RESOLVED that Cabinet – (a) note the findings of the formal consultation to increase the capacity from 116 to 220 at Ysgol Plas Brondyffryn; (b) approve the publication of a statutory notice for Denbighshire County Council to increase the capacity from 116 to 220 at Ysgol Plas Brondyffryn from 28 April 2025. The implementation of the proposal will be subject to a site being agreed, planning consent being given, finance being available and the new build being ready, and (c) confirms that it has read, understood and taken account of the Well-being Impact Assessment, as detailed in Appendix 1 to the report, as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr.Gill German / Geraint Davies
Report author Lisa Walchester/ Carwyn Edwards
Title Ysgol Plas Brondyffryn Project - School Organisation formal consultation report
1. What is the report about? 1.1. This report is to inform Cabinet Members of the findings of the formal consultation in regards to Denbighshire County Council increasing Ysgol Plas Brondyffryn’s capacity from 116 to 220.
2. What is the reason for making this report? 2.1. To enable the required approvals to be gained to progress the Ysgol Plas Brondyffryn project to the next stage.
3. What are the Recommendations? Cabinet are asked:
3.1To note the findings of the formal consultation to increase the capacity from 116 to 220 at Ysgol Plas Brondyffryn;
3.2To approve the publication of a statutory notice for Denbighshire County Council to increase the capacity from 116 to 220 at Ysgol Plas Brondyffryn from 1st September 2024 subject to the new build being ready;
3.3That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment, Appendix 1, as part of its consideration 4. Report details 4.1. This is a Band B project in the Welsh Governments Sustainable Communities for Learning programme, previously 21st Century Schools and College programme. Commitment to this proposal was outlined in a revised Strategic Outline programme, which was approved by Welsh Government in September 2020. The programme included an overall allocation of £23.8m for this project. As this project is for a special school Welsh Government, subject to the approval of the relevant Business Cases, will provide 75% of the funding with the remaining 25% to be provided by Denbighshire as per the Corporate Plan commitments.
4.2Ysgol Plas Brondyffryn is a 3-19 school which provides specialist provision for pupils with autism. The proposal is to bring 3 of the 4 current sites in Denbigh together in a purpose built building and to increase the capacity of the school as demand for these specialist places increase.
4.3The proposed site for the new build is the field next to Denbigh Leisure centre and currently used by Denbigh High School. It is owned by the Local Authority.
4.4In total we received 93 responses during the consultation- 89 online responses forms and 4 emails- plus a response from Estyn. Of the 93 responses received 71 were for the proposal, 18 against and 4 did not state either way.
4.5The main issues against the proposal are the location proposed for the new build including loss of green space, impact on Denbigh High school losing one of their playing fields and traffic concerns. There were no objections regarding the increase in capacity at the school. The location of the new build is a planning issue and this will be subject to the planning process. In regards to Denbigh High they currently have another field which is underused and survey works are ongoing to establish what improvement works are needed on this field to ensure the school can continue to deliver all elements of the PE curriculum. Please see Appendix 2 for further details.
4.6Members need to consider the consultation report and the supporting documents which have been produced following the formal consultation period. For ease of reference these are detailed below:
Appendix 2 contains the Formal Consultation Report. In this report we have; o Summarise each of the issues raised by consultees; o Respond to these issues by means of clarification; o Set out Estyn’s view of the overall merits of the proposal.
The formal consultation report document contains the following Appendices:
Appendix A- Consultation Document recipient list
Appendix B- Summary of comments/ questions raised in meetings
Appendix C- School Council findings
Appendix D- Full Governing Body response
Appendix E- Summary of responses received via email
Appendix F- Summary of responses via the Formal Consultation Response form
Appendix G- Estyn Response
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.