RESOLVED to: 1) Approve the new Capital Starts Programme as set out in Appendix Two of the report and approve the procurement and award of contracts which support the delivery of the Capital Programme. All contract awards will then be subject to approval by Executive Directors (via an Executive Director Report) under the relevant Departmental Scheme of Delegation; 2) Approve the detailed Planned Asset Maintenance Programme for 2024-25 as set out in Appendix Three of the report; 3) Adopt the Treasury Management Strategy for 2024-25 as set out in Appendix Four of the report; 4) Adopt the Investment Strategy for 2024-25 as set out in Appendix Five of the report; 5) Adopt the Capital Strategy for 2024-25 as set out in Appendix Six of the report; 6) Adopt the Minimum Revenue Provision Statement for 2024-25 as set out in Appendix Seven of the report; and 7) Adopt the application of financing up to 4% of disposal costs associated with land from capital receipts as set out in paragraph 3.7 of the report.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
2.1To obtain approval for proposals relating to the Capital Starts Programme and the Treasury Management, Investment and Capital Strategies.
2.2This report should be read alongside the following reports to this Council meeting: the Reserves Position and Reserves Policy Report, the Budget Consultation Results Report for 2024-25 and the Revenue Budget Report 2024-25.
3 Information and Analysis
Capital Programme
3.1In line with previous years, the proposed new Capital Starts Programme has been evaluated and it is recommended to proceed with new borrowing of £31.248m for new projects commencing over the three years 2024-25 to 2026-27. New borrowing of £14.991m will be required in 2024-25, £8.816m in 2025-26 and £7.441m in 2026-27. The detailed proposals are set out in Appendix Two of this Report.
1 Public
3.2A detailed list of the Planned Asset Maintenance Programme of £6.000m for 2024-25 to 2026-27, which includes £3.000m of planned maintenance to be scheduled in 2025-26 and 2026-27, is set out in Appendix Three of this Report.
Treasury Management and Investment Strategies
3.3The Treasury Management Strategy Report for 2024-25 (Appendix Four) sets out the Council’s management of its cash flow, borrowing and investments and the management of its associated risks.
3.4The Investment Strategy Report for 2024-25 (Appendix Five) deals with the management of the Council’s balances and reserves, managing the balance between risk and return.
Capital Strategy and Capital Financing
3.5The Capital Strategy for 2024-25 (Appendix Six) provides a high-level overview of how capital expenditure and capital financing contribute to the provision of local public services.
3.6The Minimum Revenue Provision Statement for 2024-25 (Appendix Seven) sets out how the amount to be put aside to repay debt used to finance capital expenditure is to be calculated.
3.7Historically the Council has funded all costs relating to the disposal of assets from revenue budgets. The 2003 Capital Finance Regulations for authorities in England and Wales, allows the costs of, or costs incidental to, a disposal of an interest in land to be financed from the capital receipt (provided that for non-housing land these costs do not exceed 4% of the capital receipt arising from the disposal). It is intended that from 1 April 2024, eligible disposal costs relating to land will be funded from the associated capital receipt (once realised), in accordance with the Capital Finance Regulations 2003 and the CIPFA practitioners guidance for capital finance in local government.
3.8The Council and Derby City Council are engaged in a project to develop a New Waste Treatment Facility (NWTF) in Sinfin, Derby, to deal with waste that residents in Derby and Derbyshire do not recycle. As part of the settlement agreed by Cabinet in July 2023, Cabinet approved a payment of £56.930m which reflected the Council’s share of the ‘estimated fair value’ (EFV) of the plant. This payment is a necessary cost attributable to bringing the waste treatment facility into use, and therefore it is proposed that this expenditure is capitalised in 2023-24.
2 Public
3.9At the time of the settlement the funding had been set aside in Earmarked Reserves. In order to support the budget management of the Council, it is now proposed that this expenditure is capitalised in 2023-24. This will mean that the expenditure is funded from borrowing, which will result in an increase in the forecast Capital Financing Costs in future years.
Consultation
4.1No consultation is required.
Alternative options considered
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.