RESOLVED to: 1) Accept the responses to the public consultation events held for the A5012 Via Gellia Safer Roads Fund (SRF) project and on-going consultation with statutory consultees; 2) Accept the scope of works recommended to be procured which may vary from those consulted upon and agreed with the Department for Transport (DfT) in December 2022; 3) Accept the strategy for procuring the works through the County’s internal Highway and Construction Services Team; 4) Accept the anticipated installation costs for each proposed safety interventions for the A5012 Via Gellia route; 5) Give authority for officers to work within the overall budget for the three SRF projects to a confirmed value of £6.798m by not implementing safety interventions that cannot be afforded; and 6) Accept the findings of the Equalities Impact Assessment for the Safer Roads Fund projects.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Safer Roads Fund Projects - A5012 ‘Via Gellia’ Cromford to Newhaven (Cabinet Member for Highways, Assets and Transport)
1. Divisions Affected
1.1Wirksworth and Dovedale.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To inform Cabinet of the responses to the public consultation events held for the A5012 Via Gellia Safer Roads Fund (SRF) project and on- going consultation with statutory consultees.
3.2To inform Cabinet of the scope of works recommended to be procured which may vary from those consulted upon and agreed with the Department for Transport (DfT) in December 2022.
3.3To inform Cabinet of the anticipated installation costs for each proposed safety interventions for the A5012 Via Gellia route. 3.4 To inform Cabinet of the strategy for procuring the works through the County’s internal Highway and Construction Services team.
3.5To give authority for officers to work within the overall budget for the three SRF projects to a confirmed value of £6.798m by not implementing safety interventions that cannot be afforded.
3.6To inform Cabinet of the findings of the Equalities Impact Assessment for the Safer Roads Fund projects.
4. Information and Analysis
4.1In its 2016 Autumn Statement, Government announced the creation of a £175 million Safer Roads Fund to improve the safety of the 50 highest risk roads in England. Three of these roads are in Derbyshire:
A619 - Baslow to Bakewell (Thirteen Bends) A5004 - Buxton to Whaley Bridge (Long Hill) and A5012 – Cromford to Newhaven (Via Gellia)
4.2Work on the A619 Baslow to Bakewell route has already been completed. Attention is now focused on progressing the work on the remaining SRF projects.
4.3Cabinet approved the acceptance of the grant funding from the Department for Transport (DfT) and to progress the Public Engagement Process in a report dated 8 September 2022 (Minute No. 155/22 refers). Cabinet also sought feedback on the public consultation together with the final scheme designs and procurement strategy before giving consent to install the proposed safety interventions. This report outlines the findings following the above actions.
4.4It should be noted that the original proposals sought by the DfT in 2018 have been reduced in scope as they could no longer be afforded within the SRF project budget. This is due to construction inflation exceeding the normal inflation rate over recent years and a slight overspend on the A619 SRF project.
4.5The County Council also undertook to underwrite any overspends to the SRF projects in 2018 when accepting the grant funding, but this too has been affected by overspends on its own capital construction projects such that funding is no longer available, the undertaking can longer be afforded and the reduction of contingency funds available in the Highways Capital programme which would have been used to underwrite any over-spend. 4.6 The DfT also agreed to remove the need for the County Council to underwrite any overspends allowing the Council instead to vary the safety interventions to be installed within the available budget. The DfT has also given the County Council autonomy as to how the grant funding is spent both in terms of the interventions to be installed and when moving funding between the two SRF projects should an overspend or underspend occur.
4.7The budget for the A5012 SRF project is £2.171m.
4.8The preliminary design of the safety interventions has been undertaken to determine their viability and anticipated installation cost.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.