Principal Contractor Appointment. Cabinet: 1. Approved entering into the JCT D&B contract with Bugler Developments Ltd for the delivery 34 units at Eastwick Row, Hemel Hempstead. 2. Delegated authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to): a . all professional appointments; b . collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991.
Word for word from the decision Dacorum published for this meeting.Source: democracy.dacorum.gov.uk
Glossary of acronyms DMC – Development Management Committee and any other GF – General Fund abbreviations used in HRA – Housing Revenue Account this report: ITT – Invitation to Tender JCT – Joint Contracts Tribunal D&B – Design & Build EA – Employers Agent
Report Author / Responsible Officer
Julie Abbey-Taylor - Head of Investment & Delivery [email protected]
1 Corporate Priorities A clean, safe and enjoyable environment Building strong and vibrant communities Ensuring economic growth and prosperity Providing good quality affordable homes, in particular, for those most in need Ensuring efficient, effective and modern service delivery Climate and ecological emergency
Wards affected Adeyfield Ward
Purpose of the report: To be read in conjunction with Part II.
1. To seek approval to enter into the JCT Design & Build 2016 (D&B) contract with Bugler Developments Ltd for the delivery of 34 units at Eastwick Row, Hemel Hempstead. This contract will require Bugler Developments Ltd to complete the previously started construction of the block of flats that was halted due to the previous contractor Jarvis Contracting Ltd going into Administration.
2. To provide delegated authority to the Council’s Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project.
Recommendation (s) to the Principal Contractor Appointment. decision maker (s): That Cabinet:
1. Approves entering into the JCT D&B contract with Bugler Developments Ltd for the delivery 34 units at Eastwick Row, Hemel Hempstead.
2. Delegates authority to the Assistant Director (Legal & Democratic Services) to execute and complete all legal agreements ancillary to the JCT Design & Build Contract 2016 and/or reasonably required to complete the Project, including (but not limited to):
a. all professional appointments; b. collateral warranties; and c. Agreements under S.38, & S.278, of the Highways Act 1980; S.247, Part III of the Town and Country Planning Act 1990; S.104 of the Water Industry Act 1991, and S.50 of the New Roads and Street Works Act 1991.
Period for post There will be a 12-month defect liability period after practical policy/project review: completion. A 2-year review period is therefore recommended for this project.
2 1. Introduction/Background:
1.1Since 2013, the Council has delivered 385 new Council homes in the Borough.
1.2The Council originally identified Eastwick Row for redevelopment and the scheme to deliver a block of 34 flats and 2 houses received approval by Cabinet in September 2020.
1.3Works had commenced on site on 21st May 2021 and were taken up to the completion of the concrete frame when, unfortunately, on 28th February 2023 Jarvis Contracting Limited (Jarvis) went into administration.
1.4Since this date, Dacorum Borough Council has worked to take back possession of the site, has undertaken significant works to ensure the site is maintained in a safe condition and has taken the scheme back to market via a competitive tender to select another contractor to take the scheme through to completion.
1.5The Council has worked with Employers Agent (EA) Philip Pank Partnerships LLP (PPP) to produce a tender pack and issue this to the market. This process has now completed and Cabinet is asked to approve the appointment of a new Principal Contractor.
2. Proposals:
Principal Contractor Appointment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.