RESOLVED – that the Corporate Governance Committee:- (a) receives the report and notes Internal Audit’s progress and performance to date in 2012/13 (b) notes the recent Internal Audit reports issued and the responses to the follow up work, and (c) agreed that the three Audit Reports identified be circulated to Members of the Committee.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
This report updates the Committee on the latest progress of the Internal Audit service in terms of its service delivery, assurance provision, reviews completed, performance and effectiveness in driving improvement.
2. What is the reason for making this report?
To bring Members up to date regarding: delivery of our Operational Plan for 2012/13 recent Internal Audit reports issued management’s response to issues we have raised Internal Audit’s performance
3. What are the Recommendations?
Committee considers and comments on Internal Audit’s progress and performance to date in 2012/13 Committee considers and comments on recent Internal Audit reports issued Committee considers the responses to our follow up work
4. Internal Audit Progress
Delivery of the Internal Audit Strategy 2012/13
4.1Appendix 1 provides a breakdown of our work during 2012/13, compared to the agreed Internal Audit Strategy It includes assurance scores and number of issues raised for the completed reviews, definitions used to form our audit assurance and the ratings used to assess the risk-levels for issues raised.
Summary of Recent Internal Audit Reports
4.2Our reports use colours for assurance ratings as follows:
High Assurance Risks and controls well managed Medium Assurance Risks identified but are containable at service level Low Assurance Risks identified that require meeting with Director/Lead Member No Assurance Significant risks identified that require member / officer case conference 4.3. Since my report in March 2012, we have issued the following reports.
Issues Raised Audit Critical Major Moderate Audit Report Comments Opinion Risk Risk Risk (Red) (Amber) (Yellow) Programme & Project Overview only, so no overall N/A 0 0 2 Management Assurance Opinion provided Community Building Action Plan followed up and is Management - Rhyl Town Yellow 0 0 10 being implemented Hall Corporate Risk - Asset Overview only, so no overall N/A 0 0 0 Portfolio Assurance Opinion provided Highways & Infrastructure Yellow 0 2 7 - Major Projects Financial Systems Assurance Testing Green 0 0 0 (IDEA) 2011-12 No formal report - Email Welsh Government Green 0 0 0 confirmation to Welsh Breakfast Initiative Grant Government only Financial Services - Green 0 0 3 Phase 2 (Ruthin services)
Management’s response to issues raised by Internal Audit
4.4Most of our Internal Audit reports identify risks and control weaknesses. We rate these as either critical, major or moderate risk. Management agrees actions to address the risks, including responsibilities and timescales.
4.5We report all instances where management fails to respond to our follow up work or where, where they exceed the agreed implementation date by more than three months. This Committee decides whether it needs to take further action, for example, by calling the relevant people to its next meeting to explain lack of progress.
4.6There are currently no actions outstanding or exceeding the three-month deadline.
Internal Audit Performance – Key Measures
Measure - Review 100% of agreed S151 Assurance areas in Operational Audit Plan by 31 March 2013
4.7We complete most of our work in financial areas during the second half of the year, but so far have complete 20% of the planned projects.
Measure - Review 100% of agreed Corporate Governance Assurance areas in Operational Audit Plan by 31 March 2013
4.8Work is in progress ongoing on the Corporate Governance Framework throughout the year. We will review risk management in the second half of the year. Measure - Review 100% of agreed High Corporate Risk Assurance areas in Operational Audit Plan by 31 March 2013
4.9There are currently six high risks in the Corporate Risk Register. We have completed work in one area and work is nearly complete in a second.
Measure - Head of Internal Audit to produce Annual Internal Audit Report by 31 May 2013
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.