Council, Thursday 24 November 2022 at 6.00pm

Additional Funding for Freedom Leisure due to the Increased Cost of Energy

Approved Committee 2 papers

Council approved this item on Thursday 24 November 2022. Below is the council's own wording, with the papers it was decided on.

Item217/22

Resolved

RESOLVED 1. That approval be given to a supplementary revenue budget, financed from the General Reserve, to support the partnership to the value of 75% of the significant increase in energy costs to the value of £204,000. 2. That support be ring-fenced to the Derbyshire Dales contract and paid on a monthly basis through open book accounting and monthly meetings with the contract managers up until 31st March 2023. 3. That further investigation be undertaken in January 2023, regarding options to mitigate costs and to review further information or support provided by central government. 4. That an update report be submitted to Council in March 2023. Voting 25 For 02 Against 01 Abstained The Chairman declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That approval be given to a supplementary revenue budget, financed from the General Reserve, to support the partnership to the value of 75% of the significant increase in energy costs to the value of £204,000

2. That this support is to be ring-fenced to the Derbyshire Dales contract and will be paid on a monthly basis through open book accounting and monthly meetings with the contract managers up until 31st March 2023

3. That further investigation be undertaken of options in January 2023 to mitigate costs and to review further information or support provided by central government

4. That an update report be submitted to Council in March 2023.

List of Appendices

Appendix 1 Expected utility increase by venue

Background Papers N/A Consideration of report by Council or other committee N/A

Council Approval Required Yes

Exempt from Press or Public No Additional funding for Freedom Leisure due to the increased cost of energy

Background

1.1The District Council has four leisure centres. These are sited in Ashbourne, Bakewell, Matlock and Wirksworth. These leisure centres provide vital health, leisure and wellbeing services to our local communities, with over 755,000 total centre participation in 2021/22.

1.2Following a review and options appraisal in 2018, the management and development of the service was out sourced to Freedom Leisure, a not for profit organisation. Freedom Leisure are not a private company therefore they don’t have a lot of reserves as all funds are put back into the organisation.

1.3Freedom Leisure is one of the UK’s leading charitable and not-for-profit leisure trusts. They manage leisure and cultural services on behalf of over 25 local authority partners and operate more than 100 leisure and cultural venues across England and Wales, including over 60 swimming pools – teaching over 62,000 children to swim on a weekly basis.

1.4Freedom Leisure have operated sustainably, improving lives through leisure for over 20 years. Their programmes are designed to support rehabilitation, active ageing, the prevention of physical, mental and social ill health, and addressing health inequalities, obesity, and support long term health conditions. The services they provide influence both the medical and social determinants of health.

1.5As a not for profit trust, they are fully dedicated to providing an affordable, accessible and inclusive health and wellbeing offer to the local communities, including providing vital life skills to children and adults learning to swim. These vital services are now under threat.

1.6As a result of outsourcing the service the original projection was that there would be a saving to the District Council of circa £4.9m over the 10 year contract life.

1.7The contract with Freedom Leisure has a management fee payable each year and for the first 5 years the District Council pays Freedom Leisure a decreasing fee. In the remaining 5 years of the contract the District Council will receive funds from Freedom Leisure for delivering the service. These costs are reducing each year, year 1 the management fee was £441k whereas for the current financial year, the management fee is only £177k.

1.8In addition to this, if there are any profits beyond break even for the Derbyshire Dales contract there is a surplus share agreement which is split 50/50 with Freedom Leisure and the District Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional Funding for Freedom Leisure due to the Increased Cost of EnergyReport 131 KB DownloadRead as text
PDF
Additional funding for Freedom Leisure due to the increased cost of energy: Appendix 1 /22Appendix 195 KB Download

At this meeting

Whole meeting

Who was there

29 of 50 attended
SB
Sue Bull CONChair, apologies
AS
Andrew Shirley CONVice-Chair, present
JA
Jacqueline Allison GPCommittee Member, present
RA
Robert Archer LIBDEMCommittee Member, apologies
JA
Jason Atkin CONCommittee Member, present
RB
Richard Bright Social Democratic PartyCommittee Member, present
MB
Matt Buckler GPCommittee Member, apologies
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, apologies
NB
Neil Buttle GPCommittee Member, present
DC
David Chapman CONCommittee Member, present
PC
Paul Cruise LIBDEMCommittee Member, present

All 50 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Additional Funding for Freedom Leisure due to the Increased Cost of EnergyThis decision
  2. Additional funding for derbyshire dales council for voluntary service (ddcvs) 2026/27Approved
  3. Freedom Leisure - Additional Funding due to the Increased Cost of EnergyApproved

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open