CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Denbighshire County Council
Cabinet, Tuesday 26 May 2026 at 10.00am

COUNTY HALL LOW CARBON HEAT GRANT PROJECT

Approved Executive 2 papers

AI summaryCabinet approves acceptance of a £1.88m Welsh Government Low Carbon Heat Grant and a £2.09m procurement for energy efficiency works at County Hall, Ruthin, with spend required by 31st March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedGrant, procurement and delegated award all approved
Money£2.09m total, £1.88m grantCouncil contributes £209k (10%)
What happens nextAward contract by August or September 2026Spend must complete by 31st March 2027
Who it affectsCounty Hall, RuthinStaff, councillors, visitors, local contractors

What was decided

Cabinet approved acceptance of the £1.88m Low Carbon Heat Grant to fund an energy and carbon efficiency scheme at County Hall, Ruthin, subject to the grant being awarded. Report 3.1

Cabinet approved initiation of a single-tender procurement process for the works at a value of £2.09m, subject to the grant application being successful. Report 3.2, 2.2

Authority to award the contract after tender, within budget and the available time frame, is delegated to the Monitoring Officer in consultation with the Section 151 Officer, the Head of Corporate Support Services: Performance, Digital and Assets, and the Lead Cabinet Member. Report 3.3

Why

The grant is over £1m and the procurement is over £2m, so both need Cabinet approval; the scheme replaces end-of-life gas boilers, air handling units, windows, radiators and insulation at County Hall. Report P7, P14, 4.2

Tight Welsh Government grant timescales mean the application was made in April, an award is expected in May, and all spend must be completed by 31st March 2027. Report P8, 4.4

Without approval now, the project cannot be procured and delivered within the grant window, putting £1.88m of external funding at risk. Report 4.4, 10.2

What happens next

Subject to grant award, run a single tender via the North Wales Construction Framework Lot 2, with a pre-tender engagement session with framework contractors. Report 8.3, 4.4

Award the contract in August or September 2026 through the delegated decision, then deliver the works in phases over an estimated 30-week construction programme. Report 4.4, 6.3

Complete all grant-funded spend by 31st March 2027, with monthly contractor payments claimed against the grant sum. Report 4.4, 10.2

The money

  • £1.88 million External Low Carbon Heat Grant applied for (90% of project cost) Report 3.1, 4.3
  • £2.09m Total estimated project cost Report 3.2, P8
  • £209k Denbighshire County Council contribution (10%), from the Climate and Nature Programme capital allocation Report 4.3
  • £1,88m Grant sum applied for, as restated in cost section
  • c.£2,09m Total project cost, as stated in cost section
  • £2.090m Estimated capital cost per the Chief Finance Officer statement Report P31
  • £0.209m Council 10% capital contribution per the Chief Finance Officer statement Report P31

Options considered

  • Chosen: Accept the grant and run a single-tender procurement covering the whole project, with delegated award. Tight Welsh Government grant deadline of 31st March 2027 requires approval now and a delegated award decision to keep to programme. Report P7, 2.2, 4.4
  • Rejected: Do not proceed if the grant application is unsuccessful. Listed in risk section: if the external grant is not awarded, the project will not go ahead.

Implications

  • Financial: Council commits £209k of capital from the Climate and Nature Programme allocation set in the 2026/27 Capital Plan, with the rest funded externally. Report 4.3, P31
  • Climate: Air source heat pumps, new air handling units and upgraded windows are expected to cut carbon emissions by an estimated 48.7 tonnes per year (paragraph 4.1) and around 47.7 tonnes per year (paragraph 5.3), supporting the council's Net Carbon Zero target. Report P14, 5.3
  • Risk: Risk of grant not being awarded: project will not proceed. Risk of not finishing in time: grant funding implications, mitigated by early approval and a delegated award decision. Report 10.2
  • Risk: Risk of contractor under-performance: to be managed through frequent performance reviews and regular meetings with the successful contractor. Report 10.3
  • Staffing: Around 30 weeks of construction will cause disruption to staff, councillors and visitors at County Hall; work will be phased and coordinated with Facilities Management, staff and communications teams. Report 6.3
  • Other: Carbon Reduction Project Officers on Degree Apprenticeships will work on the project, contributing to their development. Report 5.2

Who and where

  • Staff, councillors and visitors using County Hall, Ruthin during the 30-week construction programme Report 6.3
  • Local businesses able to bid through the tender and pre-tender engagement Report 8.3
  • Career grade Carbon Reduction Project Officers on Degree Apprenticeships Report 5.2
  • Facilities Management, Building Maintenance and Design Services teams at the council

Timeline

  • End of April 2026: Grant application submitted to Welsh Government Report 4.4
  • May 2026: Grant award expected from Welsh Government Report 4.4
  • 19th May 2026: Business case reviewed at Capital Scrutiny Group Report 8.2
  • 26th May 2026: Cabinet decision to approve grant acceptance, procurement and delegated award Report P2
  • August/September 2026: Tender award planned Report 4.4
  • Approximately 30 weeks (phased): Construction programme at County Hall Report 6.3
  • 31st March 2027: Grant-funded spend must be completed Report P8, 4.4

Plain English for the jargon

  • ASHP: Air source heat pump; a low carbon heating technology that replaces gas boilers.
  • AHU: Air Handling Unit; equipment that circulates and conditions air within a building.
  • Low Carbon Heat Grant: Welsh Government grant funding the removal of gas plant and its replacement with low carbon heat, plus fabric improvements such as windows and insulation.
  • DCC: Denbighshire County Council.
  • Section 151 Officer: The council's statutory chief finance officer, responsible for proper administration of financial affairs.
  • Monitoring Officer: The council's statutory officer responsible for legality and conduct.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED that Cabinet approves – (a) the acceptance of the external Low Carbon Heat Grant (if successful) at a value of £1.88 million to deliver the County Hall, Ruthin energy/carbon efficiency scheme; (b) the initiation of the procurement process at a value of £2.09 million, subject to the Council being successful in their grant application, and (c) the decision to award the contract post tender, subject to it being within available budget and the delivery programme committed to it by the contractor being within the time frame available, be delegated to the Monitoring Officer in consultation with the Section 151 Officer, the Head of Corporate Support Services: Performance Digital and Assets, and the Lead Cabinet Member for Corporate Strategy, Policy, Equalities and Strategic Assets.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet, 5 pages

Report to Cabinet

Date of meeting 26th May 2026

Lead Member Cllr Julie Matthews

Head of Service Helen Vaughan-Evans

Report Author Martyn Smith

Title County Hall Low Carbon Heat Grant Project

1. What is the report about? 1.1. The report outlines an external grant (Low Carbon Heat Grant) that will require Cabinet to approve the acceptance of it due to the value (over £1 million) which would be used to fund an energy/carbon efficiency scheme at County Hall, Ruthin. The procurement route would be via a single tender covering the whole project. As the tender will be over £2m this requires Cabinet approve to initiate. It is for the installation of air source heat pumps (ASHP) and the replacement Air Handling Units (AHU’s), windows and radiators at County Hall.

2. What is the reason for making this report? 2.1. A Cabinet decision is required regarding the acceptance of the grant, should the application be successful as it is over £1m. The total project value is £2.09m, 90% of this will be externally grant funded (£1.88m) and must be spent by 31st March 2027.

2.2The procurement route would be via a single tender covering the whole project. As the tender will be over £2m this requires Cabinet approve to initiate.

2.3Due to grant timescales, we seek approval for the project, approval to initiate the procurement and delegated authority to award the contract post tender subject to it being within available budget and contractors able to deliver to time. These approvals will be subject to DCC being successful in being awarded the external grant. 3. What are the Recommendations?

3.1For Cabinet to approve the acceptance of the external Low Carbon Heat Grant (if successful) at a value of £1.88 million to deliver the County Hall, Ruthin energy/carbon efficiency scheme.

3.2For Cabinet to approve the initiation of the procurement process at a value of £2.09m, subject to the Council being successful in their grant application.

3.3For Cabinet to approve the decision to award the contract post tender, subject to it being within available budget and the delivery programme committed to by the contractor being within the time frame available, be delegated to Monitoring Officer in consultation with Section 151 officer and Head of Corporate Support Services- Performance, Digital and Assets.

4. Report details 4.1. The proposed project is to replace the end of life gas boilers at County Hall, Ruthin, with air source heat pumps, to replace the Air Handling Units (AHU’s), upgrade the radiators, heating pumps and building management system, replace the windows with modern energy efficient windows (with approximately half the heat loss) and draught strips and also replace areas of ceiling insulation where this has been removed during renovation work over the years. The project will decrease energy consumption, enhance the working environment, reduce future potential expenditure on replacing the end-of-life assets and decrease carbon emissions by an estimated 48.7tonnes per year.

4.2County Hall (main office) was built over 20 years ago and is now one of our most energy inefficient per square meter across the property portfolio due to key building fabric assets now being end of life. This contributes to higher than necessary carbon emissions per annum from the site.

4.3The Welsh Government Low Carbon Heat Grant funds the removal of gas plant and the replacement with low carbon heat (such as air source heat pumps) and associated ‘fabric improvements’ (such as windows and insulation). The grant will fund 90% of the project costs. The total project cost is around £2,09m. The grant sum applied for is £1.88m (90%) and DCC will pay 10% (£209k). The £209k will be funded from the Council’s Climate and Nature Programme allocated budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CH LOW CARBON HEAT GRANT PROJECT: APPENDIX WBIAAppendix 14 pages Download
PDF
COUNTY HALL LOW CARBON HEAT GRANT PROJECTReport 5 pages DownloadRead as text

At this meeting

Whole meeting

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies