RESOLVED that Cabinet – (a) approve the award of a Contract to the preferred supplier for the operation of the Queen’s Market based on the Project Board recommendations and detail of the Contract Award Recommendation Report (Appendix 1 to the report), and (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 2 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Jason McLellan: Lead of the Council Tony Ward: Corporate Director, Environment and Economy
Head of Service Emlyn Jones: Head of Planning, Public Protection & Countryside Services
Report author Russell Vaughan
Title Queen’s Market- procurement of an operator
1. What is the report about? 1.1. Seeking the approval of Cabinet to award a Contract to the preferred supplier for the operation of the Queen’s Market.
2. What is the reason for making this report? 2.1. A decision is required to award a Contract to the preferred supplier for the operation of the Queen’s Market based on the Project Board recommendations as per the Contract Award Recommendation Report (Appendix 1).
3. What are the Recommendations? 3.1 That Cabinet approve the award of a Contract to the preferred supplier for the operation of the Queen’s Market based on the Project Board recommendations and detail of the Contract Award Recommendation Report.
3.2That the Committee confirms that it has read, understood, and taken account of the Well-being Impact Assessment (Appendix 2) as part of its consideration. 4. Report details 4.1. Denbighshire County Council are in the process of constructing Phase I of the Queen’s Buildings site in Rhyl, which is the new food / market hall and flexible events space. The Council do not have the capacity or knowledge to run a facility of this kind, so an operator is needed to run the facility on our behalf.
4.2A Delegated Decision was approved in April 2022 (Appendix 3) to commence the procurement process to appoint an operator to run and manage the Queen’s Market once developed. An advert was published on Sell2Wales in November 2022 and ran for five weeks, but unfortunately no submissions were received.
4.3Feedback was sought from the fourteen companies that expressed an interest in the opportunity either via Sell2Wales (PROACTIS) or the Rhyl Regeneration microsite, and an options appraisal produced. The Project Board decided on a second attempt at going out to the market, but with a modified two-stage procurement approach.
4.4Prospective suppliers were asked to express their interest, with these suppliers then being sent all relevant tender information. Following the evaluation process, a preferred supplier was selected and recommended by the Project Board (Appendix 4). The preferred supplier has since satisfied all the Council’s hardgate and due diligence checks (Appendix 5).
4.5The Project Board is now recommending that the Council appoint the preferred supplier and work with them to deliver the final fit out of the Queen’s Market and to agree a strategy and timeline for opening to the public.
5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. The decision will contribute to the delivery of the Corporate Priority to achieve a prosperous Denbighshire by:
Supporting economic growth; and
Developing a plan to grow Denbighshire’s businesses in the future. 6. What will it cost and how will it affect other services? 6.1. To get to this point in the process, a cross-departmental project team have been meeting very regularly to ensure that, whoever is appointed, all relevant departments who may be impacted in any capacity in the future are fully aware and involved in the process. They include Contracts Management, Procurement, Legal, Economic & Business Development (EBD) and Property.
6.2£30k of revenue funding was made available to help fund any consultants, marketing or advertising needed, but the main cost is the time of the officers involved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.