2024-25 Period 3 Financial Performance Report

Noted Executive 1 paper

Cabinet noted this item on Wednesday 25 September 2024. Below is the council's own wording, with the papers it was decided on.

Item199/24

Resolved

Cabinet RESOLVED ; 2.1 to note the General Fund revenue budget outturn is forecast to overspend at financial year end by £23.9m at Period 3, after the budgeted utilisation of £38m capitalisation directions requested from the Ministry of Housing, Communities and Local Government (MHCLG), utilisation of the £5.0m risk contingency budget and utilisation of £13.0m corporate earmarked reserves. 2.2 to note that all service directorates have been asked to reduce their net expenditure so that the annual budget can be balanced at the end of the year. It should not be underestimated what a challenge this will be against the background of increased demand pressures which are continuing to build across local government and increased market prices. Forecast overspend pressures are also demonstrated in the Month 2 and Quarter 1 reports published by other London councils. However, the Council will still strive to bring its 2024-25 budget into balance including through the in-year Financial Recovery Plan as set out from para 4.8. 2.3 to approve budget inter-directorate virements from Corporate to service directorates for non-pay inflation (£15.694m) as set out in the table in paragraph 4.102. 2.4 to note the progress in Medium Term Financial Strategy (MTFS) savings achievement of £20.8m (75.1%) against the total savings target of £27.7m as set out in paragraph 4.124. 2.5 to note the work that is continuing on the Council’s Transformation Programme as set out from paragraph 4.122. 2.6 to note the Housing Revenue Account (HRA) revenue budget outturn is forecast to overspend by £2.0m. 2.7 to approve the budget changes in 2024-25 General Fund capital programme budgets totalling a net increase of £8.5m, which includes adoption of Reconnecting Croydon (£4.755m funded by government grant) and the Oracle Improvement Programme (£4.419m funded by earmarked reserves) as set out in para 4.152. 2.8 to note the General Fund capital programme 2024-25 breakeven forecast against the revised capital budget of £118.5m. 2.9 to note the HRA capital programme 2024-25 forecast underspend of £4.9m against the capital budget of £57.2m. 2.10 to note the Council’s historic borrowing and subsequent debt burden continues to be critical to the non-sustainability of the Council’s revenue budget. Dialogue with MHCLG continues around options of further financial support from Government in regard to the level of structural indebtedness to ensure the Council can deliver sustainable Local Government services. 2.11 to note that the Council continues to operate Spend Control Panels to ensure that tight financial control and assurance oversight are maintained. 2.12 to note that current forecasts are based on the best available information at the time and will be subject to review and change during the financial year.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

LONDON BOROUGH OF CROYDON REPORT: CABINET

DATE OF DECISION 25 September 2024

REPORT TITLE: 2024-25 Period 3 Financial Performance Report

CORPORATE Jane West DIRECTOR Corporate Director of Resources (Section 151 Officer)

LEAD OFFICER: Allister Bannin, Director of Finance (Deputy S151)

LEAD MEMBER: Cllr Jason Cummings, Cabinet Member for Finance

KEY DECISION? Yes Reason: Decision incurs expenditure, or makes savings, of 0424F more than £1,000,000 or such smaller sum which the decision-taker considers is significant having regard to the Council’s budget for the service or function to which the decision relates; AND Decision significantly impacts on communities living or working in an area comprising two or more Wards.

CONTAINS EXEMPT No Public INFORMATION? Grounds for the exemption: N/A

WARDS AFFECTED: All

1 SUMMARY OF REPORT

1.1This report provides the Council’s financial performance as at Period 3 (June 2024) for the General Fund, Housing Revenue Account (HRA) and the Capital Programme. The report forms part of the Council’s financial management process for publicly reporting financial performance on a monthly basis.

Financial Performance Summary Table

Financial Performance Area 2024-25 2024-25 2024-25 2024-25 Revised Forecast Forecast Forecast Budget Variance Variance (£m) (£m) (£m) (%) Revenue Forecast (General Fund) 361.3 385.2 23.9 6.6% Revenue Forecast (Housing Revenue Account) - 2.0 2.0 N/A Capital Forecast (General Fund) 118.5 118.5 - - Capital Forecast (Housing Revenue Account) 57.2 52.3 (4.9) (8.6%) 2 RECOMMENDATIONS For the reasons set out in the report, Cabinet is recommended:

2.1to note the General Fund revenue budget outturn is forecast to overspend at financial year end by £23.9m at Period 3, after the budgeted utilisation of £38m capitalisation directions requested from the Ministry of Housing, Communities and Local Government (MHCLG), utilisation of the £5.0m risk contingency budget and utilisation of £13.0m corporate earmarked reserves.

2.2to note that all service directorates have been asked to reduce their net expenditure so that the annual budget can be balanced at the end of the year. It should not be underestimated what a challenge this will be against the background of increased demand pressures which are continuing to build across local government and increased market prices. Forecast overspend pressures are also demonstrated in the Month 2 and Quarter 1 reports published by other London councils. However, the Council will still strive to bring its 2024-25 budget into balance including through the in-year Financial Recovery Plan as set out from para 4.8.

2.3to approve budget inter-directorate virements from Corporate to service directorates for non-pay inflation (£15.694m) as set out in the table in paragraph 4.102.

2.4to note the progress in Medium Term Financial Strategy (MTFS) savings achievement of £20.8m (75.1%) against the total savings target of £27.7m as set out in paragraph 4.124.

2.5to note the work that is continuing on the Council’s Transformation Programme as set out from paragraph 4.122.

2.6to note the Housing Revenue Account (HRA) revenue budget outturn is forecast to overspend by £2.0m.

2.7to approve the budget changes in 2024-25 General Fund capital programme budgets totalling a net increase of £8.5m, which includes adoption of Reconnecting Croydon (£4.755m funded by government grant) and the Oracle Improvement Programme (£4.419m funded by earmarked reserves) as set out in para 4.152.

2.8to note the General Fund capital programme 2024-25 breakeven forecast against the revised capital budget of £118.5m. 2.9 to note the HRA capital programme 2024-25 forecast underspend of £4.9m against the capital budget of £57.2m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2024-25 Period 3 Financial Performance ReportReport 455 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, apologies
AS
Councillor Andy StranackCommittee Member, present
JW
Jane WestOfficer, expected
KK
Katherine KerswellOfficer, expected
PM
Peter MitchellOfficer, expected

All 22 on the meeting page

On this subject at Croydon

Search all
  1. 2024-25 Period 3 Financial Performance ReportThis decision
  2. 2026-27 Period 3 Financial Performance ReportAgreed
  3. 2025-26 Period 9 Financial PerformanceAgreed
  4. 2025-26 Period 6 Financial Performance ReportAgreed
  5. 2025-26 Period 5 Financial Performance ReportAgreed
  6. 2025-26 Period 3 Financial Performance ReportAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies