That the Minimum Project Requirements as set out in paragraph 2 of the report are endorsed. That the following be noted:- (a) the governance structure for the project at paragraph 3. (b) the consultation strategy for stakeholder and public consultation and the stakeholders identified in paragraph 5. (c) the indicative project timeline at paragraph 6. Resolved to recommend 3. That a sum of £65,000 for survey costs to help mitigate potential site risks and develop a more detailed scheme proposal for further approval be agreed.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Contact: Cllr Andrew Williams, Leader of the Council and Portfolio Holder for Corporate and Contracted Services
Author/Responsible Officers:
Mark Brookes, Assistant Director (Corporate and Contracted Services)
Purpose of report: To provide an update to Cabinet on feasibility work and project planning to develop a new Berkhamsted Sports Centre
Recommendations: 1. That Cabinet endorse the Minimum Project Requirements as set out in paragraph 2 of the report.
2. That Cabinet note:-
(a) the governance structure for the project at paragraph 3.
(b) the consultation strategy for stakeholder and public consultation and the stakeholders identified in paragraph 5.
(c) the indicative project timeline at paragraph 6.
1 3. That Cabinet recommend Council agree a sum of £65,000 for survey costs to help mitigate potential site risks and develop a more detailed scheme proposal for further approval.
Corporate Clean, Safe and Enjoyable Environment – Leisure Objectives: provision is central to delivering a borough that people can enjoy. A new leisure facility will help to ensure that it continues to meet the needs of current and future residents.
Implications: Financial
An outline of the financial implications for the new build option are set out in Part I and Part II report to Cabinet on 19th March 2019 and will be developed into a Value For Money formally costed proposal and business plan once Implications: stakeholder and public consultation has completed and further site due diligence carried out.
A further update to Cabinet is anticipated in April/May 2020.
Operational
The Sports Centre will continue to be run by Everyone Active until the end of their contractual term, however a new build facility would require a reassessment of the existing contractual terms with Everyone Active.
The aim (as far as is possible) will be to keep the existing facility open until the new facility is ready to be opened in order to minimise disruption to existing users.
Value for Money
The development will provide a new facility which will be designed to last for the next 40 years and flexible enough to adjust to changes in user demands during that period.
It is envisaged that the main building contractor will be competitively tendered. An appropriate, and compliant, route will be selected to ensure value for money is achieved. This is being reviewed during Stage 1 and a recommendation will be provided to Cabinet for approval in future.
2 Risk Implications: The risk implications will be fully assessed once the stakeholder/public consultation is completed and further due diligence carried out.
Failure to invest in the facility could leave it in a condition which will not meet the Councils and users expectations and could lead to reduced usage contrary to the Council’s sports strategy.
Community Impact: A Community Impact Assessment will be carried out once the outcome of the stakeholder and public consultation is known, but the proposal will be developed to ensure that it has no adverse impacts on the community with an aim to increase participation across all groups.
Health And Safety A new centre will result in significant additional Implications: investment in the site, improve the Health and Safety of the facility by bringing it up to modern standards.
Monitoring Monitoring Officer: Officer/S.151 Officer Comments: There are no legal issues to highlight at this stage as the report is recommending further feasibility and site due diligence work be carried out.
Deputy S.151 Officer:
The £65K funding for the site surveys would be drawn down from the Dacorum Development Reserve in 20/21.
Pending the final feasibility work a comprehensive funding proposal for the final scheme will be developed.
Consultees: The following stakeholders have been consulted:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.