Denbighshire County Council
Cabinet, Tuesday 28 April 2026 at 10.00am

SALT BARNS (NORTH) - PROGRESSION TO APPOINT CONTRACTOR

Approved Executive 2 papers

AI summaryCabinet approved awarding a £2,806,968.84 contract to build a new salt storage building at Bodelwyddan for winter maintenance in north Denbighshire.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew salt storage building at Bodelwyddan for north county
Money£2,806,968.84Revised project costs, approved September 2025
What happens nextAward the contractProceed to contractor appointment stage
Who it affectsNorth Denbighshire winter maintenanceCovers Rhyl, Prestatyn, rural north and the A55

What was decided

Cabinet approved awarding the contract to develop a new salt storage building at Bodelwyddan to support winter maintenance in the north of the county. Report P9, P7

Cabinet confirmed it had read, understood and taken account of the Well-being Impact Assessment (Appendix B). Report P9

Why

Existing salt storage at depots has caused environmental concerns and risks to the resilience of winter operations, with the new facility intended to bring sites into environmental compliance. Report 4.2, P18

The tender estimate is above the £2 million (excluding VAT) threshold, so Cabinet approval is required before the contract can be awarded. Report P8

What happens next

Proceed to award the contract to the successful tenderer following the procurement exercise. Report P7, P8, P9

Build the new salt storage facility at the Bodelwyddan depot, which sits parallel to the A55 and serves coastal and rural north Denbighshire. Report P10, 4.2

The money

  • £2,806,968.84 Revised project costs supported by Capital Scrutiny Group and Cabinet in September 2025

Options considered

  • Chosen: Award the contract to develop a new salt storage building at Bodelwyddan. Needed to address environmental compliance and secure resilience for winter maintenance Report P9, 4.2, P18

Implications

  • Legal: Risk of legal action and possible sanctions or fines if the project is not progressed in a timely manner, due to non-compliance with current environmental standards at depots. Report 10.2, P18
  • Climate: Project supports the council's climate emergency declaration and net zero aspirations by 2030, aiming to reduce carbon emissions from council assets and increase renewable energy and EV charging provision. Report P13, P14, P15
  • Financial: Risk that costs escalate in volatile markets; the project may need to be value engineered to stay within the agreed budget. Report 10.3
  • Staffing: Will provide a more efficient and safer working environment for Highways and Environmental Services staff. Report 6.2
  • Risk: Planning consent is not expected to be an issue given the lack of residential properties near the site. Report 10.4

Who and where

  • Highways and Environmental Services staff at the Bodelwyddan depot Report 6.2, 8.3
  • Residents and road users in north Denbighshire, including Rhyl, Prestatyn and rural areas Report P10
  • Users of the A55 trunk road in North and Mid Wales Report P10
  • Council depot operations across the county Report 10.2

Timeline

  • 2023: Strategic Investment Group welcomed and approved the project Report 8.2
  • 23 September 2025: Cabinet approved the business case and allocated funding for the project Report P7
  • 16 December 2025: Cabinet approved conducting the procurement tendering exercise Report P7
  • 28th April 2026: Cabinet approved awarding the contract Report P2

Plain English for the jargon

  • AMG: Asset Management Group
  • CSG: Capital Scrutiny Group
  • A55: Major trunk road running along the North Wales coast
  • North and Mid Wales Trunk Road Agency: Body responsible for managing trunk roads in the region, whose guidelines inform winter maintenance provision
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED that Cabinet – (a) approves the award of the contract in order to develop a new building to facilitate the safe and correct storage of salt for the purpose of winter maintenance operations, which are servicing the north of the county, and (b) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix B to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet, 4 pages

Report to Cabinet

Date of meeting 28th April 2026

Lead Member Cllr Barry Mellor, Lead Member for Environment and Transport

Head of Service Paul Jackson: Head of Highways & Environmental Services

Report Author Andy Clark: Works Unit and Streetscene Manager

Title Salt barns (north) – Progression to appoint contractor

1. What is the report about? 1.1. Authority is being sought from Cabinet to progress the salt barns (north) project to the appointment of a contractor following the successful completion of the tendering process. Asset Management Group (AMG) and Capital Scrutiny Group (CSG) both supported the business case, which was subsequently approved (with funding allocated) by Cabinet in September 2025 (Denbighshire County Council - Agenda for Cabinet on Tuesday, 23 September 2025, 10.00 am). The project gained further approval from Cabinet to conduct a procurement tendering exercise in December 2025 (Denbighshire County Council - Agenda for Cabinet on Tuesday, 16 December 2025 10.00 am).

2. What is the reason for making this report? 2.1. The tender estimate is above the £2 million (excluding VAT) threshold, and Cabinet approval is required to proceed to the next stage of the procurement and tendering process whereby the contract will be awarded. The Commissioning and Award Report is attached at Appendix A.

3. What are the Recommendations? 3.1. That Cabinet gives approval to award the contract in order to develop a new building to facilitate the safe and correct storage of salt for the purpose of winter maintenance operations, which are servicing the north of the county. 3.2. That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix B) as part of its consideration.

4. Report details 4.1. Among other uses, the site at Bodelwyddan runs an efficient operation in delivering the winter maintenance service for the north of the county. The site has been strategically located to cover coastal towns of Rhyl and Prestatyn as well as the more rural areas of the north of the county, more crucial though is the position of the depot being parallel to the A55 which is vital in terms of winter maintenance provision to comply with Welsh Government and the North and Mid Wales Trunk Road Agency guidelines. Given these locations are considered to be strategically well placed now and into the future, it is envisaged that there will be a long-term requirement for the continued use of the site.

4.2However, there is an underlying issue with salt storage facilities at our depots which have led to environmental concerns being raised as well as a risk to the resilience of the winter operations of the service. To that end a project was developed to address these concerns with a new salt storage facility, which is included in the Council’s Capital Plan.

5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. The proposal supports the Council’s Corporate Priority to provide a greener and better-connected Denbighshire in the following ways:

 Reduce carbon emissions from Council assets;

 Increase renewable energy and EV charging provision across the county;

 Contributes towards the council’s climate emergency declaration and net zero aspirations by 2030;

 Allows greater efficiency and flexibility within the service when carrying out winter maintenance operations. 6. What will it cost and how will it affect other services? 6.1. The revised costs of £2,806,968.84 were supported by CSG and by Cabinet in September 2025 (Denbighshire County Council - Agenda for Cabinet on Tuesday, 23 September 2025, 10.00 am).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SALT BARNS (NORTH): PROGRESSION TO APPOINT CONTRACTORReport 4 pages DownloadRead as text
PDF
SALT BARNS NORTH: Appendix B: Wellbeing Impact AssessmentAppendix 15 pages Download

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. SALT BARNS (NORTH) - PROGRESSION TO APPOINT CONTRACTORThis decision
  2. Salt barns (north) - progression to procurement commissioningApproved
  3. Salt barns (south) lon parcwr and corwenApproved

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies