CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Derbyshire Dales District Council
Ashbourne Reborn Programme Board, Thursday 16 October 2025 at 3.30pm

Project Update - Link Community Hub (Ashbourne Methodist Church)

Noted Committee 1 paper

AI summaryAshbourne Reborn Programme Board noted the latest update on the Link Community Hub at Ashbourne Methodist Church. The report sets a construction completion date of 27 February 2026 and flags a forecast final account increase of £80k.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard unanimously noted the report
Money£80k forecast cost riseAbout one third of contingency
What happens nextConstruction completion 27 February 2026Practical opening expected May 2026
Who it affectsAshbourne Methodist Church and communityNew hub, lodge and coffee house

What was decided

The board unanimously noted the project update report on the Link Community Hub. Report P1

Why

The report summarises construction progress, financial position, risks and operational planning for the community hub and Gateway Lodge. Report P5, 1.2

The board received a verbal update on the 23 September 2025 project board meeting, alongside written minutes from July and August 2025. Report P5, P3

What happens next

Construction is targeted for completion on 27 February 2026, with practical opening planned for May 2026 and an official opening ceremony in July 2026. Report 1.3, 1.6

Officers will pursue VAT recovery with HMRC, set up the new operating company and recruit a volunteer coordinator. Report 1.4, 1.6

Alternative funding sources for the Community Garden are being sought after an unsuccessful Severn Trent Community Fund application. Report 1.5

The money

  • £80k forecast increase in the final account, about one third of the contingency Report P59
  • 5.5% less than forecast on cashflow following the July 25 valuation Report P58

Implications

  • Financial: Forecast final account shows an overall increase of £80k, about one third of the contingency. Report P59
  • Financial: Cashflow after the July 25 valuation is 5.5% less than forecast due to contractor programme delays. Report P58
  • Risk: Delay in Link steelwork is assessed as 8 weeks, pushing the construction end date to mid April 2026 if not mitigated. Report P56
  • Staffing: A site operative was off work for 13 days following an accident, which was reported to the HSE as required. Report P55
  • Legal: The church is now registered for VAT backdated to 1st September 2023 and is negotiating recovery of construction VAT with HMRC. Report 1.4

Who and where

  • Future users of the Link Centre community hub and Gateway Lodge guesthouse Report 1.6, P8
  • Cornerstone Coffee House customers and volunteers Report 1.2, P11, P9
  • Ashbourne Methodist Church congregation Report P7, P8
  • Community organisations and cultural groups in Ashbourne Report 1.6

Timeline

  • 30th June 2025: Sectional completion of the Worship Hall achieved Report P25
  • 22nd July 2025: Cornerstone Coffee House moved to temporary venue in Trinity Hall Report P62
  • 23rd September 2025: Link Project Board meeting held, with verbal update given to the Programme Board Report P5, P68
  • 27th February 2026: Target construction completion date Report 1.3
  • May 2026: Expected practical opening of the Link Centre Report 1.6
  • July 2026: Official opening ceremony planned Report 1.6

Plain English for the jargon

  • Ashbourne Reborn: A regeneration programme for Ashbourne town centre
  • AMC: Ashbourne Methodist Church
  • MHCLG: Ministry of Housing, Communities and Local Government, the funder of the project
  • EoT: Extension of Time, a contractual claim for additional time on the project
  • CDM: Construction, Design and Management regulations for site health and safety
  • HSE: Health and Safety Executive
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/25

Resolved

RESOLVED (unanimously) That the report be noted by the board.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Ashbourne Reborn Programme Board

Recommendations

Recommendations associated with this update are provided within the Programme Report, Agenda Item 7.

List of Appendices

Appendix 1 - July 25 Link Community Hub Project Board Minutes Appendix 2 - August 25 Link Community Hub Project Board Minutes

1 LINK COMMUNITY HUB UPDATE

Project Progress and Risks: 1.1 An overview of progress through the main construction period is provided below, with further detail of the Link Community Hub Project provided in Appendix 1 and 2, Minutes of the Project Board Meetings in July and August 2025. A verbal update will be provided at the Programme Board meeting following the Project Board meeting held on 23 September, in advance of the agreed written minutes being available.

1.2Significant construction progress has been made since the last report:

• In the Link Foyer – erection of the steelwork, installation of the street level floor, installation of the roof.

• In Gateway Lodge the completion of all the new rooms (bedrooms, ensuites, kitchen) with plastering, installation of all plumbing, electrical supply, fire alarm wiring etc. The foundations of the Link extension are also in place.

• The new Garden Entrance foundations have been laid, and the walls are progressing well • Cornerstone is handed over to the contractor and the internal walls rearrangement is largely complete and the new opening into the Link Foyer has been made

1.2The temporary move of the Cornerstone Coffee House into Trinity Hall has gone well. The temporary kitchen, servery and toilet are working well, and many people have come into Trinity Hall and been impressed by the work so far. It has been very encouraging to have many positive comments and it is great to have so many people “crossing the threshold” of the buildings. The Cornerstone

CONTROLLED team is much appreciated by many people.

1.3The Construction Programme now has a completion date of 27th February 2026. We are working intensively with our Contractor, Project Manager, Architects and all related parties to ensure all resources are mobilised, risks identified promptly and effective actions taken to overcome them, so that this date is achieved.

1.4The Church is now registered for VAT backdated to 1st September 2023 (to enable us to recover construction VAT on costs already incurred). Our tax advisor’s negotiation with HMRC for recovery of construction VAT will now start. As a charity the Church needs a trading subsidiary to operate The Link Centre and Gateway Lodge and the preparation of the necessary legal and financial arrangements are progressing.

1.5We were very disappointed not to succeed with the recent Severn Trent Community Fund grant application and we are now looking for alternative sources of funding or alternative approaches to achieve the Community Garden.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Update: Link Community Hub (Ashbourne Methodist Church)Agenda 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 13 attended
DH
David Hughes LIBDEMChair, present
SB
Sue BridgettAppointed Member, present
PD
Peter Dobbs LIBDEMAppointed Member, present
SF
Steve Flitter LIBDEMAppointed Member, present
SL
Stuart Lees CONAppointed Member, present
TW
Tony WalkerAppointed Member, present
JW
John WhitbyAppointed Member, apologies
AW
Anne WrightAppointed Member, present
NA
Nick AdamsAppointed Member, present
SS
Sandra SpencerAppointed Member, present
SB
Steve BullAppointed Member, present
GH
Gemma HadfieldOfficer, in attendance

All 13 on the meeting page

More from Derbyshire Dales Ashbourne Reborn Programme Board

All decisions
MeetingDecisionOutcome
3 Sep 2026 Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Ashbourne Reborn Programme Board held on 18 06 2026 be approved as a ... Approved Open
3 Sep 2026 Ashbourne Reborn Programme Report (Derbyshire Dales District Council)That the recommendations within the report be approved unanimously. Approved Open
18 Jun 2026 Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Ashbourne Reborn Programme Board held on 26 02 2026 be approved as a ... Approved Open
26 Feb 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the Non-Exempt and Exempt minutes of the meeting of the 11 December 2025 be approved as a... Approved Open
11 Dec 2025 Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Ashbourne Reborn Programme Board held on 16 October 2025 be approved ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies