Cabinet, Tuesday 15 February 2022 at 10.00am

QUEEN'S BUILDINGS RHYL - REQUEST FOR ADDITIONAL FUNDING

Approved Executive 4 papers

Cabinet approved this item on Tuesday 15 February 2022. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that Cabinet approves the updated business case and the allocation of additional funding to the project as detailed in section 6 and 9 of the report.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of meeting 15th February 2022

Lead Member / Officer Cllr Hugh Evans OBE Leader of the Council Lead Member for the Economy and Corporate Governance

Cllr Julian Thompson-Hill Deputy Leader of the Council Lead Member for Finance, Performance and Strategic Assets

Report author Russell Vaughan

Title Queen’s Buildings Rhyl – Request for additional funding

1. What is the report about? This report has been produced to update Cabinet on the Queen’s Buildings Rhyl project, approve the updated business case and to seek additional funding to deliver Phase 1.

2. What is the reason for making this report? To update Cabinet on the Queen’s Buildings Rhyl project, seek approval of the updated business case and for additional funding to deliver Phase 1.

3. What are the Recommendations? That Cabinet approves the updated business case and the allocation of additional funding to the project as detailed in sections 6 and 9.

4. Report details In March 2019, Denbighshire County Council acquired a number of adjacent buildings in Rhyl town centre on the seafront, known collectively as Queen’s Buildings. The buildings were in a dilapidated state, with no active uses on upper floors (the seafront buildings are four storeys) and significant areas of vacant floor space at the ground floor level. Towards the end of 2020 the Council developed ambitious plans for a mixed use, phased development of the site. All buildings other than the Queen’s Chambers on the Sussex Street frontage have now been demolished and a full Planning approval for Phase I and an outline approval for subsequent phases was granted at the Planning Committee in September 2021.

At the Cabinet meeting held on 28th April 2021, approval was given to appoint a contractor to deliver Phase 1 via Lot 3 of the North Wales Construction Partnership Framework. Wynne Construction were successful and have been progressing the project from RIBA Stage 3 to produce a technical design. A report will be brought to the March 2022 Cabinet for approval to let the construction contract to Wynne as per the original approval.

The cost of delivering the whole of Phase 1 was originally estimated at £10,922,261 but the first iteration of the Stage 3 cost plan would have resulted in the out turn being significantly more expensive. An extensive value engineering exercise has been carried out to bring the costs down but it has not been possible to deliver the scheme within the existing funding envelope. One of the reasons for this is that there is a stipulation in the Planning approval requested by Natural Resources Wales (NRW) that the finished floor level of the entire building has to be raised by 740mm. This obviously affects the amount of material required to physically raise the building, but has also meant that the design of the building has had to be changed to reflect this but also to ensure that the building remains accessible for all users. Multiple meetings were held with NRW to try and minimize the requirement to raise the level of the Phase 1 development but to no avail. Another reason for the increase in cost is the inflation in the cost of construction materials due to global pressures. For example, the cost of glass and aluminium alone has increased by at least 20% due to the amount of energy required in production. A breakdown of the variance in the estimate cost is attached as Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
QUEEN'S BUILDINGS RHYL: REQUEST FOR ADDITIONAL FUNDINGReport 332 KB DownloadRead as text
PDF
QUEENS BUILDINGS: APP 1 COST VARIANCEAppendix 371 KB Download
PDF
QUEENS BUILDINGS: APP 2: reprofiled budgetAppendix 452 KB Download
PDF
QUEENS BUILDINGS: APP 3: REVISED BUSINESS CASEAppendix 945 KB Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. QUEEN'S BUILDINGS RHYL - REQUEST FOR ADDITIONAL FUNDINGThis decision
  2. Queens buildings phase 1 - construction contract awardApproved
  3. Queens buildings rhyl - phase 1 procurementApproved

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies