Denbighshire County Council
Cabinet, Tuesday 24 November 2020 at 10.00am

LLYS AWELON PHASE 2

Approved Executive 3 papers

Cabinet approved this item on Tuesday 24 November 2020. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Vote taken: 8 in favour, 0 against, 0 abstentions RESOLVED that Cabinet – (a) confirms it has read, understood and taken account of the Well-being Impact Assessment (Appendix 2 to the report) as part of its consideration, and (b) approves the release of the previously agreed £5m capital funding to contribute to the building of phase 2 Llys Awelon Extra Care Housing.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of meeting 24th November 2020

Lead Member / Officer Cllr Bobby Feeley / Phil Gilroy

Report author Emily Jones-Davies

Title Llys Awelon Phase 2

1. What is the report about? 1.1. To request release of the previously agreed £5m capital to contribute to the building of phase 2 Llys Awelon Extra Care Housing, with our partners Grwp Cynefin, as identified in the Council’s Corporate Plan.

2. What is the reason for making this report? 2.1 A decision is required to release up to £5m to contribute to the building costs in partnership with Grwp Cynefin.

2.2Following SIG on the 26th September, this report will also provide information regarding the lease, savings and climate change.

3. What are the Recommendations?

3.1That Cabinet confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix 2) as part of its consideration.

3.2That the committee confirms their agreement to release the previously agreed £5m capital funding.

4. Report details 4.1 In 2010 Denbighshire jointly commissioned a 21 Unit Extra Care unit with Grwp Cynefin. The scheme adjoins Awelon Care Home and shares communal facilities. 4.2 In 2020 Awelon Care Home closed down, along with Canolfan Awelon, in preparation of the 2nd phase of the scheme, which consists of 35 additional Units (17 x 1 bed, 17 x 2 bed & one guest suite). Planning permission has been sought to include communal facilities and a community resource.

4.3The existing lease for phase 1 of the development will be terminated, and a new long term lease will be issued to Grwp Cynefin for the whole site (both phases).

4.4In order for the pre-investigative works to take place a short term lease is being drawn up by DCC with Grwp Cynefin. This will release DCC from its liabilities for the empty property.

4.5Creating the lowest possible energy profile to deal with climate change is at the heart of the sustainability approach. The project will be taking a ‘fabric first’ approach with high levels of insulation and natural ventilation and will be aspiring for a BREEAM Excellent rating

4.6To achieve a BREEAM rating the building owner will have to prove to the Assessor (Building Research Establishment) that they have taken a sustainable approach to procurement, will be monitoring the energy and water consumption pre and post construction, have resourced the materials responsibly and mitigated any ecological development

4.7By advocating a robust approach, materials wherever possible will be chosen carefully for their green sustainability credentials, long life and positive appearance. Build-up of elements will seek to achieve the lowest possible U-values as follows:

 Beam and insulating block suspended ground floors = 0.11  Triple glazed windows = 0.7  Rendered external masonry walls = 0.12  Trussed rafter roof with fully Integrated PV = 0.08/0.09

4.8The partnership agreement will clearly state that DCC’s contribution will not exceed £5m. Grwp Cynefin will need to review the scale of the project to ensure the costs are within budget if the tender prices exceed original estimates. 5. How does the decision contribute to the Corporate Priorities?

5.1The provision of supported living services for Older People, supports the current corporate priority that vulnerable people are protected and are able to live as independently as possible. It will also support people and communities to build independence and resilience.

6. What will it cost and how will it affect other services?

6.1Following the closure of Awelon Residential Home, part of the cost savings will be used to fund the expanded Domiciliary Staff team, currently employed in Llys Awelon (Phase 1). The Corporate Utility budgets will also benefit from the electricity, gas & water savings (£42k).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LLYS AWELON: APP 1Appendix 103 KB Download
PDF
LLYS AWELON: APP 2 WBIAAppendix 114 KB Download
PDF
LLYS AWELON PHASE 2Report 229 KB DownloadRead as text

At this meeting

Whole meeting

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open