SALT BARNS (NORTH) - PROGRESSION TO PROCUREMENT COMMISSIONING
ApprovedExecutive3 papers
AI summaryCabinet approved the procurement of a new salt storage building at Bodelwyddan depot to support winter maintenance in the north of the county, with revised approved project costs of £2,806,968.84.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor a new salt storage building at Bodelwyddan
Money£2,806,968.84Revised project cost approved in September 2025
What happens nextIssue tender and run procurement processSubject to Contract Procedure Rules
Who it affectsWinter maintenance in north of countyIncluding Rhyl, Prestatyn, rural areas and A55
What was decided
Cabinet approved the tendering and procurement of a new building for the safe storage of salt used in winter maintenance operations serving the north of the county. Report P8
Cabinet confirmed it had read, understood and taken account of the Well-being Impact Assessment (Appendix B) as part of its consideration. Report P9
Why
The pre-tender estimate is above the £2 million (excluding VAT) threshold, so Cabinet approval is required to move to procurement and issue a tender. Report P7
Current salt storage at depots has raised environmental concerns and risks the resilience of winter operations, prompting a new facility at the strategically located Bodelwyddan site, parallel to the A55. Report P10, 4.2
What happens next
Take the project through the procurement and tender process in line with the council's Contract Procedure Rules, and bring forward a Commissioning and Award Report (Appendix A). Report P7, P22
The money
£2,455,015.63 Sum previously approved by CSG for the project
£2,806,968.84 Revised project costs approved by CSG and Cabinet in September 2025
Options considered
Chosen: Approve tendering and procurement of the new salt storage building. Project already had business case and funding approved in September 2025; further delay risks legal action for non-compliance with environmental standards and rising costs in volatile markets. Report P8, 10.2, 10.3
Implications
Financial: Revised project cost of £2,806,968.84, already approved by Cabinet in September 2025; further delays could increase costs due to volatile markets. Report 10.3
Legal: Risk of legal action for non-compliance with current environmental standards if the project is not progressed in a timely manner. Report 10.2
Equalities: Well-being Impact Assessment (Appendix B) considered; the report states the project will have a positive overall impact. Report P9, P18
Climate: Project supports reducing carbon emissions from council assets, increasing renewable energy and EV charging, and the council's net zero aspirations by 2030. Report P13, P14, P15, P18
Risk: Planning consent considered unlikely to be an issue due to lack of residential properties nearby. Report 10.4
Other: New facility will provide a safer, more efficient working environment for Highways and Environmental Services staff and improve winter maintenance resilience. Report 6.2
Who and where
Highways and Environmental Services staff at the Bodelwyddan depot Report 6.2, 8.3
Residents and road users in coastal towns such as Rhyl and Prestatyn and rural areas in the north of the county Report P10
Users of the A55, covered under Welsh Government and North and Mid Wales Trunk Road Agency winter maintenance provision Report P10
Timeline
2023: Project taken to Strategic Investment Group, welcomed and approved Report 8.2
Tuesday, 23 September 2025: Cabinet approved the business case and revised funding of £2,806,968.84 Report P6
16th December 2025: Cabinet approved progression to procurement and tender stage Report P2
Plain English for the jargon
CSG (Capital Scrutiny Group): Council group formerly known as the Strategic Investment Group, which approved the business case and funding.
AMG (Asset Management Group): Group that supported the business case before CSG approval.
Well-being Impact Assessment: Assessment appended at Appendix B which Cabinet confirmed it had considered as part of this decision.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
RESOLVED that Cabinet – (a) approves the tendering and procurement of the project in order to develop a new building to facilitate the safe and correct storage of salt for the purpose of winter maintenance operations, which are servicing the north of the county, and (b) confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix B to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting.Source: moderngov.denbighshire.gov.uk
Lead Member / Officer Cllr Barry Mellor, Lead Member for Environment and Transport / Paul Jackson: Head of Highways & Environmental Services
Report author Andy Clark: Works Unit and Streetscene Manager
Title Salt Barns (North) – Progression to procurement commissioning
1. What is the report about? 1.1. Authority is being sought from cabinet to progress the salt barns (north) project to the procurement and tender stage. Asset Management Group (AMG) and Capital Scrutiny Group (CSG) both supported the Business Case which was subsequently approved (with funding allocated) by Cabinet in September 2025 (Denbighshire County Council - Agenda for Cabinet on Tuesday, 23 September 2025, 10.00 am).
2. What is the reason for making this report? 2.1. The pre-tender estimate is above the £2 million (excluding VAT) threshold, and Cabinet approval is required to move to the next stage of the procurement process and issue a tender. The Commissioning and Award Report is attached at Appendix A.
3. What are the Recommendations? 3.1. That Cabinet approves the tendering and procurement of the project in order to develop a new building to facilitate the safe and correct storage of salt for the purpose of winter maintenance operations, which are servicing the north of the county.
Mae'r ddogfen hon ar gael yn Gymraeg. This document is available in Welsh. 3.2. That the Committee confirms that it has read, understood and taken account of the Well-being Impact Assessment (Appendix B) as part of its consideration.
4. Report details 4.1. Among other uses, the site at Bodelwyddan runs an efficient operation in delivering the winter maintenance service for the north of the county. The site has been strategically located to cover coastal towns of Rhyl and Prestatyn as well as the more rural areas of the north of the county, more crucial though is the position of the depot being parallel to the A55 which is vital in terms of winter maintenance provision to comply with Welsh Government and the North and Mid Wales Trunk Road Agency guidelines. Given these locations are considered to be strategically well placed now and into the future, it is envisaged that there will be a long-term requirement for the continued use of the site.
4.2However, there is an underlying issue with salt storage facilities at our depots which have led to environmental concerns being raised as well as a risk to the resilience of the winter operations of the service. To that end a project was developed to address these concerns with a new salt storage facility which has been approved for funding by the Strategic Investment Group, now known as Capital Scrutiny Group (CSG).
5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. The proposal supports the Council’s Corporate Priority to provide a greener and better-connected Denbighshire in the following ways:
Reduce carbon emissions from Council assets;
Increase renewable energy and EV charging provision across the county;
Contributes towards the council’s climate emergency declaration and net zero aspirations by 2030;
Allows greater efficiency and flexibility within the service when carrying out winter maintenance operations. 6. What will it cost and how will it affect other services? 6.1. The sum of £2,455,015.63 had been previously approved by CSG for the completion of the project. The revised costs of £2,806,968.84 were approved by CSG and then by Cabinet in September 2025 (Denbighshire County Council - Agenda for Cabinet on Tuesday, 23 September 2025, 10.00 am).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.