Derbyshire Dales District Council
Council, Thursday 14 December 2023 at 6.00pm

Ashbourne Reborn Financial Risk Update

Agreed Committee 1 paper

Council agreed this item on Thursday 14 December 2023. Below is the council's own wording, with the papers it was decided on.

Item281/23

Resolved

RESOLVED 1. That completion of the Grant Funding Agreements between the District Council and Derbyshire County Council for the Highways and Public Realm project and between the District Council and Ashbourne Methodist Church for the Link Community Hub project be noted. 2. That the increased financial risk to the District Council associated with the Grant Funding Agreement for the Highways and Public Realm project, and proposed measures to help mitigate this risk, be noted. Voting 22 For 00 Against 01 Abstention The Chair declared the motion CARRIED . 21:05 – Councillor Matt Buckler left the meeting for consideration of the following item due to previously declaring a pecuniary interest.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That completion of the Grant Funding Agreements between the District Council and Derbyshire County Council for the Highways and Public Realm project and between the District Council and Ashbourne Methodist Church for the Link Community Hub project be noted.

2. That the increased financial risk to the District Council associated with the Grant Funding Agreement for the Highways and Public Realm project, and proposed measures to help mitigate this risk, be noted.

List of Appendices None

Background Papers • Ashbourne Reborn Governance and Delivery Report to Council 27 July 2023 • Ashbourne Reborn Programme Board Update Reports 27 September 2023, 26 October 2023 and 12 December 2023.

Consideration of report by Council or other committee No

1 Council Approval Required Yes

Exempt from Press or Public No

2 ASHBOURNE REBORN FINANCIAL RISK UPDATE

Background

1.1Ashbourne Reborn is a £15.22m programme aimed at transforming Ashbourne town centre through significant improvements to highways and public realm and the development of the Link Community Hub. The programme is principally funded by the UK Government through a £13,373,509 funding allocation from the Levelling Up Fund, Round Two. The programme comprises the following projects:

Project 1: Public Realm & Highways Improvements led by Derbyshire County Council (DCC)- £8.804m

Project 2: Link Community Hub led by Ashbourne Methodist Church - £6.418m

1.2Derbyshire Dales District Council is the Accountable Body for Ashbourne Reborn. This means that, although projects are being delivered by other delivery partners, the Council has responsibility for, inter alia:

• all financial matters (including but not limited to managing the programme budget, paying delivery partners and claiming funding from the Government to cover such payments) • all procurement matters (including but not limited to appointment, contracts and purchases made by delivery partners) • ensuring outputs and outcomes are achieved on time and to budget • other compliance matters (including but not limited to equalities duties and subsidy control) • discharging this accountability by monitoring, assuring, reporting and auditing to the Government’s satisfaction.

1.3Grant Funding Agreements are required to be completed to enable the defrayal of grant to delivery partners within the parameters set out by the Department for Levelling Up, Housing and Communities (DLUHC).

1.4In parallel to the Grant Funding Agreement negotiations with DCC, to ensure progress could be maintained, a revised letter of intent from the District Council was issued in September to enable funding of appropriate elements of design work, subject to the Grant funding Agreement being progressed and the provision of related evidence prior to agreement of associated payments.

1.5The process of reaching agreement took longer than anticipated with both delivery partners, and Grant Funding Agreements became the highest project and programme risk, with potential impacts on defrayal of grant payments, contractor procurement and delivery timeframes. They were therefore prioritised by District Council officers and partners in order to mitigate these risks.

3 1.6 A general progress report on the Ashbourne Reborn programme is set out in the Ashbourne Reborn Programme Board papers for 12 December meeting.

2 Key Issues

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ashbourne Reborn Financial Risk UpdateReport 157 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

26 of 42 attended
SW
Steve Wain LIBDEMChair, apologies
DG
Dawn Greatorex LABVice-Chair, in the Chair, present
RA
Robert Archer LIBDEMCommittee Member, apologies
MB
Matt Buckler GREENCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
NB
Neil Buttle GREENCommittee Member, present
DC
David Chapman CONCommittee Member, present
SH
Susan Hobson CONCommittee Member, present
DH
David Hughes LIBDEMCommittee Member, present
SL
Stuart Lees CONCommittee Member, apologies
DM
Dermot Murphy CONCommittee Member, present

All 42 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Ashbourne Reborn Financial Risk UpdateThis decision
  2. Ashbourne Reborn Programme Report (Derbyshire Dales District Council)Approved
  3. Ashbourne Reborn Programme Report (Derbyshire Dales District Council) Including Updated Programme Board Terms of ReferenceAgreed
  4. Ashbourne Reborn Programme Report (Derbyshire Dales District Council)Agreed
  5. Ashbourne Reborn Update and Proposed Support Measures ContinuedNoted
  6. Ashbourne Reborn Programme UpdateNoted

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies