Cabinet, Tuesday 28 March 2023 at 10.00am

TERMINATION OF THE CONTRACT FOR A MAIN CONTRACTOR FOR THE WASTE DEPOT PHASE 2

Noted Executive 2 papers

Cabinet noted this item on Tuesday 28 March 2023. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

RESOLVED that Cabinet note the urgent delegated decision referred to in paragraph 2.1 of the report.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Date of meeting 28th March 2023

Lead Member / Officer Cllr Barry Mellor, Lead Member for the Environment and Transport / Tony Ward, Corporate Director: Environment and Economy

Report author Tony Ward

Title Termination of the contract for a main contractor for the Waste Depot Phase 2

1. What is the report about?

1.1The decision to terminate the contract between Denbighshire County Council (DCC) and R L Davies & Sons Ltd (RLD) for RLD to be the main contractor for the Waste Depot Phase 2 on the Colomendy Estate, Denbigh.

2. What is the reason for making this report?

2.1To formally report to Cabinet, in writing, that the Corporate Director: Environment and Economy made an urgent decision on 20th February 2023, under 2.9 of the Council’s constitution, to terminate the contract between DCC and RLD for them to act as the main contractor for the Waste Depot Phase 2 on Colomendy Estate, Denbigh. The constitution allows for an urgent delegated decision to be made where such a decision could not wait until the first available meeting of Cabinet.

2.2To confirm how the decision to award the contract to RLD was made.

2.3To update Cabinet on what has happened since RLD went into administration in relation to the construction of the depot. 2.4. To confirm that a subsequent report will be brought to Cabinet (currently scheduled for 25th April 2023), so that the Project Board can recommend the preferred option for completing the construction of the depot.

3. What are the Recommendations?

3.1That Cabinet note the urgent delegated decision referred to in paragraph 2.1.

3.2That Cabinet consider the report and provide feedback, as appropriate.

4. Report details

Termination of the contract

4.1RLD entered Administration on Thursday 16th February 2023. After obtaining the necessary approvals, a Termination Notice was served on RLD and their appointed Administrator on Monday February 20th, which terminated the Contract between DCC and RLD.

4.2The loss of RLD leaves Phase 2 without a Main Contractor. Once we issued the termination notice, the Main Contactor role reverted to DCC.

How the contract award was made

4.3The decision to award the contract was delegated to the Chief Executive by Cabinet on 12th April 2022. The local elections in May 2022, and the uncertain timescale for establishing a new Cabinet, could have caused a delay in awarding the contract. Any delay in awarding the contract would have delayed the project and would almost certainly have resulted in additional costs to the council. Once the tender exercise was completed, the Chief Executive was required to exercise the powers delegated to him by Cabinet to award the contract.

4.4As the delegated decision was made on 17th June 2022, i.e. after a new Cabinet had been formed, the Chief Executive took account of comments provided by the new Leader (Cllr Jason McLellan) and new Lead Member for Environment and Transport (Cllr Barry Mellor) when making the decision to award the contract to RLD. The Chief Executive also took note of comments provided by the S151 Officer (Steve Gadd) and the Monitoring Officer (Gary Williams). 4.5. In terms of the tender process, DCC has a declared Tender Evaluation Criteria that it must follow and comply with. The Quality (40%) / Cost (60%) scores are combined in the declared calculation methodology to come up with the final ranking. In this case, RLD were ranked 1st out of the four tenders submitted.

4.6As part of the tender evaluation, a “Dunn & Bradstreet” (D&B) finance check is undertaken to help understand the financial standing of the organisations. This process allocates a score (0 to 5) based on how far below the industry average the D&B score is. If any D&B score is below 11 (which scores 0), that tender can be legitimately set aside. RLD scored 1, based on a D&B Score of 18, and therefore passed the required/published threshold in terms of the financial test.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TERMINATION OF THE CONTRACT FOR A MAIN CONTRACTOR FOR THE WASTE DEPOT PHASE 2Report 155 KB DownloadRead as text
PDF
WASTE DEPOT PHASE 2 REPORT: APPENDIX 1 SCORING MATRIXAppendix 184 KB Download

At this meeting

Whole meeting

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies