RESOLVED that the application for the for the erection of a 90m meteorological mast for a temporary period of three years at Land at Mynydd Mynyllod, Llandrillo, Corwen be deferred to a future meeting for the reasons set out by Councillor Gwyneth Ellis above.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
PROPOSAL: Erection of a 90m meteorological mast for a temporary period of three years
LOCATION: Land at Mynydd Mynyllod Llandrillo Corwen
APPLICANT: [name removed] RWE Renewables
CONSTRAINTS: PROW Phosphorus Sensitive SAC
PUBLICITY Site Notice - No UNDERTAKEN: Press Notice - No Neighbour letters - Yes
REASON(S) APPLICATION REPORTED TO COMMITTEE: Scheme of Delegation Part 2 Recommendation to grant / approve – Town / Community Council objection
CONSULTATION RESPONSES: LLANDRILLO COMMUNITY COUNCIL - The CC are objecting to this proposal as it’s detrimental to the landscape
CLWYDIAN RANGE AND DEE VALLEY AREA OF OUTSTANDING NATURAL BEAUTY JOINT ADVISORY COMMITTEE “The Joint Committee has no observations to make on this application subject to removal of the mast and reinstatement of the land after three years. Please note that this does not confer any support for future wind farm development at the site should the prospective DNS application for the Gaerwen Wind farm be progressed.”
NATURAL RESOURCES WALES Original consultation response:
Advised further information is required to address concerns regarding water quality. In the absence of additional information being provided, NRW would object to the proposal.
Water Quality The erection of the mast will disturb the local land and will include excavation. The nature of heavy plant and potential impacts from the plant to the local environment including the potential for ground compressibility and disturbance of local ground materials have not been provided within the Method Statement (included within the Ecological Statement). The potential constraint of encountering groundwater within the excavation works has not been mentioned/discussed. Hydraulic control may be required, which depending on the method used, may result in dewatering effects away from the excavation area. Therefore, NRW advise that further information is sough from the applicant with regards to the above.
Ornithology The site is located within 2.5km of the Berwyn Special Protection Area (SPA), where the site is characterised for supporting nationally important numbers of four breeding birds. Providing the works are carried out in accordance with the methods laid out within the Ecological Statement then NRW would have no concerns. Advised the Ecological Statement should be listed as an approved document and they would encourage the construction works to be carried outside of the breeding season.
Landscape The site lies approximately 4.5km from the boundary of Clwydian Range and Dee Valley AONB, and 5.5km from Snowdonia National Park. NRW consider the new structure would not cause significant visual effect upon views from these designated landscapes or introduce intrusive/inharmonious development which could erode the setting of these valued landscapes.
Therefore have no objection, subject to a planning condition requiring the removal of temporary mast at the end of the approved period and making good of any disturbed ground.
Re-consultation response: NRW note the submission of supplementary information, but remain of the opinion that insufficient information has been provided water quality
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.