Croydon Pensions Administration Team Key Performance Indicators and Pensions Dashboard Reporting for the Period June to August 2025

Noted Finance 2 papers

AI summaryCroydon Pension Board noted the pension administration team's key performance indicators for June to August 2025, with 100% of active annual benefit statements issued before the 31 August deadline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPerformance for June to August 2025 recorded
MoneyNot stated
What happens nextPensions Dashboard reportingTo start when the Dashboard goes live to the public
Who it affectsLGPS members in CroydonActive, deferred and pensioner scheme members

What was decided

The Board noted the key performance indicators and performance against them set out in Appendix A to the report. Report 2.1

Why

Good governance of the Local Government Pension Scheme requires the Board to be informed of administration performance and to monitor it against legal deadlines and team targets. Report 3.1

The report has been developed using guidance published by CIPFA on administration of the Local Government Pension Scheme. Report 3.1

What happens next

The team will continue Blitz days to reduce outstanding leavers and prepare records for the Triennial Valuation and the McCloud remedy. Report 4.4

Plans have been put in place to reduce the number of deferred benefit annual benefit statements not produced next year. Report 4.6

Once the Pensions Dashboard goes live, the team will report on matches, possible matches and resolution activity. Report 4.13, 4.16

Options considered

  • Rejected: No alternative options considered. Not applicable for a noting report Report 5.1

Implications

  • Financial: There are no direct financial implications arising from the report. Report P22
  • Legal: Burges Salmon LLP, legal advisor to the Pension Fund, notes there are no direct legal implications from the recommendations. Report P23
  • Equalities: No adverse equality impacts have been identified; support is in place for members at risk of digital exclusion, including older members and those with disabilities. Report P27, P28, P29
  • Staffing: There are no direct workforce impacts, although the pension scheme is noted as an important staff benefit for recruitment and retention. Report 7.4, P31

Who and where

  • Local Government Pension Scheme members administered by Croydon Report 4.1, P27
  • Active members, with 100% of annual benefit statements generated before the deadline Report 4.6
  • Deferred benefit members, with 96.21% of annual benefit statements generated and discretion applied to 52 active and 12 deferred statements for the McCloud remedy Report 4.6, 4.8
  • Members in scope for the McCloud remedy and the Triennial Valuation Report 4.4, 4.7

Timeline

  • 31 October 2024: New member self service portal went live Report 4.10
  • June 2025 to August 2025: Reporting period covered by the key performance indicators Report 4.1
  • 31 August 2025: Statutory deadline met for annual benefit statements Report 4.6
  • 31 October 2025: Heywoods turned on the connection to the Pensions Dashboard on the deadline Report 4.15
  • Next annual cycle: Plans in place to reduce the number of deferred benefit annual benefit statements not produced Report 4.6

Plain English for the jargon

  • LGPS: Local Government Pension Scheme
  • KPI: Key Performance Indicator
  • ABS: Annual Benefit Statement
  • McCloud remedy: Changes to public sector pension schemes following a court ruling on age discrimination
  • ISP: Integrated Service Provider, in this case Heywoods, connecting the fund to the Pensions Dashboard
  • CIPFA: Chartered Institute of Public Finance and Accountancy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48/25

Resolved

· The Board was asked to note the key performance indicators and the performance against these indicators set out in Appendix A to this report.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Pension Board

Recommendations

2.1The Committee is asked to note the Key Performance Indicators and the performance against these indicators set out in Appendix A to this report.

Reasons for recommendations

3.1To ensure good governance of the scheme the Committee should be informed of the performance of the administration of the Local Government Pension Scheme and monitor performance against legal deadlines and team performance targets. This report has been developed using guidance published by CIPFA (Administration in the LGPS: A Guide for Pension Authorities). 4. BACKGROUND AND DETAILS

4.1This report covers the period June 2025 to August 2025 and covers legal deadlines, team performance targets, case levels and take up of the member self-service portal. The indicators and performance against these are detailed in Appendix A of this report. This report now also includes information regarding the Pensions Dashboard.

4.2The team have generally met targets for most indicators during this period with only a few cases missing legal and team targets for each category, with the exception of deferred benefit calculations which still fall below expected levels.

4.3Deferred Benefit calculations have shown a significant decrease in the average number of days to process in this period.

4.4The team have continued with Blitz days targeting cases in preparation for the Triennial Valuation to decrease the number of outstanding leavers and to prepare records for the McCloud remedy.

4.5The team have completed updating records as part of the End Of Year process.

4.6Annual Benefit Statements (ABS) were generated and released on the online portal before the statutory deadline of 31 August. 100% of active ABS were generated, 96.21% of deferred benefit ABS were generated, this is a big increase on last year’s production of deferred benefit ABS. Plans have been put in place to reduce the number of deferred benefit ABS that are not produced next year.

4.7The team have prepared the records that are in scope for McCloud for the Annual Benefit Statements. The relevant reports have been run, and data cleansing has been completed to prepare the records for the McCloud requirements on the ABS.

4.8The team has implemented the plan laid out in the July 2025 Implementation of the McCloud Remedy Board report. We have exercised the discretion to delay the publishing of the McCloud remedy service information for the members detailed in the report. There were 52 active and 12 Deferred Benefit Annual Benefit Statements which had the discretion applied.

4.9The initial errors on the Triennial Valuation report have been cleared and the data sent to the Hymans Robertson.

4.10The new Member self-service portal has been active since 31 October 2024. Members registering for the new portal have been rising steadily. The team has implemented a plan to encourage more members to sign up to the new portal as part of the ABS release. Since ABS release we have seen an increase in sign up to the member portal of 3,548 members.

4.11THE PENSIONS DASHBOARD

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Croydon Pensions Administration Team Performance Report, June 2025 to August 2025. /25Appendix A 299 KB Download
PDF
Croydon Pensions Administration Team Key Performance Indicators and Pensions Dashboard Reporting for the Period June to August 2025Report 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 11 attended
MB
Councillor Margaret BirdCommittee Member, present
RE
Richard Elliott Employer RepresentativeCo-Optee, present
TF
Teresa Fritz Employee RepresentativeCo-Optee, present
AP
Ava Payne Employee RepresentativeCo-Optee, present, as expected, virtual
DW
David Whickman Employee RepresentativeCo-Optee, present
JW
Jane WestOfficer, apologies
AF
Alison FisherOfficer, expected
MH
Matthew HallettOfficer, expected
GP
Gillian PhillipOfficer, expected
IT
Ian TalbotOfficer, expected
LS
Liam SemugabiSecretary, expected

On this subject at Croydon

Search all
  1. Croydon Pensions Administration Team Key Performance Indicators and Pensions Dashboard Reporting for the Period June to August 2025This decision
  2. Croydon Pensions Administration Report for the Period December 2025 to May 2026Noted
  3. Croydon Pensions Administration Team Key Performance Indicators and Pensions Dashboard Reporting for the Period February 2026 to April 2026Noted
  4. Croydon Pensions Administration Team Key Performance Indicators and Pensions Dashboard Reporting for the Period September to November 2025Noted
  5. Croydon Pensions Administration Team Key Performance Indicators and Pensions Dashboard Reporting for the Period August 2025 to October 2025Noted
  6. Croydon Pensions Administration Team Key Performance Indicators for the Period May 2025 to July 2025Noted

More from Croydon Pension Board

All decisions
MeetingDecisionOutcome
9 Jul 2026 Pension Board Annual Report 2025/26The Pension Board reviewed and commented on the contents of the draft Pension Board Annual Report for 2025/26. The Pe... Agreed Open
9 Jul 2026 Croydon Pensions Administration Report for the Period December 2025 to May 2026The Pension Board noted the Key Performance Indicators and the performance against those indicators set out in Append... Noted Open
9 Jul 2026 Update on "Fit for the future" ProposalsThe Pension Board noted the contents of the report. ACTIONS: Future reports to include a detailed implementation time... Noted Open
9 Jul 2026 Knowledge and Skills Policy Review and Training PlanThe Pension Board reviewed and commented on the revised draft Pension Fund Knowledge and Skills Policy. The Pension B... Decided Open
9 Jul 2026 Pension Fund Medium Term Business Plan 2026/29The Pension Board noted the Medium-Term Business Plan 2026/29. ACTION: Officers to consider opportunities for earlier... Noted Open