INTERNAL AUDIT PROGRESS REPORT

Agreed Finance 1 paper

Governance and Audit Committee agreed this item on Wednesday 11 July 2012. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

RESOLVED – that the Corporate Governance Committee:- (a) receives the report and notes Internal Audit’s progress and performance to date in 2012/13 (b) notes the recent Internal Audit reports issued and the responses to the follow up work, and (c) agreed that the three Audit Reports identified be circulated to Members of the Committee.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Governance and Audit Committee

Report To: Corporate Governance Committee

Date of Meeting: 11 July 2012

Report Author: Head of Internal Audit Services

Title: Internal Audit Progress Report

1. What is the report about?

This report updates the Committee on the latest progress of the Internal Audit service in terms of its service delivery, assurance provision, reviews completed, performance and effectiveness in driving improvement.

2. What is the reason for making this report?

To bring Members up to date regarding: delivery of our Operational Plan for 2012/13 recent Internal Audit reports issued management’s response to issues we have raised Internal Audit’s performance

3. What are the Recommendations?

 Committee considers and comments on Internal Audit’s progress and performance to date in 2012/13  Committee considers and comments on recent Internal Audit reports issued  Committee considers the responses to our follow up work

4. Internal Audit Progress

Delivery of the Internal Audit Strategy 2012/13

4.1Appendix 1 provides a breakdown of our work during 2012/13, compared to the agreed Internal Audit Strategy It includes assurance scores and number of issues raised for the completed reviews, definitions used to form our audit assurance and the ratings used to assess the risk-levels for issues raised.

Summary of Recent Internal Audit Reports

4.2Our reports use colours for assurance ratings as follows:

High Assurance Risks and controls well managed Medium Assurance Risks identified but are containable at service level Low Assurance Risks identified that require meeting with Director/Lead Member No Assurance Significant risks identified that require member / officer case conference 4.3. Since my report in March 2012, we have issued the following reports.

Issues Raised Audit Critical Major Moderate Audit Report Comments Opinion Risk Risk Risk (Red) (Amber) (Yellow) Programme & Project Overview only, so no overall N/A 0 0 2 Management Assurance Opinion provided Community Building Action Plan followed up and is Management - Rhyl Town Yellow 0 0 10 being implemented Hall Corporate Risk - Asset Overview only, so no overall N/A 0 0 0 Portfolio Assurance Opinion provided Highways & Infrastructure Yellow 0 2 7 - Major Projects Financial Systems Assurance Testing Green 0 0 0 (IDEA) 2011-12 No formal report - Email Welsh Government Green 0 0 0 confirmation to Welsh Breakfast Initiative Grant Government only Financial Services - Green 0 0 3 Phase 2 (Ruthin services)

Management’s response to issues raised by Internal Audit

4.4Most of our Internal Audit reports identify risks and control weaknesses. We rate these as either critical, major or moderate risk. Management agrees actions to address the risks, including responsibilities and timescales.

4.5We report all instances where management fails to respond to our follow up work or where, where they exceed the agreed implementation date by more than three months. This Committee decides whether it needs to take further action, for example, by calling the relevant people to its next meeting to explain lack of progress.

4.6There are currently no actions outstanding or exceeding the three-month deadline.

Internal Audit Performance – Key Measures

Measure - Review 100% of agreed S151 Assurance areas in Operational Audit Plan by 31 March 2013

4.7We complete most of our work in financial areas during the second half of the year, but so far have complete 20% of the planned projects.

Measure - Review 100% of agreed Corporate Governance Assurance areas in Operational Audit Plan by 31 March 2013

4.8Work is in progress ongoing on the Corporate Governance Framework throughout the year. We will review risk management in the second half of the year. Measure - Review 100% of agreed High Corporate Risk Assurance areas in Operational Audit Plan by 31 March 2013

4.9There are currently six high risks in the Corporate Risk Register. We have completed work in one area and work is nearly complete in a second.

Measure - Head of Internal Audit to produce Annual Internal Audit Report by 31 May 2013

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT PROGRESS REPORTReport 245 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. INTERNAL AUDIT PROGRESS REPORTThis decision
  2. Internal audit scoping reportNoted
  3. Internal audit updateDecided
  4. Internal audit annual report 2023 - 24Decided
  5. Internal audit updateNoted
  6. Internal audit updateDecided

More from Denbighshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... Approved Open
22 Jul 2026 Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... Noted Open
22 Jul 2026 Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... Approved Open
22 Jul 2026 Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. Decided Open
22 Jul 2026 Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies