Resolved
RESOLVED that the information report be accepted.
Planning Committee decided this item on Wednesday 15 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the information report be accepted.
1.1The report provides a short factual update for the Committee on developments at the North Wales Hospital site, as requested by Members at the March 2015, meeting and is for information purposes only.
1.2The last formal report to Planning Committee in relation to the site was in September 2013 when Members were requested to consider authorising the making of a Compulsory Purchase Order.
2 FACTUAL BACKGROUND
2.1Members will be aware of the lengthy history relating to the site since closure in 1995 and disposal by the former Health Authority.
2.2The planning consent granted in September 2006 for a mixed use redevelopment including enabling housing development within the grounds and restoration of listed buildings was issued following completion of a Section 106 Obligation which set out a range of requirements including the establishment of a Restoration Fund.
2.3Listed building consent was granted in 2008 for the demolition of a number of peripheral buildings within the complex. Works of demolition were commenced in late 2008 but were stopped as the relevant Licence(s) to disturb Protected Species (bats) had not been obtained.
2.4In December 2008, following a serious fire affecting the Main Hall, the Council served a Section 77 Notice under the Building Act 1984. This Notice was complied with and the building was demolished given its dangerous condition.
2.5Whilst a number of detailed submissions were made in relation to the 2006 planning permission, not all conditions were complied with within the relevant period, and the permission expired in September 2009.
2.6In March 2010, the Prince’s Regeneration Trust was formally engaged by the Council to provide advice and support. The Trust produced a detailed Route Map document explaining the options facing the Council and recommending a way forward to be pursued in the event of continued neglect by the owner.
2.7In October 2010, a Part II report was taken to Cabinet, where Members agreed to support the service of an Urgent Works Notice and Repairs Notice, and to the formation of a Single Purpose Vehicle in the form of a Building Preservation Trust, in accord with the Route Map.
2.8In December 2010, Planning Committee authorised the service of an Urgent Works Notice and a Repairs Notice, and in the event of non compliance, the intention to proceed with a Compulsory Purchase Order.
2.9The Urgent Works Notice was served in June 2011. On the basis of the response on behalf of the owners, Wye Valley Demolition were instructed to enter the site to carry out the urgent works in default. This contract spanned 14 months. Relevant demands were served on the owner to reclaim the money spent, under Section 55 of the 1990 Planning (Listed Buildings and Conservation Areas) Act 1990. The cost of the urgent works was approximately £930,000 and in brief relating to the main range buildings :
2.10The Repairs Notice was served in May 2013.
2.11In September 2013, Planning Committee authorised the commencement of the Compulsory Purchase of the hospital site in accordance with Section 47 of the 1990 Act.
2.12A Public Inquiry was held in 3 sittings between April and July 2014 in relation to 3 of the 5 Section 55 demands (i.e. approximately half of the £930,000 spent on the urgent works). The Inspector’s decision on this Inquiry is still awaited. The 2 S55 demands for which no appeal was submitted is money owned by the owner to the Council.
2.13The Compulsory Purchase Order was made in June 2014, incorporating the related Statement of Reasons. An objection was made to the Order in September 2014, by the owners.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FORMER NORTH WALES HOSPITAL, DENBIGH: INFORMATION REPORTReport | 57 KB | DownloadRead as text |
Follow Planning Committee at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 15 Jul 2026 | MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... | Approved | Open |
| 17 Jun 2026 | MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... | Approved | Open |
| 13 May 2026 | Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
| 13 May 2026 | Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.