Place Scrutiny Committee decided this item on Wednesday 18 May 2022. Below is the council's own wording, with the papers it was decided on.

Item11/19

Resolved

That the Committee notes: (i) The strong progress that has been secured through the early Digital Derbyshire contracts in providing 97% of all premises with access to Superfast broadband (>24Mbps) and 41.84% with access to an Ultrafast service (>100Mbps); (ii) The challenges that remained in delivering full fibre connection to hard to reach premises in the County; (iii) The £500,000 funding commitment made to Rural Gigabit and the top up voucher scheme in bridging the gap on rural connectivity; (iv) Plans to develop and deliver a coherent communications campaign targeted at hard to reach communities and ramp up communication strategy; (v) The work that was being actively pursued to ensure full connectivity, including the recent investment by the County Council in Top Up provision, the drive to secure additional external funding to support programme delivery and lobbying of Government; and (vi) That the officers return later in the year to provide an update on progress along with more specific information.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Place Scrutiny Committee

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

IMPROVEMENT AND SCRUTINY COMMITTEE - PLACES

WEDNESDAY, 18 MAY 2022

Report of the Executive Director - Place

Update on the Broadband Programme in Derbyshire

1. Purpose

1.1The purpose of this report is to update the Scrutiny Committee members on the progress made under the Digital Derbyshire Superfast Programme and plans for the future rollout of Gigabit-capable broadband across the County. This report will be accompanied by a brief presentation at the Scrutiny Committee meeting.

2. Information and Analysis

2.1The Digital Derbyshire Superfast Programme has now concluded. The Programme was delivered nationally by British Telecom’s Openreach, under contract with the Department of Culture, Media and Sport (DCMS) and commenced in 2013, finally concluding in November 2021.

2.2Over the nine year period, broadband access has improved for over 120,000 residential and business premises across Derbyshire as a direct result of the £24 million Programme. The funding package was made up of the following financial contributions: £4.89m contribution from Derbyshire County Council (DCC); £9.58m from state subsidy; £4.81m from British Telecom (BT); £2.5m from European Regional Development Fund (ERDF); and £2.19m match funding from the Derby, Derbyshire, Nottingham and Nottinghamshire (D2N2) Local Enterprise Partnership. 2.3 The chart below demonstrates the current level of broadband coverage across Derbyshire. A total of 97% of all premises now have access to Superfast broadband (>24 Mbps) and 41.84% have access to an Ultrafast service (>100 Mbps). However, around 4,000 premises do not have access to broadband speeds above 10Mbps; the majority of these are in rural, hard to reach locations in the Derbyshire Dales and High Peak. This situation needs to be addressed to ensure Derbyshire residents and businesses are not excluded or left further behind – a critical consideration in our efforts to fully achieve ‘levelling up’.

2.4The second graph demonstrates the increase in Fibre Broadband coverage across Derbyshire since 2010. The blue line represents Superfast availability. Source – think broadband https://labs.thinkbroadband.com/local/E10000007

Closing the Gap for Hard to Reach Locations

2.5As stated above, around 4,000 premises do not have access to broadband speeds above 10Mbps in Derbyshire. The Digital Derbyshire Team has been actively lobbying Government over a number of years to redirect local Gainshare funding (secured as a performance reward in the BT contract) and encourage dedicated monies and programmes to be established nationally to address this gap – which is evident in many rural counties.

2.6There are significant challenges in delivering full fibre to more remote premises with cost and commercial viability being the most prevalent; it is not unusual for infrastructure costs to remote premises to exceed £10,000 – and often more.

2.7As a result, a number of schemes have been developed recently to help residential and business premises in these more remote locations access reliable and speedy connections. A summary is provided below: 2.8 Derbyshire has been allocated Government funding from Project Gigabit to help close the gap. This initiative is planning to upgrade broadband services to approximately 67,000 hard to reach homes and businesses with Full Fibre, Gigabit-capable broadband (FTTP). A consultation process commenced with the Derbyshire Open Market Review in October 2021. Officers are working with the DCMS to validate responses and agree a way forward that maximises benefit for Derbyshire residents and businesses, particularly in relation to ‘not spots’ of connectivity. A fuller update on the public consultation exercise, pending procurement and community engagement programme will be provided at the Scrutiny meeting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Broadband Programme in DerbyshireReport 313 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 31 attended
SB
Councillor Steve BullChairman, present
JS
Councillor Julian SiddleVice-Chairman, present
DC
Councillor Dean CollinsCommittee Member, present
NG
Councillor Nigel GourlayCommittee Member, present
DG
Councillor Damien GreenhalghCommittee Member, apologies, sent representative
JN
Councillor John NelsonCommittee Member, present
PN
Councillor Paul NiblockCommittee Member, present
RR
Councillor Roger RedfernCommittee Member, present
AS
Councillor Alexander StevensonCommittee Member, absent
DS
Danny SunderlandClerk, expected
RS
Roz SavageOfficer, present
DT
Debbie TowndrowOfficer, expected

All 31 on the meeting page

More from Derbyshire Place Scrutiny Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 Presentation on Collection and Packaging ReformsRESOLVED that the Committee note the report and presentation. Noted Open
22 Jul 2026 Presentation on the Regeneration PipelineRESOLVED that the Committee note the report and presentation. Noted Open
25 Feb 2026 Update on the Development of the Environmental Sustainability Strategy (2026-2030)RESOLVED that: a) The Committee notes the progress made in developing the Environmental Sustainability Strategy (2026... Noted Open
24 Sep 2025 Presentation on the East Midlands Combined County Authority and the Transition of the Transport FunctionRESOLVED that the Committee notes the report and presentations. Decided Open
26 Feb 2025 Management of Section 278 and Section 38 Highway Legal AgreementsRESOLVED that the Committee: a) Acknowledges and endorses the processes outlined in the ... view the full minutes tex... Decided Open