enable delivery of the scheme. On 11 March 2026 Cabinet approved the ringfencing of CIL Strategic Infrastructure Strand monies for the scheme. To formally allocate from within the Crawley Growth Programme the capital budget required to enable fully funded delivery of the Three Bridges Station Improvement scheme. This follows an Executive Decision by the Leader of West Sussex County Council in March 2026 to allocate £3,835,000 of capital monies from within the Crawley Growth Programme to the scheme.
Word for word from the decision Crawley published for this meeting. Source: democracy.crawley.gov.uk

Follow this further

Built from Crawley's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1To the Overview and Scrutiny Commission

That the Commission considers this report, and decide what comments, if any, it wishes to submit to the Cabinet.

2.2To the Cabinet

That the Cabinet is recommended to:

a) Note the progress made with the Three Bridges Station Improvement Scheme.

b) Delegate authority to the Leader of the Council in consultation with the relevant Cabinet Member, Head of Law & Governance and Head of Corporate Finance to approve the award of the construction contract following completion of an Early Contractor Involvement (ECI) procurement process, as set out in Section 5 of this report.

c) Delegate the negotiation, approval and completion of all relevant documentation including legal paperwork, following the awarding of the contract to the relevant Head of Service, Head of Law & Governance, Head of Corporate Finance, in consultation with the appropriate Cabinet Member. (Generic Delegations 2 & 3 will be used to enact this recommendation) d) Endorse and recommend to Full Council that Three Bridges Station budget be increased to £7,970,968. This will be funded by £2,086,192 already approved within the capital programme, £2,049,776 of Community Infrastructure Levy (CIL) Strategic Infrastructure Strand and £3,835,000 reallocation of West Sussex County Council funding through the Crawley Growth Programme.

Reasons for the recommendations

3.1To enable the progression of the Three Bridges Station Improvement scheme to construction and implementation, in accordance with the Council’s Procurement Code, secured through a compliant and risk-managed procurement process. In March 2020, Cabinet delegated authority to officers to undertake a procurement exercise for the scheme in accordance with the Council’s procurement code.

3.2To formally allocate CIL Strategic Infrastructure Strand monies to the Three Bridges Station Improvement Scheme to ensure sufficient funds enable delivery of the scheme. On 11 March 2026 Cabinet approved the ringfencing of CIL Strategic Infrastructure Strand monies for the scheme.

3.3To formally allocate from within the Crawley Growth Programme the capital budget required to enable fully funded delivery of the Three Bridges Station Improvement scheme. This follows an Executive Decision by the Leader of West Sussex County Council in March 2026 to allocate £3,835,000 of capital monies from within the Crawley Growth Programme to the scheme.

Background

4.1The Three Bridges Station Improvement Scheme is a flagship infrastructure project that has been developed over several years, led by Crawley Borough Council (CBC) in partnership with West Sussex County Council (WSCC), Govia Thameslink Railway (GTR) and Network Rail.

4.2Identified as a priority scheme within the Crawley Growth Programme and Crawley Borough Council’s Corporate Plan 2025-2028, the scheme will transform one of the region’s busiest transport hubs into a modern, sustainable and accessible gateway by upgrading the station forecourt, improving the transport interchange, creating a new “eastern” entrance, enhancing accessibility and promoting sustainable travel.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Three Bridges Station Improvement Scheme: EIA Appendix AAppendix 103 KB Download
PDF
Three Bridges Station Improvement SchemeReport 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 24 attended
JC
Councillor Julian CharatanCommittee Member, present
NH
Councillor Nick HiltonCommittee Member, present
II
Councillor Ian IrvineCommittee Member, present
CM
Councillor Chris MullinsCommittee Member, present
SM
Councillor Sue MullinsCommittee Member, present
AN
Councillor Atif NawazCommittee Member, present
BN
Councillor Bob NoyceCommittee Member, present
JR
Councillor Justin RussellObserving, in attendance
JC
Jane CryerOfficer, in attendance
ID
Ian DukeOfficer, expected
CM
Carolin MartlewOfficer, in attendance
CP
Chris PageOfficer, in attendance

All 24 on the meeting page

On this subject at Crawley

Search all
  1. Three Bridges Station Improvement SchemeThis decision
  2. Three Bridges Station Improvement SchemeNoted
  3. Planning Application CR/2022/0637/FUL - Lazer World, Spindle Way, Three BridgesAgreed
  4. Planning Application CR/2021/0791/FUL - Fairlawn House, Wassand Close, Three BridgesAgreed
  5. Planning Application CR/2025/0520/NCC - Crawley College, College Road, Three BridgesAgreed
  6. Planning Application CR/2024/0057/FUL - 76 Gales Drive, Three Bridges, CrawleyDecided

More from Crawley Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 Financial Outturn 2025-2026 (Quarter 4)RESOLVED That the Cabinet: a) notes the outturn for the financial year 2025/26 as summarised in report FIN/745 . b) a... Approved Open
9 Sep 2026 Treasury Management Outturn 2025 – 2026RESOLVED That the Cabinet: a) notes the Treasury Management Outturn 2025/2026 report FIN/746 . b) approves the actual... Approved Open
9 Sep 2026 2026-2027 Budget Monitoring - Quarter 1RESOLVED That the Cabinet notes the projected outturn for the financial year 2026/27 as summarised in report FIN/747 ... Approved Open
9 Sep 2026 Crawley Homes Complaints Performance and Service Improvement Plan 2026RESOLVED That the Cabinet: a) approves the Crawley Homes Annual Complaints Performance and Service Improvement Plan R... Approved Open
9 Sep 2026 Crawley Homes Asset StrategyRESOLVED That the Cabinet: a) approves the Crawley Homes Asset Management Strategy ( appendix A of report CH/222 ) fo... Approved Open