25/03178/FUL - The Chapel, 29 Chaucer Gardens, Coulsdon

Decided Planning 2 papers

AI summaryCroydon Planning Committee has granted permission to convert The Chapel at 29 Chaucer Gardens, Coulsdon into 9 homes and a café/workspace, subject to a £15000 travel contribution and a legal agreement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFull planning permission for conversion
Money£15000Section 106 travel contribution
What happens nextS.106 within 3 monthsOr delegated refusal if not completed
Who it affectsCane Hill, CoulsdonLocally listed Chapel building

What was decided

Grant planning permission for the conversion of The Chapel into 9 flats and Class E commercial space including a café and co-workspace, retaining the bus drivers' toilet and BBC transmission equipment. Report 2.1, 3.1, P22

Secure a Section 106 agreement covering a £15000 sustainable travel contribution and the perpetual retention of the bus drivers' toilet. Report 2.1, P2, P3

Impose 23 planning conditions covering time limit, construction, materials, biodiversity, fire safety, parking, public art, noise, hours of use, accessibility, and bat mitigation. Report 2.4, P8, P10, P12, P14, P22

Why

The scheme contributes 9 new homes, including family-sized units, towards the borough's housing target and brings a locally listed, vacant chapel back into use. Report 4.0, P38, 8.6, 8.7, 8.8, 8.12, 8.54

Officers found the design preserves internal features and uses materials in keeping with the heritage asset, with detailed conditions to protect historic fabric. Report 8.17, 8.19, 8.20

Impacts on neighbours, parking, biodiversity, flooding, energy and fire safety were judged acceptable subject to conditions and the S.106 agreement. Report 8.33, 8.35, 8.41, 8.42, 8.52, 8.53, P38

What happens next

The Director of Planning and Sustainable Regeneration is delegated authority to negotiate and complete the Section 106 agreement within three months, or to refuse if it is not completed. Report 2.2, 2.3

The Director is also delegated to issue the planning permission and any further conditions or informatives considered necessary. Report 2.4, P15, P17

A range of pre-commencement, pre-occupation and compliance conditions must be discharged, including a Construction Logistics Plan, materials, landscaping, biodiversity, bat licensing, cycle and refuse stores, lighting, car park management, public art, noise and a ground floor management plan. Report P10, P12, P14

The money

  • £15000 S.106 financial contribution towards sustainable travel improvements Report 2.1, P2
  • £1500 per dwelling Contribution towards sustainable transport infrastructure such as EVCPs and cycling initiatives Report 8.42

Options considered

  • Chosen: Grant planning permission subject to S.106 and conditions. Recommended by officers; acceptable in principle, design, amenity, transport, heritage, biodiversity, energy, flood and fire terms. Report 2.1, 4.0, P38, 8.54

Implications

  • Legal: A Section 106 legal agreement is required to secure the financial contribution and the retention of the bus drivers' toilet; refusal is delegated if not completed within three months. Report 2.1, 2.3, P2, P3
  • Financial: The development is liable for the Community Infrastructure Levy (CIL). Report 8.55, P17
  • Equalities: Equalities and human rights duties have been considered in the assessment. Report 8.56
  • Climate: Water use is limited to 110L per head per day; sustainable transport contributions and EV-ready parking are secured; sustainable drainage improvements including green roofs and permeable surfaces are required. Report 8.42, 8.50, 8.52
  • Risk: Bats: a common pipistrelle and brown long-eared bat roost was found, requiring a European Protected Species Licence and mitigation by condition. Report P10, P14
  • Other: The ground floor café/retail space must be retained for public use, with restricted opening hours and a management plan to protect neighbours. Report 8.36, P14, P22

Who and where

  • Future residents of the 9 flats (3 one-bed, 4 three-bed, 2 four-bed) Report 8.8, P117, P118
  • Bus drivers serving the Cane Hill development (toilet retained in perpetuity) Report P3, 8.5
  • BBC (existing transmission equipment retained) Report 3.1, P22, 8.5
  • Cane Hill residents, including Henry Howell House flats Report 6.3, P47, 8.33, 8.34
  • The applicant and the development team Report 2.1

Timeline

  • 22nd October 2014: Original hybrid permission 13/02527/P for the wider Cane Hill redevelopment granted Report 3.6, P32
  • 13th June 2018: Reserved matters 17/06316/RSM approved, including the chapel conversion; partially implemented Report 3.6, P34
  • 2nd April 2024: Biodiversity net gain became mandatory for small sites
  • September and October 2025: Croydon Local Plan examination in public hearings Report 7.3, P64
  • 2026-02-05: Planning Committee resolves to grant permission subject to S.106 and conditions Report 2.1

Plain English for the jargon

  • PTAL: Public Transport Accessibility Level; the site's score is 0 (lowest)
  • S.106: Section 106 legal agreement used to secure planning obligations
  • CIL: Community Infrastructure Levy, a charge on certain developments to fund local infrastructure
  • Class E: Use class covering commercial, business and service uses such as cafés, retail and workspace
  • TPO: Tree Preservation Order; TPO 25 of 1993 covers the Cane Hill development
  • BNG: Biodiversity Net Gain, a requirement for developments to leave biodiversity in a better state
  • GIA: Gross Internal Area, a measurement of floor space
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16/26

Resolved

RESOLVED to GRANT the application for The Chapel, 29 Chaucer Gardens, Coulsdon.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Planning Committee

Recommendation

2.1That the Committee resolve to GRANT planning permission subject to the completion of a S.106 agreement to secure the following heads of terms:

(a) A financial contribution of £15000 towards sustainable travel improvements Confidential

(b) Retention of the bus drivers’ toilet in perpetuity

2.2That the Director of Planning and Sustainable Regeneration as delegated authority to negotiate the legal agreement indicated above.

2.3That, if by three months, the legal agreement has not been completed, the Director of Planning and Sustainable Regeneration is delegated authority to refuse planning permission.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/03178/FUL: The Chapel, 29 Chaucer Gardens, CoulsdonPlan 125 KB Download
PDF
Item 6.4 The Chapel, 29 Chaucer Gardens, Coulsdon /26Report 2.6 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
MN
Councillor Michael NealChair, present
CF
Councillor Clive FraserVice-Chair, present
LF
Councillor Lara FishDeputy-Chair, apologies
SF
Councillor Sean FitzsimonsCommittee Member, present
MI
Councillor Mohammed IslamCommittee Member, present
MJ
Councillor Mark JohnsonCommittee Member, present
HK
Councillor Humayun KabirCommittee Member, present
HR
Councillor Helen RedfernCommittee Member, present
AS
Councillor Appu SrinivasanCommittee Member, present
NS
Councillor Nikhil Sherine ThampiCommittee Member, present
JL
Councillor Joseph LeeReserve, present as substitute
LS
Liam SemugabiSecretary, expected

More from Croydon Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on Thursday 20 August 2026 be signed as a correct record. Decided Open
3 Sep 2026 26/00079/OUT- 1A Brighton Road, South Croydon, CR2 6EARESOLVED to GRANT the application for 26/00079/OUT 1A Brighton Road, South Croydon, CR2 6EA Decided Open
3 Sep 2026 Weekly Planning DecisionsRESOLVED to note the weekly Planning decisions as contained within the report. Noted Open
20 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on Thursday 23 July 2026 be signed as a correct record. Decided Open
20 Aug 2026 6.1- 25/04082/FUL- Selsdon Goods Yard, Selsdon Road, South Croydon, CR2 0EARESOLVED to GRANT the application for 25/04082/FUL- Selsdon Goods Yard, Selsdon Road, South Croydon, CR2 0EA, subject... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies