Resolved

Vote taken: 7 in favour, 0 against, 0 abstentions RESOLVED that Cabinet – ( a ) agrees to the Joint Archive Service submitting a bid to the next stage (Round 1) of the NLHF Heritage Horizon Fund; (b) notes the potential call on £2,034,521 of Council funds in order to deliver the new archive centre . This is subject to the bid being successful at the Round 1 stage of the NLHF grant application process and receipt of a form offer of funds, and (c) endorses the approach to Ruthin Gaol and the planned expansion of the heritage attraction, as outline in section 4.8 of the report.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of meeting 24th November 2020

Lead Member / Officer Cllr Tony Thomas – Lead Member for Housing & Communities Alan Smith – Head of Business Improvement & Modernisation

Report author Craig Berry – Business Information Team Manager

Title Denbighshire and Flintshire Joint Archive Project

1. What is the report about? 1.1 This report is about a proposal for a new purpose built Passivhaus Archive building in Mold, to house the newly formed Denbighshire and Flintshire Joint Archive Service. The new archive centre is subject to securing National Lottery Heritage Fund (NLHF) grant funding and match funding from both Councils.

2. What is the reason for making this report?

2.1Approval is sought to submit a Round 1 application to the NLHF.

3. What are the Recommendations? 3.1 Cabinet agrees to the joint Archive Service submitting a bid to the next stage (Round 1) of the NLHF Heritage Horizon Fund.

3.2To note the potential call on £2,034,521 of Council funds in order to deliver the new archive centre. This is subject to the bid being successful at the Round 1 stage of the NLHF grant application process and receipt of a firm offer of funds.

3.3Cabinet endorses the approach to Ruthin Gaol and the planned expansion of the heritage attraction, as outlined in section 4.8. 4. Report details 4.1 Both Councils have legislative duties to collect, preserve and make accessible documents of historical importance. Flintshire (FCC) and Denbighshire (DCC) councils are facing several challenges that are affecting their ability to meet these legislative requirements and have been working collaboratively over the last couple of years on creating a more sustainable and improved archive service for the region. This has resulted in the launch of a single shared service, initially over 2 sites – Hawarden & Ruthin. The joint service has developed an NLHF Heritage Grant Horizons bid to fund both the construction of a new purpose built Passivhaus building adjacent to Theatr Clwyd in Mold and an associated 3-year activity plan.

4.2The proposed site in Mold was selected from a site feasibility `study, which was conducted by an independent consultant (executive summary shown in Appendix E).

4.3Key milestones are set out below:

October 2019 NLHF Heritage Horizon Award - Expression of Interest February 2020 NLHF Heritage Horizon Fund Award –Presentation April 2020 Launch of joint archive service Feb 2021 NLHF Heritage Horizon Award - Round 1 submission due June 2021 NLHF decision on grant award

4.4NEED

4.4.1 The Archive Service within DCC occupies 70% of Ruthin Gaol with the Council’s Heritage Service running a visitor attraction in the remaining 30%. It is an old building, designed for incarceration, with significant running/maintenance costs and operational inefficiencies. The proposed move to a new purpose built Passivhaus archive centre would allow DCC to avoid certain costs. These are detailed in Appendix D but the most significant costs are set out below:

I. The archive service is expected to run out of space in 2 years’ time and there is very little scope for expansion on site. Costly commercial external storage and retrieval services would then have to be considered. II. The environmental management system at the Gaol is coming to the end of its lifecycle. Replacement will cost in the region of £65k. III. Air cooling equipment will require replacing within the next few years and estimates suggest that these will cost in the region of £650k. IV. Total building running costs of £70k per annum and are increasing each year. 4.4.2 It’s estimated that the investment needed for the archive service to remain at the Gaol will prove more expensive by 2035 than the £2 million required for the new build.

4.5AMBITION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DENBIGHSHIRE AND FLINTSHIRE JOINT ARCHIVE PROJECTReport 249 KB DownloadRead as text
PDF
JOINT ARCHIVE PROJECT: APP A LETTERS OF SUPPORTAppendix 623 KB Withheld: personal details
PDF
JOINT ARCHIVE PROJECT: APP B WBIAAppendix 2.2 MB Download
PDF
JOINT ARCHIVE PROJECT: APP C PROJECT RISK REGISTERAppendix 68 KB Download
PDF
JOINT ARCHIVE PROJECT: APP D PROJECT BENEFITSAppendix 127 KB Download
PDF
JOINT ARCHIVE PROJECT: APP E SITE FEASIBILITY REPORTAppendix 282 KB Download

At this meeting

Whole meeting

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open