RESOLVED that Cabinet – (a) note the budgets set for 2022/23 and progress against the agreed budget strategy; (b) approve the match-funding requirement for the Clwyd West Levelling Up Grant programme as detailed in Section 6.8 of the report and Appendix 5 to the report, and (c) approve the ‘Four Great Highways’ project as part of the Clwyd South Levelling Up Grant programme, as detailed in Section 6.9 of the report and Appendix 6 to the report.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Councillor Gwyneth Ellis, Lead Member for Finance, Performance and Strategic Assets / Steve Gadd, Head of Finance and Property
Report author Steve Gadd, Head of Finance and Property
Title Finance Report (February 2022/23)
1. What is the report about? The report gives details of the council’s revenue budget and savings as agreed for 2022/23. The report also provides a summary update of the Capital Plan as well as the Housing Revenue Account and Housing Capital Plan.
2. What is the reason for making this report? The purpose of the report is to provide an update on the council’s current financial position and confirm the agreed service budgets for 2022/23.
3. What are the Recommendations? 3.1 Members note the budgets set for 2022/23 and progress against the agreed strategy.
3.2Members approve the match-funding requirement for the Clwyd West Levelling Up Grant programme, as detailed in section 6.8 and Appendix 5. 3.3 Members approve the ‘Four Great Highways’ project as part of the Clwyd South Levelling Up Grant programme, as detailed in section 6.9 and Appendix 6.
4. Report details The report provides a summary of the council’s revenue budget for 2022/23 detailed in Appendix 1. The council’s net revenue budget is £233.696m (£216.818m in 21/22). The position on service and corporate budgets is a forecast overspend of £2.846m (£2.249m overspend last month). The increase of £0.6m is due to additional pressures within Children services and Highways and Environmental services. All services continue to review their areas to mitigate the impact of the overall budget overspend. The budget mitigation reserve will cover this level of overspend in the current year. Narrative around the current risks and assumptions underlying this assessment are outlined in Section 6 and Appendix 2.
The 2022/23 budget required service savings and efficiencies of £0.754m to be identified and these are assumed to have been achieved.
5. How does the decision contribute to the Corporate Priorities? Effective management of the council’s revenue and capital budgets and delivery of the agreed budget strategy underpins activity in all areas, including corporate priorities.
6. What will it cost and how will it affect other services? Significant service narratives explaining variances and risks are detailed in Appendix 2, however the following should also be noted:
6.1Corporate Budgets – A contingency of £1.9m was agreed as part of the budget for 22/23 to fund any ongoing impact of the pandemic, and in recognition of the increases in inflation at the time the budget was set. It is estimated that corporate contingencies amounting to £1.546m can be released; which includes £700k of the contingency detailed in 6.1 and £230k due to travel savings from new ways of working. Details relating to other risks are still being analysed: Pay settlements for 2022/23 – funds have been vired to services to fund the increase for those pay awards have been agreed. Although ‘final offers’ have been made, the pay settlement for teachers has yet to be agreed. Call on contingencies relating to energy and other inflationary pressures (see 6.1)
These will be reviewed when the final outturn is known.
6.2Education and Children’s Service – The current outturn prediction is £3.437m overspend (previously £2.999m). Although an additional pressure of £750k was accepted as part of the agreed budget for 2022/23 this remains an area of concern. The majority of the pressure (£3.255m) relate to children’s placements, which have either commenced this financial year or are now projected to continue longer than previously predicted. The Education service overspend (£182k) relates to Out-of-County budget pressure of £704k due to a reduction in number of pupils from other Councils attending DCC facilities, offset by grant maximisation and small efficiencies across the service (see Appendix 2 for further details).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.