RESOLVED 1. That the Capital Programme spend to 30th September 2022 be noted. 2. That re-phasing of existing projects for completion over the next 3 years and the removal of projects not proceeding be approved. 3. That new projects and revisions set out in paragraph 3.1.1 of the report, totalling £1,723,312, be approved for inclusion in the Capital Programme. 4. That the updated capital programme for 2022/23 to 2024/25 set out in Appendix B to the report totalling £13,431,568 be approved. 5. That financing of the Capital Programme from the sources summarised at paragraph 3.3 be approved. Voting 27 For 00 Against 02 Abstained The Chairman declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That the Capital Programme spend to 30th September 2022 be noted. 2. That re-phasing of existing projects for completion over the next 3 years and the removal of projects not proceeding be approved. 3. That new projects and revisions set out in paragraph 3.1.1 of the report, totalling £1,723,312, be approved for inclusion in the Capital Programme. 4. That the updated capital programme for 2022/23 to 2024/25 set out in Appendix B to the report totalling £13,431,568 be approved. 5. That financing of the Capital Programme from the sources summarised at paragraph 3.3 be approved.
List of Appendices
Appendix A - Capital Monitoring Report as at 30th September 2022-23 Appendix B - Revised Capital Programme 2022/23 to 2024/25. Appendix C - Movement in Reserves relating to the Capital Programme Background Papers Business Cases are available for each new scheme.
Council Approval Required Yes
Exempt from Press or Public No CAPITAL PROGRAMME BUDGET MONITORING 2022/23 & FURTHER CAPITAL PROJECTS PROPOSALS
Background
1.1The Revised Capital Programme for 2022/23 of £8,801,014 was approved at the Council meeting on 29th September 2022.
1.2The programme for 2023/24 to 2024/25 was last updated at the Council meeting in July 2022.
1.3The first part of this report presents the current financial position of spend against the 2022/23 Capital Programme as at 30th September 2022.
1.4The remainder of this report describes new bids and other updates to the capital programme for 2022/23 to 2024/25 and associated financing
2. Capital Expenditure as at 30th September 2022
2.1As at 30th September 2022 expenditure including commitments against budget was £1,387,013 (15.7% of the annual budget). As shown at Appendix A, the forecast out-turn expenditure against budget is £5,379,069 (61.1% of the annual budget). The end 2 columns provide further explanation of the variances on a project by project basis and a likely date for completion. In summary, just over half of the capital programme is forecast to be completed during the current financial year. 2.2 The key variances between budget and forecast spending in 2022/23 are as follows:-
a) The projects below are forecast to overspend by 31st March 2023 for which additional funding is being requested for 2022/23. Housing projects will require further contributions from S106 contributions reserve whilst the ICT projects will require further contribution from the IT Reserve.
Project Project Total Forecast Variance Explanation Ref Budget Spend (£) (£) (£) 298 Housing – 300,000 362,358 62,358 Inflation has increased Empty works costs, unforeseen Homes roof works and external (Phase 1) wall insulation added to specification.
302 Housing – 42,000 46,492 4,492 Scheme now complete Henmore Increased costs due to Gardens additional items such as floor coverings and water butts 290 Housing – Slight delay due to Social 43,000 51,516 8,576 Planning approval but Housing works should commence Grant – in Q4. Inflation has Calver increased costs of retrofit technology, 641 Resources 30,000 65,000 35,000 Quotes based upon -(ICT) revised net-working Network traffic loads & changes switch in technology have Replaceme resulted increased nt costs. 642 Resources 20,000 30,000 10,000 Hardware cost increases -Disaster and component Recovery shortages are increasing Storage costs.
TOTAL 120,426
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.