Resolved
RESOLVED that Cabinet note the updated engagement activity and approve the appointment of the Contractor, Kensa to proceed with the design stage of the project. [This stage of the project will take 12 – 16 weeks.]
Cabinet noted this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Cabinet note the updated engagement activity and approve the appointment of the Contractor, Kensa to proceed with the design stage of the project. [This stage of the project will take 12 – 16 weeks.]
Report to Cabinet
Date of meeting 18th October 2022
Lead Member / Officer Rhys Thomas – Lead Member Housing & Communities/David Lorey – Lead Officer Corporate Property & Housing Stock
Report author Katrina Allen – Senior Architect / Mark Cassidy – Property Operations Manager
Title District Heating System Betws Gwerfil Goch
1. What is the report about? 1.1. The potential of a district heating system for the Village of Betws Gwerfil Goch incorporating the provision of ground source heat pumps (GSHP) to Council and Privately owned dwellings.
2. What is the reason for making this report? 2.1. To update Cabinet on the community engagement during August/September 2022 and the proposal to appoint Kensa as the approved contractor for the design stages.
3. What are the Recommendations?
3.1That the Cabinet note the updated engagement activity and approve the appointment of the Contractor, Kensa to proceed with the design stage of the project. This stage of the project will take 12-16 weeks.
4. Report details 4.1. In December 2021 the Welsh Government invited bids for round 2.1 of the Optimised Retrofit Programme. Denbighshire had already secured circa £4Million from previous bids in 2020/21 and 2021/22 4.2. An opportunity to extend the offer to private home owners in off gas/hard to heat areas was put forward for the Village of Betws Gwerfil Goch. The rationale for choosing the village was based on the poorly performing properties (thermally), the lack of mains gas supply (increasing heating costs) and the relatively difficult circumstances of delivering a scheme in a remote area (the thinking being if we can deliver here, we can deliver almost anywhere within DCC)
4.3A technical partner was selected via procurement off a Welsh Procurement Alliance framework (Kensa) and initial feasibility studies produced which supported the viability of the scheme.
4.4In January 2022, Welsh Government approved funding for the scheme, recognising the innovation aspect of a whole village approach. Grant funding was awarded on the understanding that the project would be delivered during 2022/2023
4.5It was recognised that this would be a challenge by all and that community engagement would be key to successful delivery – not least to give confidence to private home owners that the proposals represent good financial and environmental benefits.
4.6Stage 1: consultation and engagement plan was initiated week commencing 7th Sept which included a parish community meeting, information letters/leaflets, roadshows, door knocking, website sign up with unique owner codes and a public engagement session in the local Chapel etc.
4.7Stage 1 engagement activity is almost complete. (Focusing on sign ups) which now allows us to carry out in depth surveys, design work and costs which will be developed by Kensa. To date, we have 26 interested residents, 4 residents have refused, 7 have indicated they need more information and no response yet from 17 homes. (we have some empty properties in the village) Further engagement/door knocking will continue while the Design Survey is ongoing.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DISTRICT HEATING SYSTEM BETWS GG: APPENDIX 1 WBIAAppendix | 103 KB | Download |
PDF |
DISTRICT HEATING SYSTEM BETWS GWERFIL GOCHReport | 152 KB | DownloadRead as text |
Follow Cabinet at Denbighshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jul 2026 | ApologiesChief Executive | Decided | Open |
| 28 Jul 2026 | Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 | Decided | Open |
| 28 Jul 2026 | Urgent mattersNo urgent matters had been raised. | Decided | Open |
| 28 Jul 2026 | MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. | Decided | Open |
| 28 Jul 2026 | Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.