RESOLVED (unanimously) 1. That the Capital Programme expenditure to 30th June 2025 is noted. 2. That re-phasing of existing projects for completion over the next 5 years is approved. 3. That two new projects totalling £31,708 and detailed in paragraphs 2.7 and 2.8 is approved for inclusion in the capital programme. 4. That the revised Capital Programme for 2025/26 to 2029/30, as shown in Appendix A, totalling £27,543,481 is approved. 5. That financing of the Capital Programme from sources summarised at paragraph 2.12 and shown in Appendix B is approved. 6. That the balance of funds available over the 5-year programme, shown at Appendix B, is noted. The Chair declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That the Capital Programme expenditure to 30th June 2025 is noted.
2. That re-phasing of existing projects for completion over the next 5 years is approved.
3. That two new projects totalling £31,708 and detailed in paragraphs 2.7 and 2.8 is approved for inclusion in the capital programme.
4. That the revised Capital Programme for 2025/26 to 2029/30, as shown in Appendix A, totalling £27,543,481 is approved.
5. That financing of the Capital Programme from sources summarised at paragraph 2.12 and shown in Appendix B is approved.
6. That the balance of funds available over the 5-year programme, shown at Appendix B, is noted.
List of Appendices Appendix A Revised Capital Programme 2025/26 to 2029/30 Appendix B Proposed financing of the Capital Programme 2025/26 to 2029/30
Background Papers None
Consideration of report by Council or other committee Not applicable
Council Approval Required Yes
Exempt from Press or Public No Capital Programme Update
Background
1.1At the Council meeting on 24th July 2025 Members approved a revised capital programme totalling £28,180,995 covering the financial years 2025/26 to 2029/30, as summarised in table 1 below:
Table 1: Capital Programme approved 24th July 2025
Financial year £ 2025/26 21,669,781 2026/27 3,205,196 2027/28 1,023,696 2028/29 1,197,826 2029/30 1,084,496 Total 28,180,995
1.2This report provides information on the current financial position of spend against the 2025/26 Capital Programme as at 30th June 2025 and seeks approval for a revised capital programme for 2025/26 to 2029/30, taking account of the expected slippage into 2026/27. 2. Proposed revisions to the Capital Programme
Capital Expenditure for 2025/26
2.1At Council on 24th July a revised capital budget of £21,669,781 was approved for 2025/26.
2.2As at 30th June expenditure including commitments against the budget was £2,711,316 as shown in Appendix A.
2.3The forecast out turn for the 2025/26 capital programme determines that the amount in 2025/26 should be revised to £21,061,477 which is a difference of £608,304 from the budget of £21,669,781 approved in July 2025 as shown in Appendix A.
Table 2: Revised Capital financing arrangements for 2025/26
Sources of Financing £ Capital Receipts General 994,093 Capital Receipts Housing 80,000 Capital Receipts Vehicles 115,000 Capital Programme Reserve 517,301 S106 Contributions (Housing) 1,610,251 S106 Contributions (other) 60,126 Grants 15,191,758 Ashbourne Reborn Reserve 425,000 IT Reserve 323,555 Invest to Save Reserve 562,510 Corporate Plan Priority Reserve 210,561 Vehicle Reserve 874,022 Revenue Grants Unapplied 97,300 Total 21,061,477
2.4Reprofiling of schemes into 2026/27 total £507,030; these are explained below:
• Project 281 Social Housing Grant Tideswell £412,500. The project is on hold due to soil nutrient neutrality. The project will not be progressing in this financial year. The budget will be reprofiled into 2026/27.
• Project 652 Matlock Bath Lovers Walk £44,530 Project on hold pending planning application. Council have rejected the project as a shelter rebuild, if required to rebuild the asset, then the project will slip into 2026/27.
• Project 667 WI-FI replacement £50,000 This project has been paused whilst other projects are completed. The budget has been reprofiled into 2026/27.
2.5Forecast Overspends on schemes in 2025/26 total £410,060
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.