Resolved
RESOLVED that the minutes of the meeting held on 4 November 2019 were agreed as an accurate record.
Croydon & Lewisham Street Lighting Joint Committee agreed this item on Thursday 15 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the minutes of the meeting held on 4 November 2019 were agreed as an accurate record.
Croydon & Lewisham Street Lighting Joint Committee
Meeting of held on Monday, 4 November 2019 at 6.30 pm in F11 - Town Hall, Katharine Street, Croydon, CR10 INX
MINUTES
Present: Councillor Kevin Bonavia (Chair); Councillor Stuart King (Vice-Chair); Councillors Sophie McGeevor and Paul Scott
PART A
1/19 Appointment of Chair and Vice-Chair
The Committee Clerk requested nominations for the positions of Chair and Vice-Chair for the municipal year 2019/20.
Councillor Stuart King nominated and Councillor Paul Scott seconded the nomination to appoint Councillor Kevin Bonavia as Chair for the remainder of the 2019/20 municipal year.
Councillor Kevin Bonavia nominated and Councillor Paul Scott seconded the nomination to appoint Councillor Stuart King as Vice-Chair for the remainder of the 2019/20 municipal year.
The Committee unanimously agreed both appointments.
2/19 Minutes of the previous meeting
RESOLVED that the minutes of the meeting held on 11 October 2018 be signed as a correct record.
3/19 Disclosure of Interest
There were no disclosures of a pecuniary interest not already registered.
4/19 Urgent Business (if any)
There were no items of urgent business.
5/19 Joint Street Lighting PFI Update The Director of Public Realm (Croydon Council) noted that the report outlined in detail the performance of the Service Provider for the PFI contract and gave an overview of key areas.
Members noted that the Core Investment Programme (Performance Standard 1) had been completed in 2016 with all street lights having been changed and, as such, the contract had moved into maintenance. In terms of planned maintenance, inspection and testing (Performance Standard 2) details were provided at paragraph 3.4 of the report and concentrated on cleaning, electrical testing and visual inspections. As the contractor had achieved the performance level of 99% no financial adjustments had occurred.
Performance Standard 3 (Operational responsiveness and reactive maintenance) was discussed and Members noted that there had been a low level of faults being reported and that emergency faults were being rectified within the required timeframe. However, it was recognised that not all non- emergency faults were being attended in time and that a financial adjustment had been applied.
The Director of Public Realm stated that Performance Standard 4 (Contract management and customer interface) required 95% of all phone calls to be answered within 25 seconds by a person had been met. Whilst difficulties had been experienced, Skanksa had not gone below the contract threshold and the contract managers at the councils had worked with the provider to identify difficulties.
In terms of working practices (Performance Standard 6), the Director of Public Realm noted that no penalties had been levied as it had been found that the provider was performing well in terms of health and safety issues for its own staff and that site conditions were being monitored and being kept in a safe condition for residents.
The Director of Public Realm highlighted section five of the report, financial implications, which stated that under the Co-Operation Agreement the Committee was required to submit final estimates for the contract to each council no later than 30 November and that the final budget was to submitted annually by 15 March. It was noted that the budget for the contract and committee was split 64% (Croydon) and 36% (Lewisham) as per a formula.
Councillor Sophie McGeevor arrived at 6.51pm.
In response to Member questions the Director of Public Realm stated that if there were concerns regarding light levels then this could be raised with the contractor and if levels were below the required standard the contractor would be responsible and changes could be made to ensure the lighting level was sufficient.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meetingMinutes | 79 KB | DownloadRead as text |
Follow Croydon & Lewisham Street Lighting Joint Committee at Croydon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Nov 2025 | Appointment of Chair and Vice-ChairTo appoint Councillor Scott Roche as the Chair of the Committee for the 2025-26 Municipal Year. The Chair, Councillor... | Decided | Open |
| 4 Nov 2025 | Minutes of the previous meetingThat the minutes of the meeting held on 10 December 2024 be agreed as a correct record of the meeting. | Agreed | Open |
| 4 Nov 2025 | Joint Street Lighting PFI UpdateRESOLVED to: Note the performance of Service Provider in respect of the street lighting PFI for September 2024 - Augu... | Noted | Open |
| 19 Oct 2023 | Appointment of Chair and Vice-ChairThat Councillor Scott Roche be appointed as Chair of the Committee for the 2023-24 Municipal Year. The Chair, Council... | Decided | Open |
| 19 Oct 2023 | Minutes of the previous meetingRESOLVED that the minutes of the meeting held on 13 October 2022 be agreed as a correct record of the meeting. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.