Resolved

RESOLVED that the Corporate Governance Committee notes: (i) The progress made and the arrangements to ensure there is continued attention to the outstanding areas (ii) That the scoping work is being undertaken setting out the strategic HR challenges arising for the council in the period 2014/17.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Governance and Audit Committee

Report To: Corporate Governance Committee

Date of Meeting: 29th January, 2014

Lead Member / Officer: Director of Modernisation and Wellbeing

Report Author: Director of Modernisation and Wellbeing

Title: People Strategy 2011/14- closure report

1. What is the report about?

The report sets out progress in delivering against the People Strategy, identifies outstanding issues and recommends next steps.

2. What is the reason for making this report?

The People Strategy has been the mechanism for ensuring that the corporate priorities of the council are underpinned by appropriate HR and organisational development work. Progress against the Strategy is being reported to the Corporate Governance Committee to complement the monitoring role it has played with the HR Improvement Plan.

3. What are the Recommendations?

That the Corporate Governance Committee

3.1notes the progress made and the arrangements to ensure there is continued attention to the outstanding areas set out in paragraph 4.6

3.2notes that scoping work is being undertaken setting out the strategic HR challenges arising for the council in the period 2014/17

4 Report details

4.1The People Strategy was developed in 2011 to set out the HR related work that was needed to ensure effective delivery of corporate priorities. Priorities for the People Strategy were agreed by the Senior Leadership Team, working with colleagues in HR.

4.2The original strategy is attached at Appendix 1. Agreed key themes were:

1 Attraction and Retention of Skills and Talent – Ensuring we have the best people for the role 2 Workforce Development – Ensuring we develop people appropriately to deliver business objectives 3 Employee Engagement – unlocking people’s potential at work 4 Managing Change 5 Healthy Workforce

4.3A detailed action plan was developed to enable delivery of the People Strategy. The Year 3 Action Plan, together with updated progress statement, is attached at Appendix 2.

4.4While the key themes have remained the same, the action plan has evolved over time to take account of significant changes. These have included

- The new incoming council in 2012 with agreement of new corporate priorities and the Corporate Plan - The reduced emphasis on collaborative working - Capacity issues arising from the need to pay urgent attention to day to day operations within HR- which led to the development of the HR Improvement Plan - The Senior Leadership Team view that the action plan needed to be shorter and more focused

4.5Delivery of the Strategy has been the responsibility both of senior managers within services and staff in HR. The model used has been that of Programme Sponsorship by a Corporate Director and project sponsorship of the 5 themes by nominated Heads of Service. Partnership in this way between services and corporate support functions is essential to ensure ownership. The model has been moderately successful though Heads of Service have found it difficult to find the capacity to drive the themes they are responsible for.

4.6Most key activities have been delivered. However, appraisal of progress against the objectives set indicates some issues which will need continued attention in taking strategic HR work forward. These are

- Clear evaluation arrangements for the quality and impact of strategic HR work and programmes. Specific examples include the need for evaluation of the effectiveness of current systems of HR support, including HR guidance on the Intranet and the Corporate Training Plan. This work will be picked up as part of the HR Business Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PEOPLE STRATEGY 2011/14: CLOSURE REPORTReport 174 KB DownloadRead as text
PDF
People Sstrategy App 1Appendix 876 KB Download
PDF
People Strategy App 2Appendix 344 KB Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. PEOPLE STRATEGY 2011/14 - CLOSURE REPORTThis decision
  2. Consultation on the supporting people spend plan & changes to the supporting people strategy for 2013 to 2014Agreed
  3. Supporting people strategy updateDecided
  4. Supporting people strategy update and operational plan 2012 – 13Agreed

More from Denbighshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 MINUTESRESOLVED that subject to the above, the minutes of the meeting held on the 10 June 2026 be received and approved as a... Approved Open
22 Jul 2026 Treasury management 2026/27 updateRESOLVED that; 1. The Governance and Audit committee note the performance of the TM function during 2025/26 and its c... Noted Open
22 Jul 2026 Annual governance and audit committee report 2025/26RESOLVED that, members of the Governance and Audit Committee approve the draft Annual Governance and Audit Committee ... Approved Open
22 Jul 2026 Membership of the governance and audit sub-committee of the north wales corporate joint committeeRESOLVED that Councillor James Elson be nominated as the substitute representative. Decided Open
22 Jul 2026 Governance and audit committee work programmethat subject to the above, the Governance and Audit Committee Forward Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies