Production of 2023-24 Revenue Budget

Noted Scrutiny 1 paper

Resources Scrutiny Committee noted this item on Thursday 1 December 2022. Below is the council's own wording, with the papers it was decided on.

Item24/22

Resolved

RESOLVED to (1) note the Revenue Budget Forecast Outturn for 2022-23 as at Quarter 1 (30 June 2022) ; (2) note that was likely to be a significant shortfall in the Revenue Budget 2023-24 based on currently known information; (3) note the ongoing work to identify further savings options, to reduce the 2023-24 Revenue Budget shortfall and therefore mitigate the use of one off reserves to deliver a balanced budget; and (4) note the a key announcements in the Autumn Statement 2022 relevant to Local Government.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Resources Scrutiny Committee

Purpose of the report

1.1To consult Members of the Improvement and Scrutiny Committee – Resources as part of the process towards production of the 2023-24 Revenue Budget, providing Members with an update of the Revenue Budget Forecast Outturn for 2022-23, an update on the projected funding and pressures in respect of the Revenue Budget 2023-24, based on currently known information, and a summary of the key announcements relevant to Local Government in the recent Autumn Statement 2022.

2 Information and Analysis

Background

2.1In setting the Revenue Budget in 2022-23, the Five-Year Financial Plan was updated, demonstrating that savings of £67m were required over the period of the Five-Year Financial Plan. In terms of the 2023-24 Revenue Budget, based on estimates at that time, savings of £11.114m had been identified to be delivered in 2023-24 in order to achieve a balanced budget. It was assumed that grant funding to the Council in 2023-24 would be cash-flat i.e., at 2022-23 levels, with a 2% Council Tax increase. Services pressures totalling approximately £19m were assumed for 2023-24, with a pay award of 2% estimated at a cost of £6.651m. The estimated Revenue Budget position as of February 2022 for 2023-24 is summarised in the table below.

1 Public

£m £m Expenditure Base budget b/f 601.250 Pay Award 6.651 Cost pressures 19.475 Additional interest receipts (2.182) Increase Risk Management Budget 1.856 Total Expenditure 627.050

Less Funding Business Rates (18.069) Government Grants (215.686) Council Tax (382.181) Total Funding (615.936) Savings Required (11.114)

2.2Since February 2022, the global economy has shifted dramatically, in response to events in Ukraine and rising energy costs, resulting in unprecedented inflation levels. Demand pressures on Council services have also continued to grow.

2.3Over the course of the Summer/Autumn 2022 departments have undertaken significant work in identifying new savings proposals and preparing details of revenue cost pressures, along with an update on Forecast Revenue Outturn 2022-23.

2.4The key announcements in the recent Autumn Statement, relevant to Local Government, are also set out in paragraphs 2.22 - 2.23 below. More details and Council-specific information are unlikely to be available until the Provisional Local Government Finance Settlement is announced, which is expected to be in the week commencing 19 December 2022.

Forecast Revenue Outturn 2022-23 Summary

2.5The Council’s forecast Revenue Outturn 2022-23 summary below was reported to Cabinet on 13 October 2022 and is as at Quarter 1 (30 June 2022). The Quarter 2 (30 September 2022) forecast will be reported to Cabinet on 8 December 2022.

2.6The forecast position is reported net of the impact of the ring-fenced Dedicated Schools Grant (DSG) of £389.554m and Public Health grant of £43.803m, other ring-fenced grants and income from other third parties and associated spend.

2 Public

2.7An overall Council overspend of £29.654m is forecast as at Quarter 1, after using £0.478m of un-ringfenced Department for Levelling Up Housing & Communities (DLUHC) Covid-19 general emergency grant funding brought forward from 2021-22. However, against this forecast, it is planned that the Council will use all, or some, of the balances on the Budget Management (all £10.000m), Covid-19 (£9.654m of £15.370m) and Inflation Earmarked Reserves (all £10.000m), to report a break-even position (net zero).

2.8Whilst use of earmarked reserves, in-year, will result in the Council reporting a break-even position, the impact of the unfunded pay offer for 2022-23, demand pressures and inflationary costs will need to be addressed as part of the budget setting process for 2023-24, as the effect will be an ongoing cost pressure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Production of 2023-24 Revenue BudgetReport 109 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
SS
Councillor Stuart SwannChairman, present
JB
Councillor James BarronVice-Chairman, present
RA
Councillor Ron AshtonCommittee Member, apologies
JD
Councillor Joan DixonCommittee Member, present
MF
Councillor Mark FosterCommittee Member, present
AH
Councillor Anne-Frances HayesCommittee Member, present
JI
Councillor Jean InnesCommittee Member, present
DM
Councillor David MullerCommittee Member, present
DM
Councillor Dermot MurphyCommittee Member, present
IW
Ivan WaltersClerk, expected
PH
Peter HandfordOfficer, expected
EC
Emma CrapperOfficer, expected

All 16 on the meeting page

On this subject at Derbyshire

Search all
  1. Production of 2023-24 Revenue BudgetThis decision
  2. Production of Revenue BudgetDecided
  3. Production of 2022-23 Revenue BudgetNoted

More from Derbyshire Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
22 Jan 2024 Budget Savings Proposals 2024/25 to 2028/29RESOLVED (1) to note the financial context and approach to budget setting for 2024/25. (2) to note the possible optio... Noted Open
14 Dec 2023 Production of the 2024/25 BudgetRESOLVED to note: 1) The Revenue Budget Forecast Outturn for 2023-24, as at Quarter 2 (30 September 2023); 2) That th... Noted Open
1 Dec 2022 Learning and Development - Progress Strategy UpdateRESOLVED (1) to note the work the to date in implementing the Learning and Development Strategy, and (2) to receive a... Noted Open
1 Dec 2022 Channel Shift UpdateRESOLVED to note the progress of the Channel Shift programme; Noted Open
1 Dec 2022 Capital Budget Monitoring & Forecast as at Quarter 1 2022-23RESOLVED to note the current position on the monitoring of Capital schemes as at 30 June 2022 (Quarter 1) Noted Open