Capital Programme update

Noted Committee 3 papers

Council noted this item on Thursday 25 September 2025. Below is the council's own wording, with the papers it was decided on.

Item153/25

Resolved

RESOLVED (unanimously) 1. That the Capital Programme expenditure to 30th June 2025 is noted. 2. That re-phasing of existing projects for completion over the next 5 years is approved. 3. That two new projects totalling £31,708 and detailed in paragraphs 2.7 and 2.8 is approved for inclusion in the capital programme. 4. That the revised Capital Programme for 2025/26 to 2029/30, as shown in Appendix A, totalling £27,543,481 is approved. 5. That financing of the Capital Programme from sources summarised at paragraph 2.12 and shown in Appendix B is approved. 6. That the balance of funds available over the 5-year programme, shown at Appendix B, is noted. The Chair declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That the Capital Programme expenditure to 30th June 2025 is noted.

2. That re-phasing of existing projects for completion over the next 5 years is approved.

3. That two new projects totalling £31,708 and detailed in paragraphs 2.7 and 2.8 is approved for inclusion in the capital programme.

4. That the revised Capital Programme for 2025/26 to 2029/30, as shown in Appendix A, totalling £27,543,481 is approved.

5. That financing of the Capital Programme from sources summarised at paragraph 2.12 and shown in Appendix B is approved.

6. That the balance of funds available over the 5-year programme, shown at Appendix B, is noted.

List of Appendices Appendix A Revised Capital Programme 2025/26 to 2029/30 Appendix B Proposed financing of the Capital Programme 2025/26 to 2029/30

Background Papers None

Consideration of report by Council or other committee Not applicable

Council Approval Required Yes

Exempt from Press or Public No Capital Programme Update

Background

1.1At the Council meeting on 24th July 2025 Members approved a revised capital programme totalling £28,180,995 covering the financial years 2025/26 to 2029/30, as summarised in table 1 below:

Table 1: Capital Programme approved 24th July 2025

Financial year £ 2025/26 21,669,781 2026/27 3,205,196 2027/28 1,023,696 2028/29 1,197,826 2029/30 1,084,496 Total 28,180,995

1.2This report provides information on the current financial position of spend against the 2025/26 Capital Programme as at 30th June 2025 and seeks approval for a revised capital programme for 2025/26 to 2029/30, taking account of the expected slippage into 2026/27. 2. Proposed revisions to the Capital Programme

Capital Expenditure for 2025/26

2.1At Council on 24th July a revised capital budget of £21,669,781 was approved for 2025/26.

2.2As at 30th June expenditure including commitments against the budget was £2,711,316 as shown in Appendix A.

2.3The forecast out turn for the 2025/26 capital programme determines that the amount in 2025/26 should be revised to £21,061,477 which is a difference of £608,304 from the budget of £21,669,781 approved in July 2025 as shown in Appendix A.

Table 2: Revised Capital financing arrangements for 2025/26

Sources of Financing £ Capital Receipts General 994,093 Capital Receipts Housing 80,000 Capital Receipts Vehicles 115,000 Capital Programme Reserve 517,301 S106 Contributions (Housing) 1,610,251 S106 Contributions (other) 60,126 Grants 15,191,758 Ashbourne Reborn Reserve 425,000 IT Reserve 323,555 Invest to Save Reserve 562,510 Corporate Plan Priority Reserve 210,561 Vehicle Reserve 874,022 Revenue Grants Unapplied 97,300 Total 21,061,477

2.4Reprofiling of schemes into 2026/27 total £507,030; these are explained below:

• Project 281 Social Housing Grant Tideswell £412,500. The project is on hold due to soil nutrient neutrality. The project will not be progressing in this financial year. The budget will be reprofiled into 2026/27.

• Project 652 Matlock Bath Lovers Walk £44,530 Project on hold pending planning application. Council have rejected the project as a shelter rebuild, if required to rebuild the asset, then the project will slip into 2026/27.

• Project 667 WI-FI replacement £50,000 This project has been paused whilst other projects are completed. The budget has been reprofiled into 2026/27.

2.5Forecast Overspends on schemes in 2025/26 total £410,060

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3a. Capital Programme Update: Appendix A: 5 year Capital Programme /25Appendix 210 KB Download
PDF
3b. Capital Programme Update: Appendix b: 5 year Capital Programme Financing /25Appendix 381 KB Download
PDF
Capital Programme updateReport 185 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

27 of 39 attended
RS
Roger Shelley LIBDEMChair, present
LP
Lucy Peacock LABVice-Chair, present
DG
Dawn Greatorex LABCommittee Member, apologies
RA
Robert Archer LIBDEMCommittee Member, apologies
AB
Anthony Bates CONCommittee Member, present
JB
John Bointon CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, present
MB
Matt Buckler GREENCommittee Member, present
SB
Sue Bull CONCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
DB
David Burton LIBDEMCommittee Member, present

All 39 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Capital Programme updateThis decision
  2. Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31Approved
  3. Capital programme updateNoted
  4. Capital Programme UpdateNoted
  5. Provisional Capital Outturn 2024/25 and Revised Capital Programme 2025/26 to 2029/30Approved
  6. Capital Programme UpdateNoted

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies