Safer Roads Fund Project A5012 Via Gellia, Cromford to Newhaven

Approved Executive 1 paper

Cabinet approved this item on Thursday 8 September 2022. Below is the council's own wording, with the papers it was decided on.

Item155/22

Resolved

RESOLVED to: 1) Approve the progress of the A5012 Safer Roads Fund Major Project to the Consultation and Public Engagement process; 2) Confirm receipt of and accept the Department for Transport Grant at the confirmed value of £3.079m for the Safer Roads Fund A5012 “Via Gellia ” Cromford to Newhaven project, and that this Grant Value/Project Budget should be confirmed in the 2023-24 Capital Programme; and 3) Confirm that the outcome of the Consultation, together with the final scheme design and procurement strategy, will be reported back to Cabinet for approval.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

Thursday, 8 September 2022

Report of the Executive Director - Place

Safer Roads Fund Project - A5012 "Via Gellia" Cromford to Newhaven (Cabinet Member for Highways, Assets and Transport)

1. Divisions Affected

1.1Wirksworth and Dovedale.

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To seek approval by Cabinet to progress this A5012 Safer Roads Fund (SRF) Major Project to the Consultation and Public Engagement process.

3.2To inform Cabinet and confirm the £3.079 million award from the Department for Transport Safer Roads Fund Grant, which has been received for this A5012 “Via Gellia” Project.

3.3To inform Cabinet that the outcome of the Consultation, together with the final scheme design and procurement strategy, will be reported back to Cabinet for approval. 4. Information and Analysis

4.1In its 2016 Autumn Statement, Government announced the creation of a £175 million Safer Roads Fund to improve the safety of the 50 highest risk roads in England. Three of these roads are in Derbyshire:

A619 - Baslow to Bakewell (Thirteen Bends) A5004 - Buxton to Whaley Bridge (Long Hill) A5012 – Cromford to Newhaven (Via Gellia)

4.2The County Council was required to work with the Department for Transport (DfT) to develop outline scheme proposals that delivered safety improvements and then to submit these proposals as bids. On 31 January 2017, Cabinet approved, in principle, to accept the grants for all three of the above projects (Minute No. 36/17 refers).

4.3In June 2018, the DfT approved the Council’s three bids and outline schemes and, in August 2018, provided outline details of the funding arrangements for the A5012 – Cromford to Newhaven Project. At this time, DfT’s intention was that grant funding for the project would be fully released for 2020-21 financial year.

4.4In a Grant Award, March 2021 (deferred by Dft due to Covid Pandemic), the Council received £3.079m un-ringfenced grant for the A5012 Safer Roads Fund Project.

4.5The A5012 route improvements will be implemented over an approximately 3 year period from receipt of Grant (although detailed programme for site installation of the various “Countermeasures” i.e. the detailed Works Solutions on site, cannot be confirmed with DfT until after the Public Consultation/Public Engagement phase). Subject to Consultation, Average Speed Cameras would seek to address inappropriate speed from the Bonsall Junction area, north westwards towards Newhaven, helping to reduce the number and severity of collisions. Physical improvements identified below are proposed along the route to address general hazards and specific high-risk locations by:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Safer Roads Fund Project A5012 Via Gellia, Cromford to NewhavenReport 169 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
BL
Councillor Barry LewisChairman, present
SS
Councillor Simon SpencerVice-Chairman, present
AD
Councillor Alex DaleCommittee Member, present
CH
Councillor Carol HartCommittee Member, present
NH
Councillor Natalie HoyCommittee Member, present
TK
Councillor Tony KingCommittee Member, present
JP
Councillor Julie PattenCommittee Member, apologies
KS
Councillor Kewal Singh AthwalCommittee Member, present
CR
Councillor Carolyn RenwickCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
HB
Helen BarringtonOfficer, apologies, sent representative
CC
Carol CammissOfficer, in attendance

All 19 on the meeting page

On this subject at Derbyshire

Search all
  1. Safer Roads Fund Project A5012 Via Gellia, Cromford to NewhavenThis decision
  2. Safer Roads Fund Projects - A5012 ‘Via Gellia’ Cromford to NewhavenAgreed
  3. Safer Roads Fund Projects - A5004 ‘Long Hill’ Buxton to Whaley BridgeAgreed
  4. Safer Roads Fund Project A5004 Long Hill , Buxton To Whaley BridgeApproved

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies