DENBIGH HIGH SCHOOL REFURBISHMENT - AWARD OF TENDER (DESIGN AND BUILD TWO STAGE CONTRACT)

Approved Executive 2 papers

AI summaryDenbighshire Cabinet awards first stage of Denbigh High School refurbishment contract to Wynne Construction, with a total project funding envelope of £19.8 million.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStage 1 pre-construction design services only
Money£19,836,575 total funding envelopeConstruction investment of £15.2 million
What happens nextDetailed design stage then construction contractOutline and Full Business Cases to come to Cabinet
Who it affectsDenbigh High School community and learnersJointly funded by Welsh Government and Denbighshire

What was decided

Cabinet approved awarding the contract to Wynne Construction via the North Wales Construction Partnership to design and subsequently deliver the construction element of the project. Report 3.1, P7

Cabinet confirmed it had read, understood and taken account of the Wellbeing Impact Assessment as part of its consideration. Report 3.2, P28

Why

Wynne Construction emerged as the successful bidder after four bids were scored by a cross-disciplinary panel on 30% price, 60% quality and 10% community benefits. Report 4.3, 4.4, 4.5

The project supports the Corporate Plan 2022 to 2027 by delivering a construction investment, modern teaching environments, improved energy efficiency, and apprenticeship and training opportunities. Report P16, 5.3

It is jointly funded through the Welsh Government's Sustainable Communities for Learning Programme and Denbighshire County Council, and the Strategic Outline Business Case was approved by Welsh Government in March 2026. Report 6.3

What happens next

Wynne Construction will begin Stage 1 pre-construction services to develop the detailed and technical design that will form the basis for the final build contract price. Report 4.2, P7

An Outline Business Case will be brought to Cabinet between the two stages, and a Full Business Case approval will be sought at Stage 2 once cost clarity is achieved. There is a break clause at Stage 2. Report 4.2, 6.2

The scheme will require planning permission, SuDS Approval Body approval and Building Control approval, and a phasing plan will be drawn up to limit disruption on the live school site. Report 10.2, 7.2

The money

  • £15.2million Construction investment delivering economic, social value and community benefits
  • £19.8million Total funding envelope for the project
  • £11,461,132 Welsh Government 65% share of main funding Report P23
  • £6,171,379 Denbighshire County Council share of main funding Report P23
  • £17,632,511 Main funding total (excluding Net Zero Carbon) Report P24
  • £2,204,064 Net Zero Carbon funding, 100% Welsh Government Report P25
  • £19,836,575 Total project funding Report P26

Implications

  • Financial: Capital commitments will require borrowing, with long-term interest and debt repayment costs that will need to be built into future Medium Term Financial Plans, plus future revenue costs of running the school. Report P30
  • Climate: The project is expected to enhance energy efficiency and contribute to the Council's Net Zero Carbon and Ecologically Positive target by 2030 and Welsh Government NZC targets. Report 5.3
  • Risk: Active risks include the need for planning permission, SAB approval, Building Control approval, increasing costs, and Welsh Government Business Case approval; risks are monitored via the VERTO project management system.
  • Equalities: A Wellbeing Impact Assessment has been prepared and is a live document; a negative impact identified is a period of disruption during construction works, with a phasing plan to allow continued delivery of a broad curriculum. Report P28, 7.2

Who and where

  • Denbigh High School learners, staff and Senior Leadership Report 7.2
  • The school's Chair of Governors and wider school community Report 8.2
  • The Denbigh Member Area Group Report 8.2
  • Other Denbighshire services including Planning and Public Protection, Energy Efficiency, Ecology, ICT, Catering and Communications Report 6.4

Timeline

  • September 2025: Employer's Agent appointed to the project Report 4.5
  • December 2025: Cabinet approved commencement of procurement and the Strategic Outline Case
  • 23rd of January 2026: Invitation to tender issued as a mini competition to Lot 5 of the North Wales Construction Partnership Report 4.3
  • March 2026: Welsh Government approved the Strategic Outline Business Case
  • 13th of March 2026: Tender period closed, with four bids received Report 4.3
  • 26th of May 2026: Cabinet decision to award the Stage 1 contract to Wynne Construction Report P2
  • 2027: Denbighshire to submit a revised Strategic Outline Programme for 2027-2030 Report 6.2

Plain English for the jargon

  • Sustainable Communities for Learning Programme: Welsh Government capital funding programme for school buildings, covering 65% of the main project funding here.
  • Net Zero Carbon (NZC): The Welsh Government and Council target of achieving net zero carbon emissions, funded here separately at 100% by Welsh Government.
  • Wellbeing Impact Assessment (WBIA): An assessment of the project's impact on the wellbeing goals and sustainability, kept as a live document.
  • North Wales Construction Partnership: Procurement framework through which the tender was run, with Lot 5 used for this mini competition.
  • Strategic Outline Business Case / Outline Business Case / Full Business Case: Stages of business case approval required to progress and fund the project, with the Full Business Case needed before Stage 2 construction award.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that Cabinet – (a) approve the award of contract to Wynne Construction to design and subsequently deliver the construction element of the project, and (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 3 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet, 5 pages

Report to Cabinet Briefing

Date of meeting 26th of May 2026

Lead Member Cllr Diane King, Lead Member for Education, Children and Families

HeaREd of Service Geraint Davies, Head of Education Services

Report Author Lowri Roberts, Modernising Education Officer

Title Denbigh High School Refurbishment – Award of Tender (Design and Build Two Stage Contract)

1. What is the report about? 1.1. This report seeks approval from Cabinet to appoint Wynne Construction, via the North Wales Construction Partnership, to a two-stage design and build contract for the delivery of the Denbigh High School refurbishment project. This report and award of contract relates to stage 1 pre-construction services only.

2. What is the reason for making this report? 2.1. The reason for this report is to seek Cabinet approval to award Wynne Construction the Stage 1 pre-construction services contract following completion of a robust procurement exercise via the North Wales Construction Partnership.

3. What are the Recommendations?

3.1It is recommended that Cabinet approve the award of contract to Wynne Construction to design and subsequently deliver the construction element of the project.

3.2That Cabinet confirms it has read, understood and taken account of the Well- being Impact Assessment (Appendix 3) as part of its consideration. 4. Report details 4.1. In December 2025 Cabinet gave their approval to commence the procurement process for a Design and Build contract for the refurbishment of Denbigh High School. Cabinet also gave their approval to submit the Strategic Outline Business Case to the Welsh Government, this has subsequently been approved in March 2026.

4.2The Design and Build contract is a two-stage process, this report and decision sought relates to the first stage which is to progress the detailed and technical design which will form the basis for finalising the build contract price. There is a break clause at stage two, final business case approval will also be sought at this stage once cost clarity has been achieved. An interim business case, known as the Outline Business Case will also bridge these two stages and will be brought to Cabinet for scrutiny and approval as the project progresses.

4.3The invitation to tender was issued on the 23rd of January 2026, the tender period closed on the 13th of March 2026. The invitation to tender was issued as a mini competition to contractors within Lot 5 of the North Wales Construction Partnership. Four of the contractors within the lot have returned a bid.

4.4All bids have been evaluated and scored by a cross-disciplinary panel, the criteria for scoring is based on 30% price, 60% quality and 10% community benefits.

4.5Wynne Construction have emerged as the successful bidder. A detailed commercial tender scoring report is provided in Appendix 1 (Part II Document). An Employers Agent was appointed to the project in September 2025 and they have assisted in the process, specifically with regard to the commercial elements. This report is a Part II item due to containing commercially sensitive information from bidders.

5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. A prosperous Denbighshire - The project will deliver a construction investment of £15.2million. This in turn will deliver a suite of economic social value and community benefits including apprenticeship, training and upskilling. 5.2. A learning and growing Denbighshire - The project will ensure that the Council continues to support learners within their community by delivering modern and enhanced teaching and learning environments.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WBIA DHSAppendix 3 18 pages Download
PDF
DENBIGH HIGH SCHOOL REFURBISHMENT: AWARD OF TENDER (DESIGN AND BUILD TWO STAGE CONTRACT)Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. DENBIGH HIGH SCHOOL REFURBISHMENT - AWARD OF TENDER (DESIGN AND BUILD TWO STAGE CONTRACT)This decision
  2. Denbigh high school refurbishment - draft strategic outline case and approval to progress design and build tenderApproved
  3. Application no. 18/2014/1164/ps - highfield park, llangwyfan, denbighRefused
  4. Application no. 01/2013/1599/pf - the forum, 27 - 29 high street, denbighDecided
  5. Application no. 01/2013/1601/lb - the forum, 27 - 29 high street, denbighDecided
  6. Application no. 01/2013/1599/pf - the forum, 27 - 29 high street, denbighDeferred

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies