Planning Committee, Wednesday 12 January 2022 at 9.30am

APPLICATION NO. 46/2019/0806 - BOD HAULOG, THE ROE, ST ASAPH

Decided Planning 2 papers

Planning Committee decided this item on Wednesday 12 January 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED that permission be GRANTED contrary to officer recommendations detailed within ... view the full minutes text for item 6.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Planning Committee

46/2019/0806

Graddfa / Scale: 1:1250

Canol / Centre: 303229, 374594

Dyddiad / Date: 2021-12-23 15:39:27

© Hawlfraint y Goron a hawliau cronfa ddata 2021 Arolwg Ordnans 100023408 © Crown copyright and database rights 2021 Ordnance Survey 100023408 Location plan extract Site map Proposed access plan Indicative layout plan Site frontage along the Road where access is proposed Existing dwelling View from within site towards side / rear of existing dwelling Outbuilding within site Outbuilding within site Outbuilding within site View from within site View from site towards neighbouring dwelling From within site towards neigbouring dwelling From within site towards neigbouring dwelling From within site towards neigbouring dwelling Denise Shaw WARD : St Asaph West

WARD MEMBER(S): Cllr Peter Scott

APPLICATION NO: 46/2019/0806/ PO

PROPOSAL: Development of 0.75 ha of land for residential purposes (outline application including access)

LOCATION: Bod Haulog The Roe St Asaph LL17 0LY

APPLICANT: Drs Oliver & Robert Prys-Jones

CONSTRAINTS: C1 Flood Zone B Flood Zone

PUBLICITY Site Notice - Yes UNDERTAKEN: Press Notice - Yes Neighbour letters - Yes

REASON(S) APPLICATION REPORTED TO COMMITTEE: Scheme of Delegation Part 2  Member request for referral to Committee

CONSULTATION RESPONSES: ST ASAPH CITY COUNCIL – No objections.

NATURAL RESOURCES WALES: NRW raised concerns with the proposal on grounds of unacceptable flood risk impacts in the original consultation response and have been consulted several times throughout the course of the application following the submission of amended and additional flood consequences assessment information.

The final NRW re-consultation response with respect to flood risk is as follows:

Flood Risk The planning application proposes highly vulnerable development (residential) within Zone C1 as defined by the Development Advice Map (DAM) referred to under Technical Advice Note (TAN) 15: Development and Flood Risk (July 2004). NRW Flood Risk Map confirms the site to be located within the 1% (1 in 100) and 0.1% (1 in 1,000) annual exceedance probability (AEP) event flood outlines. The site is also shown to be within the historical flood outline for the 2012 flood event.

The site is currently occupied by a single dwelling and undeveloped land. The development proposal is for residential development, consisting of 22-31 dwellings and would therefore constitute an intensification of use at the site.

The modelling work undertaken by JBA, which is presented in the most recent iteration of the Flood Consequences Assessment (FCA) (ref: 2019s0037 - Bod Haulog - FCA V6.docx), demonstrates that the proposal would result in increases in flood risk elsewhere, both in the 1% Annual Exceedance Probability (AEP) event with an allowance for climate change and the 0.1% AEP event, in overtopping and breach scenarios. The increase in flood risk would impact residential properties, commercial buildings, the library, and general infrastructure. In the 0.1% AEP breach event, flood depths over a large area to the east of the site are shown to be increased by between 100 to 150mm, with some properties along The Roe shown to have increased flood depths of over 150 mm as a result of the proposed development.

The FCA therefore confirms that offsite flooding is in excess of the tolerable limit described in our guidance (Natural Resources Wales / Modelling for Flood Consequence Assessments), which indicates that any detriment to third parties should be less than 5 mm, due to resolution used in the model.

Given the offsite impacts resulting from the development, the proposal fails to comply with the requirements of A1.12 of TAN15, which requires no flooding elsewhere. This will need to be an important factor for your Authority to consider in determining the application.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
46_2019_0806Report 3.1 MB DownloadRead as text
PDF
APPLICATION NO. 46/2019/0806: BOD HAULOG, THE ROE, ST ASAPHReport 6 KB Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. APPLICATION NO. 46/2019/0806 - BOD HAULOG, THE ROE, ST ASAPHThis decision
  2. Application no. 41/2023/0798 - manninagh, bodfariDecided
  3. Application no. 40/2024/1141 - ysbyty glan clwyd, bodelwyddanDecided
  4. Application no: 41/2024/0115 the warren, bodfari, denbighDecided
  5. Planning conditions report: application reference number 09/2023/0669 - outbuildings at hafod y parc, bodfariApproved
  6. Application no. 40/2023/0473/pf - glan clwyd hospital, rhuddlan road, bodelwyddanDecided

More from Denbighshire Planning Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 MINUTESthat the minutes from the meeting held on the 15 July 2026 be received and approved as a true and correct record of t... Approved Open
15 Jul 2026 MINUTESthat the minutes from the meeting held on the 17 June 2026 be received and approved as a true and correct record of t... Approved Open
17 Jun 2026 MINUTESthat the minutes of the Planning Committee meeting held on the 13 May 2026 be received and approved as a true and cor... Approved Open
13 May 2026 Appointment of chairRESOLVED that Councillor Mark Young be appointed Chair of the Planning Committee for the 2026/27 municipal year. Decided Open
13 May 2026 Appointment of vice-chairRESOLVED that Councillor Alan James be appointed Vice-Chair of the Planning Committee for the 2026/27 municipal year. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies