That Cabinet agrees, in principle, the proposals set out in this report for the transfer of the Council’s s to Hertfordshire Building Control Ltd. That further work is carried out by Officers to complete the technical, contractual and administrative arrangements for the transfer of the Council’s s to Hertfordshire Building Control Ltd. That, once the due diligence and work outlined in recommendation 2 above is completed, the final proposals are referred to Cabinet and Council with the recommendation to transfer of the Council’s s to Hertfordshire Building Control Ltd.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
BUILDING CONTROL SERVICE Title of report: Cllr Graham Sutton, Portfolio Holder for Planning and Contact: Infrastructure
Author/Responsible Officer James Doe, Assistant Director – Planning, Development and Regeneration Sara Whelan, Group Manager – Development Management and Planning Purpose of report: To set out proposals to Cabinet for the future delivery of the Borough Council’s Building Control service.
Recommendations 1. That Cabinet agrees, in principle, the proposals set out in this report for the transfer of the Council’s Building Control Services to Hertfordshire Building Control Ltd.
2. That further work is carried out by Officers to complete the technical, contractual and administrative arrangements for the transfer of the Council’s Building Control Services to Hertfordshire Building Control Ltd. 3. That, once the due diligence and work outlined in recommendation 2 above is completed, the final proposals are referred to Cabinet and Council with the recommendation to transfer of the Council’s Building Control Services to Hertfordshire Building Control Ltd. Corporate The report supports the corporate objectives of : Objectives: A clean, safe and enjoyable environment – a sustainable and well-functioning Building Control service in the long term will continue to ensure that new buildings are constructed to safe standards in compliance with the national Building Regulations, and that an effective service to deal with the public safety issues of dangerous structures as they arise can continue to be provided and delivered effectively
Delivering an efficient and modern Council – The proposals aim to provide a resilient Building Control service in the public interest and offer the best available value for money to the local tax payer.
Implications: Financial
Financial comments are provided in the Part II report.
Value for Money ‘Value For Money Implications’ The commercial environment within which DBC has to operate its in-house Building Control service is one of increasing competition from the private sector and high professional staff costs. This has caused service resilience problems and makes the cost of running the service unsustainable to the Council.
Risk Assessment completed Risk Implications Risks highlighted included economic downturn, losing market share and lower than expected income. Hertfordshire Building Control have current practices in place to mitigate against these and most items on the register were green, although risks would have a high impact there is a low probability of them happening.
Community Impact Assessment completed Community Impact Assessment The recommendation to join Hertfordshire Building Control would mostly impact DBC staff. The changes would not have any negative impacts on the wider community.
Health And Safety None directly arising from this report Implications Monitoring Officer: Monitoring Hertfordshire Building Control Ltd has been set up as a Officer/S.151 “Teckal” company under regulation 12 of the Public Contract Officer Comments Regulations 2015, which means that it can benefit from contracts for works, services or supply from its controlling Contracting Authority (or Authorities) without having to go through a competitive tender process,
In order to qualify as a Teckal company the following circumstances must exist:
• The Contracting Authority/ies must exercise a control which is similar to that which it exercises over its/their own departments – this means it/they must exercise a decisive influence over both strategic objectives and significant decisions of the controlled company either itself or through another subsidiary; and
• More than 80% of the activities of the company must be carried out in the performance of tasks entrusted to it by the controlling Contracting Authority/ies.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.