Resolved
RESOLVED to note the current position on the monitoring of Capital schemes as at 30 June 2022 (Quarter 1)
Resources Scrutiny Committee noted this item on Thursday 1 December 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the current position on the monitoring of Capital schemes as at 30 June 2022 (Quarter 1)
Agenda Item FOR PUBLICATION
DERBYSHIRE COUNTY COUNCIL
IMPROVEMENT AND SCRUTINY COMMITTEE - RESOURCES
1 December 2022
Report of the Director of Finance & ICT
Capital budget monitoring and forecast as at Quarter 1 2022-23 (Corporate Services and Budget)
1. Purpose
1.1To inform Members of the Improvement and Scrutiny Committee – Resources of the Capital budget monitoring position as at 30 June 2022.
2. Information and Analysis
2.1The report includes Cabinet approved schemes that have been active during this financial year, including schemes closed in year. Each scheme has a nominated budget holder who is responsible for ensuring the scheme stays within budget, and who provides the projected spend figures. The schemes have been approved over several previous years in addition to the current year. Monitoring Reports have been considered by Cabinet in accordance with the Budget Monitoring Policy and Financial Regulations.
2.2The 2022-23 capital programme is £101.896m, approved adjustments to this figure reduced this to £95.757m. The budget for active schemes being monitored this year total £624.846m, this reduction reflects the projects closed since 1 April 2022. There is a forecast underspend of £5.309m over the life of these projects (see Appendix 2).
1 CONTROLLED 2.3 Adult Social Care & Health - projected underspend of £0.997m
Adult Care has a budget of £94.538m comprised of 59 schemes. Five schemes account for 76% of the budget These are summarised in the table and narrative below.
Major Schemes £m Disabled Adaptations 2019 - 2022 20.583 Belper Integrated Specialist Facilities Centre 15.613 Bennerley Avenue – Care Home 15.000 Darley Dale Specialist Community Care Centre 10.520 Heanor Specialist Community Care Centre 9.750
Disabled Adaptations The Disabled Adaptations schemes are the currently open programmes which relate to aids and adaptations installed in resident’s own homes so they may remain as independent as possible. They will be fully financed from borrowing together with contributions from clients and district councils. Currently the spend is forecast to be under budget by £0.617m. With approval this will be used to fund schemes in future years.
The Belper Integrated Specialist Facilities Centre The Belper Centre offers accommodation for up to 40 older persons and includes a library on site. The Care Home opened in June 2020 and the residents from Ada Belfield moved into the new accommodation during September 2020. The risk of asbestos contamination reported to Cabinet in previous monitoring reports remains and the cost of this is currently estimated to be in the region of £1.500m. Legal have now advised that pursuing the asbestos contamination claim is not viable. The overspend has been covered by using underspends from other projects, the overall spend is projected to be £15.613m. Although the defects period has now expired some remedial works relating to flooring and doors are still underway, therefore the final certificate has not yet been signed off.
Bennerley Avenue - Care Home Construction for this commenced in February 2021 with final completion estimated to be autumn 2023. The timely completion is subject to the finalising of a legal easement - pressure is being applied to achieve this. The Home will replace the nearby Hazelwood Care home and will have 30 general needs beds and 10 Community support beds. The budget and forecast expenditure are £15.000m. The Authority is still seeking a partner to develop an Extra Care Home on the same site.
2 CONTROLLED Specialist Care Centres These provide care for physically frail, elderly clients with dementia:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring & Forecast as at Quarter 1 2022-23Report | 166 KB | DownloadRead as text |
Follow Resources Scrutiny Committee at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jan 2024 | Budget Savings Proposals 2024/25 to 2028/29RESOLVED (1) to note the financial context and approach to budget setting for 2024/25. (2) to note the possible optio... | Noted | Open |
| 14 Dec 2023 | Production of the 2024/25 BudgetRESOLVED to note: 1) The Revenue Budget Forecast Outturn for 2023-24, as at Quarter 2 (30 September 2023); 2) That th... | Noted | Open |
| 1 Dec 2022 | Learning and Development - Progress Strategy UpdateRESOLVED (1) to note the work the to date in implementing the Learning and Development Strategy, and (2) to receive a... | Noted | Open |
| 1 Dec 2022 | Channel Shift UpdateRESOLVED to note the progress of the Channel Shift programme; | Noted | Open |
| 1 Dec 2022 | Production of 2023-24 Revenue BudgetRESOLVED to (1) note the Revenue Budget Forecast Outturn for 2022-23 as at Quarter 1 (30 June 2022) ; (2) note that w... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.