Revenue Budget Monitoring Quarter 1 2025/26

Approved Committee 1 paper

Council approved this item on Thursday 25 September 2025. Below is the council's own wording, with the papers it was decided on.

Item154/25

Resolved

RESOLVED (unanimously) 1. That the updated revised revenue budget for 2025/26, including the virements as identified in paragraph 1.2 of the report, be approved. 2. That the forecast underspending of £387,530 for 2025/26 be received and agreed. 3. That a decision on which reserves to allocate the forecast underspend is taken later in the financial year, when we will have more certainty on our financial position, as detailed in paragraph 1.7 of the report. The Chair declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That the updated revised revenue budget for 2025/26, including the virements as identified in paragraph 1.2 of the report, be approved.

2. That the forecast underspending of £387,530 for 2025/26 be received and agreed.

3. That a decision on which reserves to allocate the forecast underspend is taken later in the financial year, when we will have more certainty on our financial position, as detailed in paragraph 1.7 of the report.

List of Appendices Appendix 1 Approved Budget Changes since Revenue Out-turn Report (24th July 2025) and Reserves Requests for approval at quarter 1 Appendix 2 Updated Revised Budget 2025/26 Appendix 3 Summary of Reserves – Forecasts for 2025/26 and 2026/27

Background Papers None

Consideration of report by Council or other committee No

Council Approval Required Yes

Exempt from Press or Public No Revenue Budget Monitoring Quarter 1 2025/26

Background

1.1On 3rd March 2025 Council set a net revenue budget of £13,583,534 for 2025/26. This was subsequently updated when the revenue out-turn report 2024/25 was approved by Council on the 24th July 2024 and a further £1,226,288 was requested and transferred from the Committed Expenditure, Revenue Grants Unapplied and Local Plan Reserves to give a revised net revenue budget of £14,809,822.

1.2Since the revised budget was formally approved, there has been a number of virements approved under delegated authority which has impacted directorate totals. These additional approved budget changes are summarised in Appendix 1 and have the overall effect of increasing the budget by £418,015. Additional requests for the transfer to/from earmarked reserves are also summarised in Appendix 1 these total £111,340 for 2025/26. The use of these reserves is for on-going approved Council projects where timing has been uncertain, and funds have previously been set aside within reserves.

1.3The forecast out-turn position at Quarter 1 for the Council is an underspend of £387,530. This is based on estimates at 30th June 2025; updated forecasts will be reported throughout the financial year. Appendix 2 details the current forecast position and revised budget. A breakdown of the key variances can be found in the table below:

£ 000's Forecast overachievement of investment income (154) Overachievement of garden waste income (16) Forecast underspend on staffing budgets (198) Other non-material variances (20)

Total Quarter 1 Forecast underspend (388)

1.4The 2025/26 investment income budget was set at £700k in March 2025. By 30 June 2025 we have already achieved £359k and it is anticipated that a further £495k can be achieved over the remainder of the financial year, giving a forecast budget surplus of £154k. The budget was set assuming the Bank of England base rate would fall to 3.5% by 1 April 2025, this has not occurred and the base rate during the first quarter of the financial year was 4.5% until 8th May 2025 when it reduced to 4.25%, which has meant the Council has received better returns on investments than anticipated when the budget was set. This forecast is based on a number of assumptions and will continue to be refined throughout the financial year; it currently assumes an average interest rate of 4% will be achieved on investments for the remainder of the financial year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue Budget Monitoring Quarter 1 2025/26Report 218 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

27 of 39 attended
RS
Roger Shelley LIBDEMChair, present
LP
Lucy Peacock LABVice-Chair, present
DG
Dawn Greatorex LABCommittee Member, apologies
RA
Robert Archer LIBDEMCommittee Member, apologies
AB
Anthony Bates CONCommittee Member, present
JB
John Bointon CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, present
MB
Matt Buckler GREENCommittee Member, present
SB
Sue Bull CONCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
DB
David Burton LIBDEMCommittee Member, present

All 39 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Revenue Budget Monitoring Quarter 1 2025/26This decision
  2. Revenue budget monitoring quarter 3 2025/26Approved
  3. Revenue budget 2026/27Approved
  4. Revenue Budget Monitoring Quarter 2 2025/26Approved
  5. Revenue Budget Monitoring Quarter 3 2024/25Approved
  6. Revenue Budget Monitoring Quarter 2 2024/25Approved

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies