Council AGREED the recommendations in the report to: 1. Note the work undertaken to date and activities planned by the Panel; and 2. Agree to extend the completion date of the Panel’s review, to report their recommendations to all Members in December 2019 and note the Panel’s increased membership as detailed in paragraph 3 of the report.
Word for word from the decision Croydon published for this meeting.Source: democracy.croydon.gov.uk
(1) Note the work undertaken to date and activities planned by the Panel.
(2) Agree to extend the completion date of the Panel’s review, to report their recommendations to all members in December 2019 and note the Panel’s increased membership as detailed in paragraph 3 of the report. 2. EXECUTIVE SUMMARY
2.1This report updates members of the Council on the work of the Governance Review Panel following its establishment in October 2018, summarising work of the Panel undertaken to date and outlining the emerging areas of focus for the review.
2.2The report also seeks approval from Council to extend the deadline for presenting the Panel’s recommendations no later than in December 2019 and to allocate additional resource to allow the Panel’s work to continue.
Background
3.1In October 2018, the Council resolved to establish an independently led, cross- party Governance Review Panel, which was duly set up and an independent chair appointed. The task for the Panel is to conduct a review of the Council’s governance structures and to make recommendations on options for improvements to the Council’s governance arrangements.
3.2Following consultation with both parties, the panel membership was extended to include one additional panel member from each party.
3.3The Panel is made up of eleven members as follows:
Independent Chair – Dame Moira Gibb Independent Member – Anne Smith 5 Majority Members – Councillors Hamida Ali, Sean Fitzsimons, Clive Fraser, Simon Hall, Joy Prince 4 Minority Members – Councillors Richard Chatterjee, Jason Perry, Helen Redfern, Scott Roche
4. THE WORK OF THE PANEL
4.1The first meeting of the Panel took place on the 29th October 2018. The Panel reviewed its terms of reference (appendix 1) and discussed the best approach to delivering them. In its early meetings the Panel received presentations providing an overview of the council’s governance structures and current localities work being undertaken across the borough.
4.2The Panel looked at governance reviews carried out by councils elsewhere and sought advice from organisations and academics involved in supporting such reviews. Panel Members subsequently developed a work programme based on the objectives specified in the terms of reference and informed by good practice from similar projects undertaken by other local authorities.
4.3In late November 2018 a project officer was appointed to support the work of the Panel. Work programme
4.4The Panel’s programme is made up of four stages (also shown in Table 1):
Work programme scoping, completed in February 2019 Evidence gathering and consideration, in progress and to complete in August 2019 Options and recommendations scoping, early discussions in progress and to complete in October 2019 Finalising the report, to complete in December 2019
Table 1. Key activities and timescales
Phase Timescales Status
Panel’s work programme scoping Nov-Feb 2019 Completed GOVERNANCE
In progress – on Evidence gathering and review Feb-Aug 2019 REVIEW
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.