RESOLVED : To 1.1 Note the General Fund is projecting a net overspend of £10.547m as at Month 5, or £3.6m assuming the budgeted contribution to reserves is moved from opportunities into the projected outturn. Service directorates are indicating a £25.316m overspend with a £14.769m underspend corporately. 1.2 Note that a further number of risks and compensating opportunities may materialise which would see the forecast year-end variance change. These indicate a net opportunity of £1.838m (risks £10.769m and opportunities of £12.607m) and are reported within Section 3 of this report. Should all these risks materialise, and none of the mitigations be effective, the Council is forecast to overspend by £21.316m. However, if none of the risks materialise and all the opportunities are delivered, the Council will underspend by £2.060m. 1.3 Note the further actions being taken, through development of the Deficit Recovery plan, to mitigate the projected overspend with a view to eliminating it by the end of the financial year. Further details are in paragraph 2.15. 1.4 To approve the non-delivery of the MTFS savings as indicated within Table 2b. 1.5 Note the Housing Revenue Account (HRA) is projecting an end of year position of a £3.210m overspend, mainly due to inflation in energy costs. 1.6 Note the Capital Programme spend to date for the General Fund of £7.644m (against a budget of £112.069m) with a projected forecast underspend of £7.715m for the end of the year. 1.7 Note the Housing Revenue Account Capital Programme spend to date of £4.978m (against a budget of £22.083m), with a projected forecast underspend of £3.050m for the end of the year. 1.8 Note, the above figures are predicated on forecasts from Month 5 to the year end and therefore could be subject to change as forecasts are made based on the best available information at this time. 1.9 Note, the Council continues to operate a Spend Control Panel to ensure that tight financial control and assurance oversight are maintained A new financial management culture is being implemented across the organisation through increased scrutiny, such as the Assurance meetings, improved communication and budget manager training from CIPFA.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

REPORT TO: Cabinet 12th October 2022

SUBJECT: Financial Performance Report – Month 5 (August 2022)

Jane West, Corporate Director of Resources (Section LEAD OFFICER: 151) Councillor Jason Cummings Cabinet Member for Finance CABINET MEMBER: SUMMARY OF REPORT: This report provides the Council’s annual forecast as at Month 5 (August 2022) for the Council’s General Fund (GF), Housing Revenue Account (HRA) and the Capital Programme (CP). The report forms part of the Council’s financial management process for publicly reporting financial performance against its budgets on a monthly basis.

FINANCIAL IMPACT

Forecast Forecast Movement Month 5 Month 4

£m £m £m

General Fund over/(underspend) 10.5 9.5 1.0

Housing Revenue Account 3.2 3.1 0.1 over/(underspend)

Forecast Original Actual to Forecast Variance Approved Date as at for year for year Budget 31/08/22 end end 2022/2023 2022/2023 2022/2023 £m £m £m £m Capital Programme 134.152 12.622 123.387 (10.765)

The Month 5 position for the General Fund shows a worsening of £1.064m in the forecast outturn for 2022/23 since Month 4, mainly due to the Housing service seeing an increase in demand for temporary accommodation and rising rental costs.

1 The Month 5 end of year projection for the General Fund is indicating a net overspend of £10.547m against the budget.

There are a further set of risks and opportunities, which indicate a net opportunity of £1.838m (risks £10.769m and opportunities of £12.607m) most of which are not yet sufficiently developed to be included in the outturn forecast. Should all these risks materialise, and none of the mitigations be effective, the Council could overspend by £21.316m. However, if none of the risks materialise and all the opportunities are delivered, the Council could underspend by £2.060m.

It should be noted that the overall financial position of the Council suggests it is highly unlikely that it will be possible to use the existing £6.887m corporate budget to top up the Council’s reserves in 2022/23. This budget is currently included as an opportunity in this month’s report but from next month will be moved into the end of year projected outturn. Had this been actioned this month, the projected overspend this month would have been £3.6m. This is reflected at 2.18 which sets out the current projection for reserves at the end of the year.

Work is continuing to look at measures to mitigate the forecast overspend and avert any further adverse impacts on the forecast. Early mitigating actions are reported as opportunities in this report. The impact of the in-year position is also being considered as part of the planning for 2023/24.

Paragraph 2.15 includes a Deficit Recovery Plan which sets out the actions the Council is taking to mitigate the projected overspend, which together with minimising risks and maximising opportunities is designed to eliminate the overspend by the end of the financial year.

Section 3 details these risks and the risk mitigations that have been identified at this stage.

The Housing Revenue Account is forecasting a £3.210m overspend variance against budget at the end of the year, an adverse movement by £0.063m mainly due to inflation in energy costs.

The Capital Programme has spent £12.622m against a £134.152m budget in the fifth month. The end of year position is forecast to be an underspend of £10.765m.

2 The Executive Mayor in Cabinet is recommended to:

1.1Note the General Fund is projecting a net overspend of £10.547m as at Month 5, or £3.6m assuming the budgeted contribution to reserves is moved from opportunities into the projected outturn. Service directorates are indicating a £25.316m overspend with a £14.769m underspend corporately.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Period 5 Financial Performance ReportReport 570 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, apologies
SR
Councillor Scott RocheCommittee Member, present
AS
Councillor Andy StranackCommittee Member, present
CS
Colin SweeneySecretary, expected
JW
Jane WestOfficer, expected
KK
Katherine KerswellOfficer, expected

All 22 on the meeting page

On this subject at Croydon

Search all
  1. Period 5 Financial Performance ReportThis decision
  2. 2026-27 Period 3 Financial Performance ReportAgreed
  3. 2025-26 Period 9 Financial PerformanceAgreed
  4. 2025-26 Period 6 Financial Performance ReportAgreed
  5. 2025-26 Period 5 Financial Performance ReportAgreed
  6. 2025-26 Period 3 Financial Performance ReportAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies