APPROVAL OF BUSINESS CASE FOR RHYL NEW SCHOOL PROJECT

Approved Committee 3 papers

County Council approved this item on Tuesday 25 February 2014. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED that Council approve the Business Case for the Rhyl New School prior to determination by the Welsh Government.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to County Council

Report To: Council

Date of Meeting: 25th February 2014

Lead Member / Officer: Councillor Eryl Williams, Lead Member for Education

Report Author: Head of Customers and Education Support

Title: Approval of Business Case for Rhyl New School Project

1. What is the report about?

The report seeks to inform Council of the current position with regard to the Council’s submission of the Final Business Case for Rhyl New School to the Welsh Government.

2. What is the reason for making this report?

In September 2013 the Welsh Government approved the Strategic Outline Case for the Rhyl New School project. Following discussions with Welsh Government officials it has been agreed to submit a combined Outline / Final Business Case for their consideration.

3. What are the Recommendations?

To approve the Business Case for Rhyl New School prior to determination by the Welsh Government.

4. Report details.

4.1The Corporate Plan details the Council’s ambition to deliver significant investment in the School Building portfolio between 2012-17. A significant element of this work will be the delivery of the Band A projects for the 21st Century Schools Programme.

4.2The Welsh Government provided approval in principal for £36.7m as their 50% contribution towards the 21st Century Schools Programme in December 2011. Subsequent to this the Welsh Government have worked with all local authorities to ascertain how the overall £1.2 billion investment across Wales can be allocated into deliverable workstreams for individual local authorities. One of these projects was the Rhyl New School. The project will provide a new school building for Rhyl High School to serve up to 1200 pupils in mainstream education whilst also housing approximately 45 pupils from Ysgol Tir Morfa, the community special school in Rhyl. 4.3 All projects within the 21st Century Schools Programme (21st CSP) will be required to follow the guidance for Business Case approvals as defined in the HM Treasury Model. For projects below £5m a Business Justification Case will require approval whilst for projects above £5m, approval of the Strategic Outline Case (SOC), Outline Business Case (OBC) and Full Business Case (FBC) will be required.

4.4Cabinet gave approval in February 2013 for approximately £1.5m to fund Phase 2 (Detailed Design) which would enable the project to be progressed to a stage where approval could be sought for the full business case. The “stage D” design report was submitted in December 2013 by Wilmott Dixon, the Council’s appointed contractor to deliver this project. This is a key document which summarises the feasibility works undertaken over the past 8 months on this project. The key objectives are:

• To give a comprehensive overview of the feasibility undertaken. • To understand the education vision and how this has translated into a new community facility. • To demonstrate technical proficiency appropriate to the design of the building and site. • To present robust costing information which demonstrates that the school can be delivered to an agreed budget. • To demonstrate an achievable master programme for the project which reflects possible outcomes of the planning process. • To highlight any risks which remain with the project and show these can be mitigated and managed through the next stages of the project. • To present a level of information on the feasibility to receive successful Denbighshire / Welsh Government funding approval and to enable the authority to move forward to the detailed stages of the project.

4.5The overall cost for the Wilmott Dixon contracted element of the project within the Stage D report was £22,281,516. This was £38,017 less than the previously estimated sum. The overall cost for the project is presently £24,586,100 which includes Denbighshire costs (client and design fees) and Client contingency sums.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APPROVAL OF BUSINESS CASE FOR RHYL NEW SCHOOL PROJECTReport 218 KB DownloadRead as text
PDF
Equality Impact Assessment TemplateReport 134 KB Download
PDF
Rhyl New School: Full Business Case App 1Appendix 599 KB Download

More from Denbighshire County Council

All decisions
MeetingDecisionOutcome
7 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on the 12 May 2026 subject to the agreed corrections be received and co... Agreed Open
7 Jul 2026 Council performance self-assessment 2025 to 2026 and performance update report october 2025 to march 2026RESOLVED that the Council I. noted the six-monthly Performance Update Report and Citizens' Voice Report; II. noted th... Noted Open
7 Jul 2026 Strategic equality and diversity group (sedg) annual statement 2025 to 2026RESOLVED that Council: I. acknowledged the Strategic Equality and Diversity Group Annual Statement for 2025/26; and I... Decided Open
7 Jul 2026 Pay policy statement 2026/27RESOLVED that Council: I. approved the Pay Policy Statement for 2026/27 as recommended by the Senior Leadership Remun... Approved Open
7 Jul 2026 Appointment of county councillor to the standards committeeRESOLVED that Councillor Andrea Tomlin be appointed as the County Council representative on the Standards Committee. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies