Item47
Resolved
RESOLVED (unanimously) 1. That progress to date be considered and that the position regarding programme, cost, deliverables and risks be received and noted. 2. That the principles of the ongoing rescoping and value engineering exercises on both projects be noted and endorsed, subject to further refinement by Project Teams and final consideration by Project Boards to bring each project within budget. 3. That the submission of a Project Adjustment Request at the earliest opportunity be approved (as required by MHCLG) based on the proposed expenditure profile in Appendix 4 to the report. That this matter also be referred to Derbyshire Dales District Council’s Community and Environment Committee for final consideration prior to submission. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.