Report to: South London Waste Partnership (SLWP) Joint Waste Committee Date: 7th December 2023 Author(s): Francesco Grieco, Head of Finance & Business Intelligence Report title: South London Waste Partnership Budget Update 2023/24 – Period 6 Update
SUMMARY 1.1 This paper provides an outturn position on the Partnership’s budget for the current financial year. At month 6 of the financial year 2023/24, that being 30th September 2023, the forecast outturn is an underspend of £1,375 against the ‘revised’ budget.
Revised Budget Forecast Variance TOTAL £1,253,755 £1,252,380 -£1,375
BACKGROUND 2.1 The Partnership sets its budget each year for the forthcoming financial year. Spend against budget is monitored monthly in order to respond to pressures and to allow budgets to be flexed where appropriate. The budget for 2023/24 was approved at the January 2023 Joint Committee and, following a budget challenge, a revised budget was agreed later in the year. Appendix 1 contains both the approved and the revised budgets, along with an individual borough forecasts against the revised budget. The financial commentary that follows tracks spend year to date against the lower revised budget.
FINANCIAL POSITION COMMENTARY – 2023/24 3.1 Core Budget 3.2 The Core Partnership Activity budget covers staff salaries, IT, HR, the document management system, and finance support, as well as ad hoc legal and technical advisor support. The core staff activities include contract management, commissioning, infrastructure development work, and finance administration. 3.3 The budget for the ‘Core Partnership Team Activity’ is currently forecasting a total underspend of £6,376 which is mainly attributed to an underspend in staffing costs. At period 6 there is a confirmed overspend in relation to document management due to inflation assumptions.
Budget Forecast Variance Core Partnership Team Activity £850,005 £843,629 £-6,376 Advisors and Corporate Support £65,608 £65,543 -£65 Core Staff Resources £764,397 £756,211 -£8,186 Document Management £20,000 £21,876 £1,876 1 3.4 Communications and Improvement Projects
3.5Green waste and food waste campaigns – these have now passed through the internal approvals process at borough officer level and work has commenced. At period 6 the food and green waste projects are forecasted to be delivered on budget.
3.6Intelligence gathering - prior to any spend on intelligence gathering projects, it has been agreed that an approvals process will be undertaken in all four boroughs. At period 6 it is anticipated that the intelligence gathering will not be progressed and it will be presented as an underspend.
3.7Resident engagement - It is anticipated that the resident engagement projects will be progressed and will be delivered on budget. Budget Forecast Variance Communications and Improvements Projects £141,250 £141,250 £0 Resident Engagement £10,000 £10,000 £0 Intelligence Gathering £65,000 £65,000 £0 Spend to save green waste campaign £10,000 £10,000 £0 Spend to save food waste campaign £56,250 £26,250 £0
3.8Commissioning Projects
3.9Recyclates Treatment Contract – From the 1st April 2025 the receipt treatment and recycling of kerbside collected recyclates will be a standalone service managed separately from the collections contract. Work to commission the new recyclates treatment contract/s is underway and will continue into the financial year 2024/25. Project costs for 2023/24 are included within the commissioning category and at period 6 current financial year activities are projected to be delivered within budget.
3.10HRRC Services - Work to secure the continued delivery of the HRRC Services contract via an extension with variation is progressing through the approvals processes in each of the boroughs and at period 6 this project is projected to be delivered within budget.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Approved Budget and Revised Budget /20Appendix 1 | 203 KB | Download |
PDF |
South London Waste Partnership Budget Update 2023/24: Period 6 UpdateReport | 164 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Croydon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Dec 2023 | Minutes of the Previous MeetingThat minutes of the meeting held on 15 June 2023 were agreed and to be signed as an accurate record. | Agreed | Open |
| 7 Dec 2023 | Recommended budget 2024-25to approve the recommended budget 2024/25 as set out in the report. | Approved | Open |
| 7 Dec 2023 | Communications and Engagement Updateto note the contents of the report. | Noted | Open |
| 4 Feb 2020 | Budget Update 2019/20To note the contents of the report. | Noted | Open |
| 4 Feb 2020 | Budget 2020/21To agree the final budget for the core activities of the Partnership as set out at paragraph 2.3 of the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.