Governance and Audit Committee, Wednesday 11 July 2012 at 9.30am

REVIEW OF STRATEGIC RISK MANAGEMENT: CLOSURE REPORT

Decided Finance 2 papers

Governance and Audit Committee decided this item on Wednesday 11 July 2012. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED – that the Corporate Governance Committee receives the report and notes the project closure report, Appendix ... view the full minutes text for item 9.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Governance and Audit Committee

Report To: Corporate Governance Committee

Date of Meeting: 11 July 2012

Lead Officer: Alan Smith, Head of Business Planning & Performance

Report Author: Tony Ward, Corporate Improvement Team Officer

Title: Review of Strategic Risk Management: Closure Report

1. What is the report about?

This report presents the project closure report for the Strategic Risk Management Review Project.

2. What is the reason for making this report?

To provide information regarding the review of strategic risk management and the subsequent implementation of a new process for coordinating strategic risk management.

3. What are the Recommendations?

The Members note the attached project closure report (attached at Appendix A). The Corporate Improvement Team Manager will be in attendance to respond to any comments or queries in relation to the report.

4. Report details.

The council undertook a review of strategic risk management due to concerns about how well embedded the activity was within the organisation. The review proposed a number of changes to the current process, including: a new strategic risk management policy & procedure; and moving responsibility for coordinating strategic risk management from Internal Audit Services to the Corporate Improvement Team. Following implementation of these changes, the following benefits have been realised (detailed on page 5 of the attached Risk Review Closure Report: A modernised, more integrated and effective Risk Management system that is fit for purpose and simple to understand. A clear template that has contributed to the reduction in the size of the risk registers (see appendix III) by some four-fifths (401 pages to 80), making the registers easier to follow, and allowing for savings in printing across the authority. A significant reduction in the number of objective traps and issues from 172 to 30 (see appendix III). All 35 instances of duplication were also eliminated from the registers. A proactive and continuous risk aware culture across all parts of the council, which reduces the possibility of unplanned activity or financial costs and their effect on the council’s reputation, and maintains and improves customer confidence in our ability to deliver on our commitments. Clear accountability and reporting procedures in place. Services are encouraged to take a whole-service approach to their registers, allowing for greater focus, less duplication and fewer issues being reported. A dedicated team in the Corporate Improvement Officers that coordinate risk consistently throughout the council. Resources, including member and officer time, can be used more effectively. The relationship between the Corporate Risk Register and the service risk registers is better defined, aligning more clearly the responsibility for those risks with Director and Cabinet portfolios. A system that mirrors that which is used by Conwy County Borough Council, which makes for easier planning where joint services are concerned.

5. How does the decision contribute to the Corporate Priorities?

Effective risk management is necessary in order to identify and manage the potential events which (if they occurred) would have a detrimental impact on our ability to achieve our objectives, including our Corporate Priorities.

6. What will it cost and how will it affect other services?

The cost of the risk management review, and implementation, has been absorbed by the Business Planning & Performance service. The Corporate Improvement Team (within Business Planning & Performance) are responsible for coordinating strategic risk management to ensure that the new approach continues to be followed for our Corporate and Service risk registers.

7. What consultations have been carried out?

No consultation has taken place in relation to developing this report or the Risk Review Closure Report (attached). It has been produced by the Corporate Improvement Team based on an analysis of the outputs from risk management (i.e. risk registers).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REVIEW OF STRATEGIC RISK MANAGEMENT: CLOSURE REPORTReport 41 KB DownloadRead as text
PDF
Strat Risk Man AppendReport 252 KB Download

At this meeting

Whole meeting

More from Denbighshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... Approved Open
22 Jul 2026 Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... Noted Open
22 Jul 2026 Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... Approved Open
22 Jul 2026 Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. Decided Open
22 Jul 2026 Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies