That the Committee notes: a) How Derbyshire County Council currently process Traffic Regulation Orders (TROs); b) The delivery of TRO schemes over the past five-year period; c) The existing TRO processing backlog; d) Progress of the project to reduce the TRO backlog; e) Projected project completion timescales; and f) Objectives of the project going forward, and the risks associated to delivery of the project goals.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
1.1This Project Progress Report provides an overview of:
• How Derbyshire County Council (DCC) currently process Traffic Regulation Orders (TROs) • The delivery of TRO schemes over the past five-year period • The existing TRO processing backlog • Progress of the project to reduce the TRO backlog • Projected project completion timescales • Objectives of the project going forward, and the risks associated to delivery of the project goals.
2. Information and Analysis
2.1Project Objectives • Reduce TRO Backlog to manageable levels – manageable levels are set at 13 TRO’s being processed or awaiting processing; this is based on the average number of TRO’s completed over the last four-year period • Process TRO’s within reasonable timeframe – reasonable timeframe is within 18 months. • Share information with Derbyshire Highways Programme to inform shaping of the new service to account for additional resources required. • Gain Capitalised funding for TRO processing and construction by 24/25 • Make efficiency improvements to the TRO process
2.2Background - Traffic Regulation Orders, Types and Processes
TRO’s are legal documents that restrict or prohibit the use of the highway network, in line with The Road Traffic Regulation Act 1984. They help us to manage the highway network for all road users, including pedestrians, and they aim to improve road safety and access to facilities. Examples of schemes that require a TRO include:
• Speed limits • On-street parking restrictions • Weight limits • One-way streets and banned turns • Prohibition of Driving
Improvement schemes can have an ‘all in’ cost of thousands, to tens of thousands, of pounds depending on the size, complexity and level of physical works required. TRO’s follow a statutory process and are a legal document. Communities are often surprised at the length of time it can take to progress a scheme. It is the Authority's responsibility to make sure a fair process is undertaken in determining a TRO, and key to that process is robust consultation. TRO consultations, combined with statutory processes can mean a typical and often simple TRO can take between 12 and 18 months to deliver. Complex or contentious TROs can take longer. A typical TRO process includes the following:
• Feasibility and priority assessment consideration • Proposed scheme design • Informal consultation (21 days minimum for comments to be received) • Consideration of all comments received • Amendments and preparation for statutory processes • Statutory consultation (22 days minimum for comments to be received) • Consideration of all comments received • Draft all relevant legal documentation ready for formal advertising of the scheme in the media and on the DCC website. • Consideration of objections (and attempts to resolve them) • Detailed report or TRO Committed (if unresolved objections) • Making of the TRO including sealing • Implementation of the TRO (making physical changes on site)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.