25/01233/FUL - Mostyn, The Avenue, Coulsdon, CR5 2BN

Decided Planning 2 papers

AI summaryCroydon Planning Committee grants permission for a three-storey block of six flats at Mostyn, The Avenue, Coulsdon, subject to a £9,000 sustainable travel contribution and a Section 106 agreement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to S106 agreement and conditions
Money£9,000 S106 contributionTowards sustainable travel improvements
What happens nextS106 legal agreement to be completedWithin three months or delegated refusal
Who it affectsMostyn, The Avenue, Coulsdon CR5 2BNCoulsdon Town ward, corner with South Drive

What was decided

The committee resolved to grant planning permission for demolition of the existing two-storey dwelling and erection of a three-storey building providing six self-contained flats, four car parking spaces and associated landscaping. Report 3.1, 8.9

Permission is subject to completion of a Section 106 agreement securing a £9,000 sustainable travel contribution and a restriction preventing future occupants from obtaining parking permits in the adjacent Controlled Parking Zone. Report 2.1, P13, P14, 8.52, 8.53

If the legal agreement is not completed within three months, the Director of Planning and Sustainable Regeneration is delegated authority to refuse planning permission. Report 2.2, 2.5

Why

The principle of residential redevelopment is acceptable and contributes to the borough's housing supply, with the scheme providing two family-sized three-bedroom homes alongside four two-bedroom flats. Report 8.3, 8.5, 8.66

Previous reasons for refusal relating to trees, ecology, biodiversity net gain and absence of a legal agreement have been addressed through additional surveys, an amended landscaping plan, a trial-pit investigation of tree roots, and the proposed Section 106 heads of terms. Report 1.2, 8.36, 8.45, 8.47

The design, scale and massing are considered appropriate for this corner plot context, and the proposal would not cause unacceptable harm to neighbouring amenity, protected trees, biodiversity, flooding or highway safety, subject to conditions. Report 8.16, 8.33, 8.45, 8.60, 8.66

What happens next

A Construction Logistics Plan, Arboricultural Method Statement, Construction Environmental Management Plan and site supervision schedule must be submitted and approved before development commences. Report P19, 8.38, 8.59

Above ground floor slab level, the developer must submit details of biodiversity enhancements, materials, landscaping, wildlife-sensitive lighting, visibility splays, cycle and refuse storage. Report P20

Off-site biodiversity units or statutory credits must be secured to deliver the mandatory 10 percent biodiversity net gain, and the development must be carried out in line with the approved ecological, flood risk and fire safety assessments. Report 8.48, P21

The money

  • £9,000 S106 financial contribution towards sustainable travel improvements (6 x £1,500) Report P13, 8.53

Options considered

  • Chosen: Grant planning permission subject to S106 agreement and conditions. Scheme accords with development plan; previous refusal reasons addressed; no unacceptable harm identified subject to conditions Report 2.1, 4.1, P47, 8.66
  • Rejected: Refuse planning permission if S106 not completed within three months. Delegated fallback if legal agreement is not finalised, not the primary decision Report 2.2, 2.5

Implications

  • Financial: Developer must pay £9,000 S106 contribution and is liable for Community Infrastructure Levy. Report P13, P23, 8.53
  • Legal: Future occupants will be restricted from obtaining parking permits in the adjacent Coulsdon Town Centre CPZ via S106 agreement. Report P14, 8.52
  • Equalities: All flats would be step-free with a lift; Flat 4 is designed to be wheelchair adaptable, and remaining units to Part M4(2) of Building Regulations.
  • Climate: Energy statement shows 75 percent CO2 reduction using solar panels and air source heat pumps, with a condition securing final sustainability details. Report 8.63, P20
  • Risk: Site lies in a Critical Drainage Area; a Flood Risk Assessment and SuDS strategy using rainwater collection and a crate soakaway is required by condition. Report 3.5, 8.62, P21
  • Other: Mandatory 10 percent biodiversity net gain to be achieved through off-site units or statutory credits, secured by pre-commencement condition. Report 8.48

Who and where

  • Adjoining residents at 2 The Avenue, with separation and boundary trees retained Report P109, 8.29, 8.30
  • Residents of the newly built block of flats at 1 South Drive, around 12.8m away Report P112, 8.31
  • 26 neighbouring properties notified, with 12 objections received Report 6.1, P55
  • East Coulsdon Residents Association, who objected on character, parking, highways and amenity grounds Report 6.4, P60
  • Cllr Luke Shortland, who objected on character, scale and massing and requested committee consideration Report P10, 6.3
  • Future occupants of the six flats, with access to private and communal amenity space Report 8.20, 8.21, 8.23

Timeline

  • 27 August 2024 and 9 June 2025: Dusk/dawn bat emergence and re-entry surveys carried out; no bats detected Report 8.44
  • 8th September (2025): Site meeting between planning officer, tree officer and applicant's tree consultant, followed by trial pit dig Report 3.2, 8.36
  • 30/01/2025: Earlier application 24/03105/FUL for the same scheme refused on grounds of tree impacts, ecology and biodiversity, and lack of legal agreement Report P41, P42, P43, P44
  • 19th March 2026: Croydon Planning Committee resolves to grant permission subject to S106 and conditions Report P1
  • Within three months of committee resolution: Section 106 legal agreement must be completed or delegated refusal may be exercised Report 2.2, 2.5

Plain English for the jargon

  • Section 106 agreement: A legal agreement between a developer and the local authority used to mitigate the impact of a development, here securing a financial contribution and parking permit restrictions.
  • PTAL: Public Transport Accessibility Level, scored 0 to 6b, measuring access to public transport; the site scores 3, considered good.
  • BNG: Biodiversity Net Gain, a statutory requirement for development to deliver at least a 10 percent measurable improvement in biodiversity, here achieved off-site.
  • TPO: Tree Preservation Order, a legal protection for specified trees; TPO 25/00004/TPO protects a Yew and a Field Maple on this site.
  • SuDS: Sustainable Drainage Systems, methods such as soakaways that manage surface water run-off and reduce flood risk.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/26

Resolved

RESOLVED to GRANT the application for Mostyn, The Avenue, Coulsdon, CR5 2BN .
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Planning Committee

PLANNING COMMITTEE AGENDA 19th March 2026

PART 6: Planning Applications for Decision Item 6.2

1 APPLICATION DETAILS

Ref: 25/01233/FUL Location: Mostyn, The Avenue, Coulsdon, CR5 2BN Ward: Coulsdon Town Description: Demolition of existing dwelling and erection of a 3 storey building to provide 6 no. residential flats with vehicular access, car parking and associated soft and hard landscaping. Drawing Nos: 268-23-MAP.003; 268-23-MAP.004; 268-23-PR.1 Rev F; 268-23-PR.2 Rev F; 268-23-PR.3 Rev F; 268-23-PR.4 Rev F; 268-23-PR.5 Rev F; 268-23-PR.6 Rev F; 268-23-PR.7 Rev F; 268-23-PR.8 Rev F; 268-23- PR.9 Rev F; 268-23-PR.10 Rev F ; 268-23-PR.10 Rev F ; 268-23- PR.14.

Applicant: [name removed], Tetrick Planning Limited Agent: [name removed] Officer: Thomas Tinel

Housing Mix 1 bed 2 bed 2 bed 3 bed 4 bed + TOTAL (2 person) (3 person) (4 person) (4 person) (6 person)

Existing 1 1 Proposed 4 2 6 (market housing)

Number of car parking Number of cycle parking spaces spaces Policy requirement 5 (maximum) 12 long stay (minimum) Proposed 4 14 long stay

1.1This application is being reported to committee because:

 The number of objections received exceeded the threshold required for consideration by the Planning Committee.  Cllr Luke Shortland made representations in accordance with the Committee Consideration Criteria and requested committee consideration.

1.2This application is the first resubmission following the refusal of application 24/03105/FUL which was refused on reasons related to tree impacts, ecology and biodiversity net gain, and absence of legal agreement to mitigate highways impact. The principle of the proposed intensification of the site, the development design and massing, impact on the neighbours and parking provision has previously been considered acceptable. 2 RECOMMENDATION

2.1That the Committee resolve to GRANT planning permission subject to the completion of a S.106 agreement to secure the following heads of terms:

(a) A financial contribution of £9,000 towards sustainable travel improvements

(b) Restriction to parking permits for the future occupants

2.2That, if by three months, the legal agreement has not been completed, the Director of Planning and Sustainable Regeneration is delegated authority to refuse planning permission.

2.3That the Director of Planning and Sustainable Regeneration has delegated authority to issue the planning permission and impose conditions and informatives to secure the following matters:

Conditions

1) Commencement time limit of 3 years 2) Development to be carried out in accordance with the approved drawings

Pre-commencement 3) Submission of Construction Logistics Plan 4) Submission of Arboricultural Method Statement 5) Submission of site supervision schedule and tree officer pre-commencement meeting 6) Submission of Construction Environmental Management Plan for biodiversity 7) Site levels/cross sections

Prior to above ground floor slab level 8) Submission of biodiversity enhancement layouts 9) Submission of detailed design, including materials, detail, boundary treatment and retaining walls 10) Submission of detailed landscaping plan, including details of soft and hard landscaping and new tree planting 11) Details of a wildlife sensitive lighting scheme 12) Details of vehicular and pedestrian visibility splays 13) Details of cycle and refuse storage

Pre-occupation/Compliance 14) Development to be carried out in accordance with the approved Ecological Impact Assessment 15) Development to be carried out in accordance with the approved Flood Risk Assessment and SUDS measures 16) Development to be carried out in accordance with the approved fire safety measures 17) Any other planning condition(s) considered necessary by the Director of Planning and Sustainable Regeneration

Informatives

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/01233/FUL: Mostyn, The Avenue, Coulsdon, CR5 2BNPlan 119 KB Download
PDF
Item 6.2 Mostyn, The Avenue, Coulsdon /26Report 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
MN
Councillor Michael NealChair, present
CF
Councillor Clive FraserVice-Chair, present
LF
Councillor Lara FishDeputy-Chair, present
SF
Councillor Sean FitzsimonsCommittee Member, apologies
MI
Councillor Mohammed IslamCommittee Member, present
MJ
Councillor Mark JohnsonCommittee Member, present
HK
Councillor Humayun KabirCommittee Member, present
HR
Councillor Helen RedfernCommittee Member, present
AS
Councillor Appu SrinivasanCommittee Member, present
NS
Councillor Nikhil Sherine ThampiCommittee Member, present
CH
Councillor Christopher HermanReserve, present as substitute
LS
Liam SemugabiSecretary, expected

More from Croydon Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on Thursday 20 August 2026 be signed as a correct record. Decided Open
3 Sep 2026 26/00079/OUT- 1A Brighton Road, South Croydon, CR2 6EARESOLVED to GRANT the application for 26/00079/OUT 1A Brighton Road, South Croydon, CR2 6EA Decided Open
3 Sep 2026 Weekly Planning DecisionsRESOLVED to note the weekly Planning decisions as contained within the report. Noted Open
20 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the meeting held on Thursday 23 July 2026 be signed as a correct record. Decided Open
20 Aug 2026 6.1- 25/04082/FUL- Selsdon Goods Yard, Selsdon Road, South Croydon, CR2 0EARESOLVED to GRANT the application for 25/04082/FUL- Selsdon Goods Yard, Selsdon Road, South Croydon, CR2 0EA, subject... Decided Open