RESOLVED that Cabinet – (a) notes the position of the UK Government Funding Award for the project; (b) approves the recommendation from the Capital Scrutiny Group to proceed with the match funding contribution to support Phase 1 of the Former North Wales Hospital Project in line with the Council’s own financial procedures and the associated Capital Business Case (Appendix 2 to the report ); (c) authorises the issue of the Grant to the Development Partner acknowledging i ) the checks that have been undertaken as a part of the Due Diligence process required by UK Government and ii) understanding this is subject to satisfactory subsidy control assessment, and finalisation of all outstanding S106 and land transfer items being addressed, and (d) confirms that it has read, understood, and taken account of the Ambition North Wales Impact Assessment as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
4.1The Former North Wales Hospital project is a complex project on a large site of historical significance for North Wales. The ambition of the current project is to deliver a scheme of physical regeneration improvements to the site of the Former North Wales Hospital and to save a Grade 2* listed building of significant importance that has not been occupied since 1996. The proposal represents a huge economic development opportunity to Denbigh and Denbighshire.
4.2This is a project of regional significance and although instigated by Denbighshire County Council more than 15 years ago, it is now being led by Ambition North Wales (ANW) and sits within the Land and Property Programme for the North Wales Growth. The full history surrounding the site and its development can be found in Appendix 1. 4.3. ANW have undertaken a robust 5 stage business case process for this project which was formal approved by the Regional Partnership earlier this year. The total project development cost has been identified as £107 Million.
4.4The Project in its entirety is expected to be undertaken over a 12-year period in 3 phases with Phase 1 of this scheme for the demolitions and site remediation works inclusive of primary site, upgrading utilities, establish bio habitat infrastructure and construction skills centre.
4.5The costs of Phase 1 is £13M of which ANW have secured £7M from the UK Government’s Growth Deal funding and £3M of private investment.
4.6Denbighshire County Council’s Cabinet resolved in December 2021 to include Phase 1 of this project within its application for UK Government Levelling Up Funding. Following a comprehensive grant appraisal process, the Council has now received formal notification that this funding has been awarded with £3M allocated to this project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.