That planning permission be REFUSED for the following reasons: 1) By virtue of the absence of pedestrian and/or vehicular visibility splays when exiting the site, particularly when turning right, the development would result in an unacceptable risk to highway safety, contrary to Policy CS12(a) of the Dacorum Borough Core Strategy (September 2013) and paragraphs 110 and 111 of the National Planning Policy Framework. 2) By virtue of the scale, form and level changes of proposed Units 1-3, the proposed development would cause less than substantial harm to the Markyate conservation area, including the relationship with No.9 Albert Street (a Grade II Listed Building), which is not outweighed by the public benefits of the development. As such the development fails to comply with CS27 of the Dacorum Borough Core Strategy (September 2013) and paragraph 202 of the National Planning Policy Framework. 3) The private amenity space proposed for the proposed houses and flats fails to meet the requirements of Saved Appendix 3 of the Dacorum Borough Local Plan (1991-2011), both in terms of the scale and functionality of the private amenity space to be provided and also in terms of its compatibility with surrounding areas. The failure to provide adequate private amenity space in accordance with Saved Appendix 3 demonstrates the overdevelopment of the plot under the current proposals. The development is therefore also contrary to Policy CS12(g) of the Dacorum Borough Core Strategy (September 2013).
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
That planning permission be DELEGATED with a view to APPROVAL subject to the outcome of the Applicant carrying out of additional ecological surveys and an appropriate assessment in accordance with article 6(3) of the Habitats Directive, securing a mitigation if necessary to avoid any further significant effects on the Chilterns Beechwood Special Area of Conservation, the completion of an additional bat survey(s), with further delegated authority to add any bat / ecological mitigation conditions as necessary arising from the ecological surveys.
Summary
2.1In principle the development is acceptable with reference to Policies CS1 and CS4 of the Dacorum Borough Core Strategy (2013), with no overriding objection to the loss of a long established employment use. Subject to the carrying out of additional ecological surveys and that these do not identify overriding problems, on fine balance and taking a pragmatic approach, there is a case for the LPA to support this application.
2.2The scheme has been subject to revisions since the application’s receipt and following two withdrawn applications. In terms of the Revised Scheme, there are reservations expressed by the Design & Conservation Team regarding the design of Units 1 to 3, but this is based upon on less than substantial harm to Markyate Conservation Area. Whilst not fully in accordance with Policies CS12 and CS27, with reference to the Framework’s Part 16, it is concluded that, on fine balance, the public benefits of providing new housing in the proposed compact form- a quality alternative when compared to the existing array of buildings by providing a modern residential enclave- outweighs the less than substantial harm confirmed by the Design & Conservation Team. Therefore, on very fine balance the heritage harm arising would, in this instance, not outweigh the public benefits of the proposed development.
2.3The context is that in developing brownfield land within built up areas such as the application site, it is rarely possible for every design expectation to be met. In this respect overall, it is considered that the development would appear compact and create a small high quality residential enclave of much needed small dwellings which is in accordance with the national space standards in an historically compact area. It is recognised that the 8.4m depth gardens of Units 1, 2 and 3 are below the ‘standard’ 11.5m depth, however they are still of a usable size with a south facing aspect. Units 4, 5, and 6 would also benefit from usable small amenity areas. There is also some scope for planting.
2.4With reference to the adopted Parking Standards there would be adequate parking served by the existing very wide roadway linked to the High Street, with no highway objections from HCC Highways to the use of the long established site access. This takes into account that for vehicles exiting there is very minimal visibility to the access’ right hand side which cannot be improved. Fire tenders can access the site in forward gear, with the proposal involving the provision of a sprinkler system for Units 1 to 3, taking account that there is an inadequate turning area for tenders. There are no objections to the approach regarding the collection and storage of refuse.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
5b21/03244/FUL - Conversion and construction of 6 dwellinghouses on brownfield site - 50 High Street Markyate St Albans Hertfordshire AL3 8HZThis decision
21/03244/FUL - Conversion and construction of 6 dwellinghouses on brownfield site - 50 High Street Markyate St Albans Hertfordshire AL3 8HZThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.