Noted; 1. The feasibility work for the project and the options for facility mix as set out in Section 5 to allow the next stages of the project to be developed and considered in more detail during the next project stage. 2. ( a ) the consultation undertaken with stakeholders and the further consultations required, including public consultation, as set out in Section 4. (b) the indicative project timeline at Section 7. 3. The potential forecast project costs for each option (detailed in Part II Appendix) and agree to use £420,000 of the approved project budget to proceed with the next project stage (RIBA Stage 2 – Concept Design). Agreed; 4. To award the multi-disciplinary consultant project team contract to Faithful+Gould (via the CCS Project Management & Full Design Team Services Framework (RM3741)) with contractual break clauses at the end of each RIBA stage. 5. Endorsed the proposal to provide a further update to Cabinet at the end of RIBA Stage 2 (Concept Design), at which point a more detailed level of understanding of the site will have been achieved and a design, cost and business plan developed accordingly.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
If Part II, reason: The Part II appendix contains information relating to the financial or business affairs of the Council.
(Local Government Act 1972, Schedule 12A, Part 1, Paragraph 3).
Title of report: Berkhamsted Leisure Centre Redevelopment
Contact: Cllr Andrew Williams, Leader of the Council and Portfolio Holder for Corporate and Contracted Services
Author/Responsible Officers:
Mark Brookes, Assistant Director (Corporate and Contracted Services)
Purpose of report: To provide an update to Cabinet on feasibility work and project planning to develop a new Berkhamsted Sports Centre
Recommendations
1. That Cabinet note the feasibility work for the project and the options for facility mix as set out in Section 5 to allow the next stages of the project to be developed and considered in more detail during the next project stage.
2. That Cabinet note:-
(a) the consultation undertaken with stakeholders and the further consultations
1 required, including public consultation, as set out in Section 4.
(b) the indicative project timeline at Section 7.
3. That Cabinet note the potential forecast project costs for each option (detailed in Part II Appendix) and agree to use £420,000 of the approved project budget to proceed with the next project stage (RIBA Stage 2 – Concept Design).
4. That Cabinet agree to award the multi- disciplinary consultant project team contract to Faithful+Gould (via the CCS Project Management & Full Design Team Services Framework (RM3741)) with contractual break clauses at the end of each RIBA stage.
5. That Cabinet endorse the proposal to provide a further update to Cabinet at the end of RIBA Stage 2 (Concept Design), at which point a more detailed level of understanding of the site will have been achieved and a design, cost and business plan developed accordingly.
Corporate Clean, Safe and Enjoyable Environment – Leisure Objectives: provision is central to delivering a borough that people can enjoy. A new leisure facility will help to ensure that it continues to meet the needs of current and future residents.
Implications: Financial
An outline of the financial implications of the project are set out in the Part II report and will be developed into a formally costed proposal and business plan once further design and stakeholder consultation has completed.
This report seeks approval to proceed to RIBA Stage 2 only and a drawdown of £420,000 for the consultancy and survey costs required at that stage. A further report seeking authority for the full project cots will be reported to Cabinet and Council at the end of RIBA Stage 2.
Operational
2 Subject to agreement on contractual terms, the sports centre will continue to be run by Everyone Active until the end of their contractual term, however a new build facility would require a reassessment of the existing terms.
The aim (as far as is possible) will be to keep the existing facility open until the new facility is ready to be opened in order to minimise disruption to existing users.
Value for Money
The development will provide a new facility, which will be designed to last for the next 40 years and flexible enough to adjust to changes in user demands during that period.
The main building contractor will be competitively tendered separately to the consultant project team and an appropriate and compliant route will be selected to ensure value for money is achieved.
Further detail and recommendations are provided within this report and key decisions will be provided to Cabinet for approval in future.
Risk Implications: Failure to invest in the facility could leave it in a condition, which will not meet the Councils and users expectations and could lead to reduced usage contrary to the Council’s sports strategy.
An initial review of project specific risks has been undertaken and a detailed risk register will be developed through the next stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.