RESOLVED that the Committee notes the update on the Integrated Rail Plan and has provided comments for consideration in on-going discussion with HS2 Ltd and Department for Transport. On behalf of the Committee, the Chairman thanked [name removed] for his most informative update.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
1.1To provide the Committee with an update on the Integrated Rail Plan and support wider discussion on the implications of IRP for Derbyshire.
2. Information and Analysis
2.1On 18 November 2021, the Integrated Rail Plan (IRP) for the North and Midlands was published by the Department for Transport (DfT). The IRP has been devised to review the principal rail investment proposals in the Midlands and the North, High Speed 2 (HS2), Northern Powerhouse Rail (NPR) and Midlands Engine Rail to ensure they were coordinated, balanced and sequenced to meet the Government’s overarching objectives in an affordable and value-for-money manner. As such, the review was not intended to set out the entirety of the rail programme for the North and Midlands (e.g. not include projects brought forward through the Restoring Your Railway programme).
1.2From a Derbyshire perspective the key elements of the IRP were:
1) A new High Speed line from Birmingham to East Midlands Parkway The proposed High Speed 2 eastern leg from Birmingham to Leeds is proposed has been amended through the IRP and now is proposed only to go as far north as the existing East Midlands Parkway station on the Midland Main Line (MML). The previously proposed route through Long Eaton to the planned gateway station at Toton and along the eastern side of Derbyshire adjacent the M1 to the boundary with South Yorkshire and via the spur from Hilcote to Clay Cross has been effectively cancelled.
Work on the new line is anticipated to start in the late 2030s and be completed in the mid-2040s.
2) High Speed service north to Leeds. How HS2 trains will serve Leeds and destinations further north is to be resolved by £100m study to be undertaken by Network Rail. This is likely to consider a number of options, including upgrading the existing Erewash Valley and Barrow Hill lines through Derbyshire to accommodate HS2 services. There is no published date for the start or completion of this study but it is expected to take two years to finish. The safeguarding of land that has been put in place to protect the old HS2 route north of East Midlands Parkway, including the proposed depot site at Staveley, will remain in place until the study is completed. There is, however, no budget identified in the IRP to deliver HS2 services further north so much remains to be resolved.
3) Toton station A new local train station at Toton (the previously planned East Midlands HS2 hub station may still be delivered, subject to 50% of the cost being provided by local e.g. linked to local site development. There is also commitment to accelerate plans for an East Midlands Development Delivery Vehicle to regenerate the three large opportunity sites in the area, including Toton itself and another at Ratcliffe on Soar adjacent the East Midlands Parkway station.
4) Electrification of the Midland Main Line The existing Midland Main Line is proposed to be electrified along its whole length from the current end of the overhead power lines at Kettering through to Leicester, Nottingham, Derby, Chesterfield and Sheffield. Work on this project will begin in the mid-2020s and be completed in the early 2030s.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.