That the Committee notes: (i) The strong progress that has been secured through the early Digital Derbyshire contracts in providing 97% of all premises with access to Superfast broadband (>24Mbps) and 41.84% with access to an Ultrafast service (>100Mbps); (ii) The challenges that remained in delivering full fibre connection to hard to reach premises in the County; (iii) The £500,000 funding commitment made to Rural Gigabit and the top up voucher scheme in bridging the gap on rural connectivity; (iv) Plans to develop and deliver a coherent communications campaign targeted at hard to reach communities and ramp up communication strategy; (v) The work that was being actively pursued to ensure full connectivity, including the recent investment by the County Council in Top Up provision, the drive to secure additional external funding to support programme delivery and lobbying of Government; and (vi) That the officers return later in the year to provide an update on progress along with more specific information.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
1.1The purpose of this report is to update the Scrutiny Committee members on the progress made under the Digital Derbyshire Superfast Programme and plans for the future rollout of Gigabit-capable broadband across the County. This report will be accompanied by a brief presentation at the Scrutiny Committee meeting.
2. Information and Analysis
2.1The Digital Derbyshire Superfast Programme has now concluded. The Programme was delivered nationally by British Telecom’s Openreach, under contract with the Department of Culture, Media and Sport (DCMS) and commenced in 2013, finally concluding in November 2021.
2.2Over the nine year period, broadband access has improved for over 120,000 residential and business premises across Derbyshire as a direct result of the £24 million Programme. The funding package was made up of the following financial contributions: £4.89m contribution from Derbyshire County Council (DCC); £9.58m from state subsidy; £4.81m from British Telecom (BT); £2.5m from European Regional Development Fund (ERDF); and £2.19m match funding from the Derby, Derbyshire, Nottingham and Nottinghamshire (D2N2) Local Enterprise Partnership. 2.3 The chart below demonstrates the current level of broadband coverage across Derbyshire. A total of 97% of all premises now have access to Superfast broadband (>24 Mbps) and 41.84% have access to an Ultrafast service (>100 Mbps). However, around 4,000 premises do not have access to broadband speeds above 10Mbps; the majority of these are in rural, hard to reach locations in the Derbyshire Dales and High Peak. This situation needs to be addressed to ensure Derbyshire residents and businesses are not excluded or left further behind – a critical consideration in our efforts to fully achieve ‘levelling up’.
2.4The second graph demonstrates the increase in Fibre Broadband coverage across Derbyshire since 2010. The blue line represents Superfast availability. Source – think broadband https://labs.thinkbroadband.com/local/E10000007
Closing the Gap for Hard to Reach Locations
2.5As stated above, around 4,000 premises do not have access to broadband speeds above 10Mbps in Derbyshire. The Digital Derbyshire Team has been actively lobbying Government over a number of years to redirect local Gainshare funding (secured as a performance reward in the BT contract) and encourage dedicated monies and programmes to be established nationally to address this gap – which is evident in many rural counties.
2.6There are significant challenges in delivering full fibre to more remote premises with cost and commercial viability being the most prevalent; it is not unusual for infrastructure costs to remote premises to exceed £10,000 – and often more.
2.7As a result, a number of schemes have been developed recently to help residential and business premises in these more remote locations access reliable and speedy connections. A summary is provided below: 2.8 Derbyshire has been allocated Government funding from Project Gigabit to help close the gap. This initiative is planning to upgrade broadband services to approximately 67,000 hard to reach homes and businesses with Full Fibre, Gigabit-capable broadband (FTTP). A consultation process commenced with the Derbyshire Open Market Review in October 2021. Officers are working with the DCMS to validate responses and agree a way forward that maximises benefit for Derbyshire residents and businesses, particularly in relation to ‘not spots’ of connectivity. A fuller update on the public consultation exercise, pending procurement and community engagement programme will be provided at the Scrutiny meeting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.